90 individual off-grid systems Chile by ENEL
The challenge
It was during the development of South America's first geothermal power plant "Cerro Pabellón", inaugurated in September 2017, situated in the Antofagasta region of Chile that Enel first came in contact with the inhabitants of Toconce. Committed to improve the quality of life in remote areas by clever electrification, Enel took on the challenge of finding a solution for 90 of the village's households.
The solution
By implementing a distributed energy solution, each home is equipped with its own photovoltaic energy system, complete with PV panels on the roof and an integrated cabinet containing an inverter/charger, an MPPT solar charge controller and a lithium battery. With individual systems the households can manage their energy consumption autonomously.
The electrical cabinets are mounted in accordance with the Chilean electrical standards and access to the cabinets is restricted. The households with installed solar systems have received a detailed training on how to use and maintain their installations.
Why Studer
This village is installed at 3'310 meter above sea level and any equipment installed there must support both hot and cold extreme temperatures. Studer products were chosen for their demonstrated reliable performance under extreme conditions.
Studer products also offer a unique versatility in programming, and are compatible with many types of batteries, in this case lithium-ion batteries from SimpliPhi.
Project outcome
The inhabitants of Toconce have now access to electricity in their homes 24/7. Their quality of life has greatly improved with their use of household electronics such as refrigerators, washing machines and lights.
Their previous use of noisy, polluting diesel generators have been replaced by clean, green energy giving them the opportunity to grow and/or start new businesses.
System components
Responsible company
Enel Green Power Chile and STC Sunbelt
The challenge
It was during the development of South America's first geothermal power plant "Cerro Pabellón", inaugurated in September 2017, situated in the Antofagasta region of Chile that Enel first came in contact with the inhabitants of Toconce. Committed to improve the quality of life in remote areas by clever electrification, Enel took on the challenge of finding a solution for 90 of the village's households.
The solution
By implementing a distributed energy solution, each home is equipped with its own photovoltaic energy system, complete with PV panels on the roof and an integrated cabinet containing an inverter/charger, an MPPT solar charge controller and a lithium battery. With individual systems the households can manage their energy consumption autonomously.
The electrical cabinets are mounted in accordance with the Chilean electrical standards and access to the cabinets is restricted. The households with installed solar systems have received a detailed training on how to use and maintain their installations.
Why Studer
This village is installed at 3'310 meter above sea level and any equipment installed there must support both hot and cold extreme temperatures. Studer products were chosen for their demonstrated reliable performance under extreme conditions.
Studer products also offer a unique versatility in programming, and are compatible with many types of batteries, in this case lithium-ion batteries from SimpliPhi.
Project outcome
The inhabitants of Toconce have now access to electricity in their homes 24/7. Their quality of life has greatly improved with their use of household electronics such as refrigerators, washing machines and lights.
Their previous use of noisy, polluting diesel generators have been replaced by clean, green energy giving them the opportunity to grow and/or start new businesses.
Argentina: Agroindustria en Cabos
El Proyecto
La Solución
Para la generación de energía eléctrica se instaló un arreglo fotovoltaico de 8kWp y para acumular lo generado se montaron tres bancos de batería de ciclo profundo TROJAN, los cuales permiten almacenar 675 Ah@C20 a 48V, sumado a equipos de regulación, control y generación de STUDER.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones en zonas remotas sumado a su flexibilidad, robustez y garantía de 10 años que constituyen las principales razones para su elección.
Resultado del Proyecto
La ejecución del proyecto posibilitó la instalación y puesta en funcionamiento de la nueva actividad comercial de la empresa Agroindustrial, cumpliendo con todas las Normas exigidas por el Servicio Nacional de Sanidad y Calidad Agroalimentaria que es un organismo sanitario del estado argentino encargado sobre todo de la fiscalización y certificación de los productos.
System components
1 x Inversor Cargador de XTH 8000-48 STUDER
1 x Controladores VT-80 STUDER
1 x Controladores VT-65 STUDER
30 x Paneles Solares JINKO Solar 265Wp
32 x Baterías T-105 TROJAN
Responsible company
Sungreen
El Proyecto
La Solución
Para la generación de energía eléctrica se instaló un arreglo fotovoltaico de 8kWp y para acumular lo generado se montaron tres bancos de batería de ciclo profundo TROJAN, los cuales permiten almacenar 675 Ah@C20 a 48V, sumado a equipos de regulación, control y generación de STUDER.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones en zonas remotas sumado a su flexibilidad, robustez y garantía de 10 años que constituyen las principales razones para su elección.
Resultado del Proyecto
La ejecución del proyecto posibilitó la instalación y puesta en funcionamiento de la nueva actividad comercial de la empresa Agroindustrial, cumpliendo con todas las Normas exigidas por el Servicio Nacional de Sanidad y Calidad Agroalimentaria que es un organismo sanitario del estado argentino encargado sobre todo de la fiscalización y certificación de los productos.
Argentina: Electrificación rural, Pueblo Olaroz Chico
El Proyecto
Olaroz Chico es una pequeña localidad del departamento de Suques, en la provincia de Jujuy. Se encuentra en la puna Jujeña a una altura de 4165 m.s.n.m. El abastecimiento de energía eléctrica utilizado era mediante un grupo electrógeno, lo que implicaba disturbio sonoro y contaminación, además el abastecimiento de energía era un máximo de 10 horas por día. Hoy Olazor Chico es el primer pueblo solar de Argentina con abastecimiento de baterías de litio.
Para la generación de energía, se cuenta ahora, con un parque solar con paneles de 275Wp. Estos entregan una energía que luego es regulada para realizar la carga de los bancos de batería por 3 reguladores MPPT STUDER modelo VarioString VS-120.
Para la alimentación de consumos se utilizan 7 inversores de la marca STUDER con una capacidad 8kVA por equipo para consumo de las viviendas y 2 Inversores QMax de 4kVA cada uno, en configuración inversor/cargador colgados a la salida. Estos inversores, están configurados de manera tal que durante el día funcionan en modo cargador (bypass), cargando las baterías de litio, y a la noche el usuario los pasa a modo inversor y alimenta las luminarias del pueblo mediante las mismas.
Ver video aquí:
https://www.youtube.com/watch?v=O_DwB9iiHzs
https://www.youtube.com/watch?v=jcHrFSnVUKY
La solucíon
El sistema de autoabastecimiento de energía renovable solar fue diseñado en conjunto por los ingenieros de EJESA, QMax y VZH con financiamiento y gestión del Gobierno de Jujuy. Para lograr esto, se opta por la utilización de 7 inversores STUDER de 8kVA cada uno, 2 inversores cargadores QMax de 4 kVA para la alimentación de los consumos, 3 reguladores STUDER VarioString de 120A por unidad y un parque solar que consta de 430 Paneles y 5 bancos de baterías de la marca Autobat y Vision.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones remotas que sumado a su flexibilidad, robustez y garantía constituyen las principales razones para su elección.
Además está sobradamente comprobada la fiabilidad en trabajos a más de 4000 m.s.n.m. donde otros fabricantes no dan garantía, y STUDER ofrece 10 años.
Resultado del Proyecto
La ejecución del proyecto permitió la alimentación sin interrupciones de la totalidad del pueblo durante las 24hs del día con energía solar sin necesidad de encender el grupo electrógeno.
System components
7 x Inversor/cargador STUDER XTH 8000-48
2 x Inversor Qmax QM-4048SP-C
3 x Reguladores MPPT VarioString VS-120
48 x Baterías AUTOBAT 1375Ah en C100
48 x Baterías AUTOBAT 3000Ah en C100
6 x Módulos Litio 5kW Vision
430 x Paneles Solares Yingli Solar 275Wp
Responsible company
QMAX
El Proyecto
Olaroz Chico es una pequeña localidad del departamento de Suques, en la provincia de Jujuy. Se encuentra en la puna Jujeña a una altura de 4165 m.s.n.m. El abastecimiento de energía eléctrica utilizado era mediante un grupo electrógeno, lo que implicaba disturbio sonoro y contaminación, además el abastecimiento de energía era un máximo de 10 horas por día. Hoy Olazor Chico es el primer pueblo solar de Argentina con abastecimiento de baterías de litio.
Para la generación de energía, se cuenta ahora, con un parque solar con paneles de 275Wp. Estos entregan una energía que luego es regulada para realizar la carga de los bancos de batería por 3 reguladores MPPT STUDER modelo VarioString VS-120.
Para la alimentación de consumos se utilizan 7 inversores de la marca STUDER con una capacidad 8kVA por equipo para consumo de las viviendas y 2 Inversores QMax de 4kVA cada uno, en configuración inversor/cargador colgados a la salida. Estos inversores, están configurados de manera tal que durante el día funcionan en modo cargador (bypass), cargando las baterías de litio, y a la noche el usuario los pasa a modo inversor y alimenta las luminarias del pueblo mediante las mismas.
Ver video aquí:
https://www.youtube.com/watch?v=O_DwB9iiHzs
https://www.youtube.com/watch?v=jcHrFSnVUKY
La solucíon
El sistema de autoabastecimiento de energía renovable solar fue diseñado en conjunto por los ingenieros de EJESA, QMax y VZH con financiamiento y gestión del Gobierno de Jujuy. Para lograr esto, se opta por la utilización de 7 inversores STUDER de 8kVA cada uno, 2 inversores cargadores QMax de 4 kVA para la alimentación de los consumos, 3 reguladores STUDER VarioString de 120A por unidad y un parque solar que consta de 430 Paneles y 5 bancos de baterías de la marca Autobat y Vision.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones remotas que sumado a su flexibilidad, robustez y garantía constituyen las principales razones para su elección.
Además está sobradamente comprobada la fiabilidad en trabajos a más de 4000 m.s.n.m. donde otros fabricantes no dan garantía, y STUDER ofrece 10 años.
Resultado del Proyecto
La ejecución del proyecto permitió la alimentación sin interrupciones de la totalidad del pueblo durante las 24hs del día con energía solar sin necesidad de encender el grupo electrógeno.
Argentina: Vivienda Aislada
El Proyecto
- Construcción en una sola planta con sistema de platea de concreto aislado con 40 cm de tierra arcillosa aislada con film de polietileno y pilotes de refuerzo.
- Paredes dobles de ladrillos cerámicos con cámara de aire.
- Techo de chapa aislado con espuma ignífuga de 40 mm de espesor.
- Cielorrasos de yeso para disminuir los volúmenes habitables con el objeto de minimizar la energía de climatización.
- Aberturas de Plástico doble vidrio y doble cierre.
- Sistema de Climatización con equipos inverter de bajo consumo eléctrico.
La Solución
La idea ha sido construir una casa totalmente eficiente y autónoma con independencia de la red eléctrica. La idea es fomentar el funcionamiento de las energías renovables con acumulación.
La zona donde está la casa, sufre de muchos cortes de luz y de oscilaciones en el voltaje de la red eléctrica que varían desde 180Vac hasta 250Vac. Esto es un problema para la electrónica de los equipos eléctricos que hay en la casa, reduciendo su vida de funcionamiento y aumentando sus costes
Por Qué STUDER
STUDER garantiza una tensión estable alargando la vida de todos los equipos electrónicos de alta calidad. El sistema siempre garantiza un funcionamiento, y cuando hay cortes de luz, las casas vecinas alimentadas por la red eléctrica sufren las consecuencias, mientras la casa alimentada a través de paneles fotovoltaicos y STUDER, sigue con su funcionamiento normal, evitando problemas y pérdidas materiales.
Resultado del Proyecto
El resultado del proyecto es tener una casa vivienda, aislada de la red eléctrica y que es autosuficiente, en el que la inversión inicial se ve compensada, amortizándose a lo largo de años sin tener que pagar a la compañía eléctrica por el uso de la energía. Además de ahorrarse todos los problemas de calidad de suministro y cortes de luz.
System components
2 x Inversor/Cargador XTH 8000-48 STUDER
2 x Regulador MPPT VS-120 STUDER
1 x RCC-02 STUDER
30 x Paneles Solares de 280Wp Amerisolar
2 x bancos de 24 elementos de baterías tubulares BAE 12 PVS 1800,1740 Ah en C100
1 x Caseta prefabricada para albergar las baterías y los equipos STUDER
Responsible company
VZH and QMAX
El Proyecto
- Construcción en una sola planta con sistema de platea de concreto aislado con 40 cm de tierra arcillosa aislada con film de polietileno y pilotes de refuerzo.
- Paredes dobles de ladrillos cerámicos con cámara de aire.
- Techo de chapa aislado con espuma ignífuga de 40 mm de espesor.
- Cielorrasos de yeso para disminuir los volúmenes habitables con el objeto de minimizar la energía de climatización.
- Aberturas de Plástico doble vidrio y doble cierre.
- Sistema de Climatización con equipos inverter de bajo consumo eléctrico.
La Solución
La idea ha sido construir una casa totalmente eficiente y autónoma con independencia de la red eléctrica. La idea es fomentar el funcionamiento de las energías renovables con acumulación.
La zona donde está la casa, sufre de muchos cortes de luz y de oscilaciones en el voltaje de la red eléctrica que varían desde 180Vac hasta 250Vac. Esto es un problema para la electrónica de los equipos eléctricos que hay en la casa, reduciendo su vida de funcionamiento y aumentando sus costes
Por Qué STUDER
STUDER garantiza una tensión estable alargando la vida de todos los equipos electrónicos de alta calidad. El sistema siempre garantiza un funcionamiento, y cuando hay cortes de luz, las casas vecinas alimentadas por la red eléctrica sufren las consecuencias, mientras la casa alimentada a través de paneles fotovoltaicos y STUDER, sigue con su funcionamiento normal, evitando problemas y pérdidas materiales.
Resultado del Proyecto
El resultado del proyecto es tener una casa vivienda, aislada de la red eléctrica y que es autosuficiente, en el que la inversión inicial se ve compensada, amortizándose a lo largo de años sin tener que pagar a la compañía eléctrica por el uso de la energía. Además de ahorrarse todos los problemas de calidad de suministro y cortes de luz.
Australia: Off-grid wastewater system Wattamolla Beach
The challenge
Wattamolla beach, lagoon, and picnic area, is part of the Royal National Park, established in 1879 and the second oldest National Park in the world. The popular site can attract up to 8000 people per day in peak periods putting a strain on the national park's wastewater system requiring up to 90kWh per day. It is difficult to supply such high power demands in a site where trees are protected and solar exposure is limited.
The solution
The NSW National Parks and Wildlife Service decided to purchase a system with 19.2kW solar array and 250kWh battery bank to service the many visitors to the Wattamolla beach, lagoon, and picnic area. The system also has 12kW of 3-phase Xtender capacity and 21kW of VarioString MPPT capacity. The treated wastewater is pumped 6km away to the irrigation area.
During off-peak season it has sufficient energy to support the wastewater system by itself. During the summer season when the number of visitors increases substantially, the Studer Xtender inverter/chargers bring in the diesel genset when required to ensure maximum battery health and fail-proof operation.
Why Studer
For this important site it was essential to use products with proven track records of reliability. The Studer products also present a highly customisable architecture allowing precise automatic operation, the ability to wire the large array in high-voltage strings, and for the comprehensive data logging capability inbuilt into the RCC-02 display/control.
Project outcome
The wastewater system requires power 24 hours a day and previously the only alternative to obtain a constant supply at this remote site was by generator. Aside from the very high cost of fuel and delivery, the associated noise and pollution went very much against the beliefs of the organisation.
By maximising coverage of the loads by solar, fuel use, servicing requirements, and delivery inconvenience has been reduced, and the ecological focus of the organisations has been proven and sustained.
System components
60 x Suntellite 320W Solar Modules
48 x Sonnenschein 2600Ah 2V A600 OPZV Gel Batteries
3 x STUDER XTM 4000-48 Xtender Inverter/Charger
3 x STUDER VarioString VS-120 7kW MPPT
MicroSolar Tilt Adjusted Frame
Responsible company
Solar Power Australia
The challenge
Wattamolla beach, lagoon, and picnic area, is part of the Royal National Park, established in 1879 and the second oldest National Park in the world. The popular site can attract up to 8000 people per day in peak periods putting a strain on the national park's wastewater system requiring up to 90kWh per day. It is difficult to supply such high power demands in a site where trees are protected and solar exposure is limited.
The solution
The NSW National Parks and Wildlife Service decided to purchase a system with 19.2kW solar array and 250kWh battery bank to service the many visitors to the Wattamolla beach, lagoon, and picnic area. The system also has 12kW of 3-phase Xtender capacity and 21kW of VarioString MPPT capacity. The treated wastewater is pumped 6km away to the irrigation area.
During off-peak season it has sufficient energy to support the wastewater system by itself. During the summer season when the number of visitors increases substantially, the Studer Xtender inverter/chargers bring in the diesel genset when required to ensure maximum battery health and fail-proof operation.
Why Studer
For this important site it was essential to use products with proven track records of reliability. The Studer products also present a highly customisable architecture allowing precise automatic operation, the ability to wire the large array in high-voltage strings, and for the comprehensive data logging capability inbuilt into the RCC-02 display/control.
Project outcome
The wastewater system requires power 24 hours a day and previously the only alternative to obtain a constant supply at this remote site was by generator. Aside from the very high cost of fuel and delivery, the associated noise and pollution went very much against the beliefs of the organisation.
By maximising coverage of the loads by solar, fuel use, servicing requirements, and delivery inconvenience has been reduced, and the ecological focus of the organisations has been proven and sustained.
Barbados: Atmospheric Water plant
The Challenge
EcoSkyWater is a company that produces pure drinkingwater fromthe air using ZeroMassWater Sources units. The owner wanted to develop a completely ecofriendly production plant, so he wanted the power to be supplied by renewable energy. Wewere given the challenges of provide power for this plant, which was needed to be completely autonomous, but reliable and stable.
The Solution
EnSmart of course knew this was possible with Studer inverters and charge controllers. The plant started with a power requirement that was not fully known at the time. The initial requirementwas for a splitphase system to power air condition units, lights, office equipment, water pumps and a small bottling machine and bottle caping machine. The plant started with two XTM4000-48-01 inverters, three VS-70 charge controllers, four 5KWH Soltaro Lithium batteries and 24x 330W panels. Once the plant was operational the demands on the system grew quickly as the owner evolved the product offering and there was a requirement for three phases. This was not a problem for Studer Xtender series, so another XTM4000-48-01 was added and we reconfigured the system. However, the plant power requirement continued to growand started to push the XTM4000s to the limit. The owner wanted to upgrade but did not want to lose his investment in the XTM4000s, so the solution was to add two XTH6000-48-01, one for L1, one for L2 and combine the existing 3x XTM4000-48-01 in parallel to work on L3. EnSmart also added more panels 12x 400W.
Why STUDER
EnSmart wanted a flexible, robust, reliable inverter as our premium inverter when we started the business as off-grid specialist. After reviewing and tested several inverters we quickly realized that Studer was the best grid-interactive inverter on the market at the time. Studer's Smart-boost capabilitywas also a feature thatwas a game changer for us and the product offering to our clients. Studer quality and attention to the system load handling made it possible to provide power to our clients' entire house or business with a mix of load types, AC units, air compressors even welding equipment with the confidence that it would be reliable and stable.
Project Outcome
The client is happy with the solution. It runs his plant every day and produces power for a variety of functions, while keeping with his ecofriendly philosophy. The plant maintains a zerocarbon footprint and operates autonomously from the grid. ECO SKYWATER is currently expanding to other countries and has formatted their product into an all-encompassing offer in which they are looking to include Studer.
System components
2 Xtender XTH 6000-48-01 inverters
3 Xtender XTM 4000-48-01 inverters
3 VarioString VS-70 Charge Controllers
4 Soltaro/Wa! sonic 5KWH LiFePo4 ba! eries
24 Amerisolar AS-CP330 - 330W
12 Trina Solar TSM-DEG15M.20(II) - 400W
1 RCC, 1 Xcom LAN and 1 Xcom-CAN
Responsible company
EnSmart Inc
The Challenge
EcoSkyWater is a company that produces pure drinkingwater fromthe air using ZeroMassWater Sources units. The owner wanted to develop a completely ecofriendly production plant, so he wanted the power to be supplied by renewable energy. Wewere given the challenges of provide power for this plant, which was needed to be completely autonomous, but reliable and stable.
The Solution
EnSmart of course knew this was possible with Studer inverters and charge controllers. The plant started with a power requirement that was not fully known at the time. The initial requirementwas for a splitphase system to power air condition units, lights, office equipment, water pumps and a small bottling machine and bottle caping machine. The plant started with two XTM4000-48-01 inverters, three VS-70 charge controllers, four 5KWH Soltaro Lithium batteries and 24x 330W panels. Once the plant was operational the demands on the system grew quickly as the owner evolved the product offering and there was a requirement for three phases. This was not a problem for Studer Xtender series, so another XTM4000-48-01 was added and we reconfigured the system. However, the plant power requirement continued to growand started to push the XTM4000s to the limit. The owner wanted to upgrade but did not want to lose his investment in the XTM4000s, so the solution was to add two XTH6000-48-01, one for L1, one for L2 and combine the existing 3x XTM4000-48-01 in parallel to work on L3. EnSmart also added more panels 12x 400W.
Why STUDER
EnSmart wanted a flexible, robust, reliable inverter as our premium inverter when we started the business as off-grid specialist. After reviewing and tested several inverters we quickly realized that Studer was the best grid-interactive inverter on the market at the time. Studer's Smart-boost capabilitywas also a feature thatwas a game changer for us and the product offering to our clients. Studer quality and attention to the system load handling made it possible to provide power to our clients' entire house or business with a mix of load types, AC units, air compressors even welding equipment with the confidence that it would be reliable and stable.
Project Outcome
The client is happy with the solution. It runs his plant every day and produces power for a variety of functions, while keeping with his ecofriendly philosophy. The plant maintains a zerocarbon footprint and operates autonomously from the grid. ECO SKYWATER is currently expanding to other countries and has formatted their product into an all-encompassing offer in which they are looking to include Studer.
Bolivia: Sitios nodos rurales
El Proyecto
Dentro del programa de expansión de su red de fibra óptica, VIVA (NUEVATEL PCS DE BOLIVIA S.A.), contempló el tendido de más de 1000 km de Fibra Óptica, uniendo distintos poblados rurales del Departamento Oriental “Beni” (213,564 km²). Dicha expansión involucró algunos nodos que no disponen de energía de la red eléctrica pública, por lo que se optó por una generación propia híbrida (solar-diésel), predominantemente solar para 4 de tales nodos.
La Solución
El proyecto de generación propia combina generación fotovoltaica (5.76kWp + área para futura expansión), para la mayor parte del año, con generación a diésel (20kW) para las horas donde la energía acumulada en las baterías no sea suficiente para satisfacer la carga del nodo.
Siendo Nuevatel un operador vanguardista respecto a las nuevas tecnologías, se propuso como acumuladores el uso de baterías de litio (48kWh) a ser cargadas con equipos STUDER VarioTrack VT-80 (2x3.84kW) y respaldadas por un generador AC (20kW) que alimenta un banco de rectificadores (16kW). A todos los sitios se incluyó un modem GSM (Xcom232i) para monitoreo remoto del sistema de solar.
Los equipos están en una caseta o cuarto con ventilación natural.
Por Qué STUDER
STUDER por ser un fabricante de equipos “robustos, flexibles y de alta fiabilidad” brinda la confianza requerida para estos sitios remotos y de difícil acceso, especialmente durante la época de lluvias de la región. Aparte los 10 años de garantía.
Resultado del Proyecto
Los sitios entraron en operación en junio del año 2019 y han operado sin consumir diésel ni reportar caídas de operación hasta la fecha. Es el escenario ideal de la solución propuesta.
System components
2 x Controlador de carga MPPT VT-80 STUDER
1 x Sistema de control RCC-02 STUDER
1 x Xcom 232i + Xcom-GSM STUDER
18 x Paneles Fotovoltaicos de 320Wp
10 x Baterías de litio (LiFePO4) 48Vdc/100Ah
1 x Generador a diésel 20 kW Caterpillar
8 x Rectificadores HE de 2Kw Eltek
Responsible company
VIVA
El Proyecto
Dentro del programa de expansión de su red de fibra óptica, VIVA (NUEVATEL PCS DE BOLIVIA S.A.), contempló el tendido de más de 1000 km de Fibra Óptica, uniendo distintos poblados rurales del Departamento Oriental “Beni” (213,564 km²). Dicha expansión involucró algunos nodos que no disponen de energía de la red eléctrica pública, por lo que se optó por una generación propia híbrida (solar-diésel), predominantemente solar para 4 de tales nodos.
La Solución
El proyecto de generación propia combina generación fotovoltaica (5.76kWp + área para futura expansión), para la mayor parte del año, con generación a diésel (20kW) para las horas donde la energía acumulada en las baterías no sea suficiente para satisfacer la carga del nodo.
Siendo Nuevatel un operador vanguardista respecto a las nuevas tecnologías, se propuso como acumuladores el uso de baterías de litio (48kWh) a ser cargadas con equipos STUDER VarioTrack VT-80 (2x3.84kW) y respaldadas por un generador AC (20kW) que alimenta un banco de rectificadores (16kW). A todos los sitios se incluyó un modem GSM (Xcom232i) para monitoreo remoto del sistema de solar.
Los equipos están en una caseta o cuarto con ventilación natural.
Por Qué STUDER
STUDER por ser un fabricante de equipos “robustos, flexibles y de alta fiabilidad” brinda la confianza requerida para estos sitios remotos y de difícil acceso, especialmente durante la época de lluvias de la región. Aparte los 10 años de garantía.
Resultado del Proyecto
Los sitios entraron en operación en junio del año 2019 y han operado sin consumir diésel ni reportar caídas de operación hasta la fecha. Es el escenario ideal de la solución propuesta.
Bolivia: Telecom VIVA
El Proyecto
VIVA (NUEVATEL PCS DE BOLIVIA S.A.) tiene dentro de sus objetivos, la ampliación de la cobertura de sus servicios al área rural de Bolivia, con tecnologías amigables con el medio ambiente procurando emplear soluciones basadas en fuentes de energías renovables.
De igual manera, la ampliación de los servicios y las nuevas demandas energéticas que ello implica, ha requerido repotenciar las estaciones de telecomunicación existentes con más generadores de energía y sistemas de acumulación de mayor capacidad para evitar el uso prolongado de grupos electrógenos.
En este sentido la propuesta tecnológica combina un nuevo generador fotovoltaico con uno existente en la estación de Cerro Pelado y equipos STUDER que dan la posibilidad de combinar distintas tecnologías y potencias de generación fotovoltaica en un mismo equipo de regulación y control; solución valorada por VIVA en su dinámica de repotenciamiento de estaciones existentes, procurando también la sustitución de bancos de batería de capacidades más adecuadas que permitan minimizar la utilización del sistema de respaldo (grupo electrógeno) con la consiguiente reducción del consumo de diésel y por ende de su costo de operación.
La Solución
Para repotenciar el sistema de Cerro Pelado y reducir las horas de operación del grupo electrógeno, se instaló un arreglo fotovoltaico de 4.1 kWp que requirió el diseño de una estructura especial de soporte, que pudiera integrarse con la estructura del generador fotovoltaico existente a la vez de considerar las limitaciones de espacio en el lugar. Así mismo fue montado un banco de baterías de placa tubular de ciclo profundo tecnología OPzV de 1632 Ah@C10 a 48 V, sumado a equipos de regulación y control de STUDER que permitieron tener un mejor control sobre la operación del grupo electrógeno reduciendo las horas de su funcionamiento.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones remotas de sistemas de telecomunicación que sumado a su flexibilidad, robustez y garantía constituyen las principales razones para su elección.
Resultado del Proyecto
La ejecución del proyecto permitió la reutilización de equipos existentes para la repotenciación de la estación de telecomunicaciones de Cerro Pelado, reduciendo las horas de operación del grupo electrógeno con los consiguientes ahorros en combustible.
System components
1 x Controlador de carga VT-80 STUDER
1 x Controlador de carga VS-120 STUDER
1 x Sistema de control RCC-02 STUDER
1 x Relé auxiliar ARM-02 STUDER
16 x Paneles Solares de 260W JINKO
48 x Elementos de baterías estacionarias TAB OPzV de 816Ah@C10
Responsible company
VIVA and Sie S.A.
El Proyecto
VIVA (NUEVATEL PCS DE BOLIVIA S.A.) tiene dentro de sus objetivos, la ampliación de la cobertura de sus servicios al área rural de Bolivia, con tecnologías amigables con el medio ambiente procurando emplear soluciones basadas en fuentes de energías renovables.
De igual manera, la ampliación de los servicios y las nuevas demandas energéticas que ello implica, ha requerido repotenciar las estaciones de telecomunicación existentes con más generadores de energía y sistemas de acumulación de mayor capacidad para evitar el uso prolongado de grupos electrógenos.
En este sentido la propuesta tecnológica combina un nuevo generador fotovoltaico con uno existente en la estación de Cerro Pelado y equipos STUDER que dan la posibilidad de combinar distintas tecnologías y potencias de generación fotovoltaica en un mismo equipo de regulación y control; solución valorada por VIVA en su dinámica de repotenciamiento de estaciones existentes, procurando también la sustitución de bancos de batería de capacidades más adecuadas que permitan minimizar la utilización del sistema de respaldo (grupo electrógeno) con la consiguiente reducción del consumo de diésel y por ende de su costo de operación.
La Solución
Para repotenciar el sistema de Cerro Pelado y reducir las horas de operación del grupo electrógeno, se instaló un arreglo fotovoltaico de 4.1 kWp que requirió el diseño de una estructura especial de soporte, que pudiera integrarse con la estructura del generador fotovoltaico existente a la vez de considerar las limitaciones de espacio en el lugar. Así mismo fue montado un banco de baterías de placa tubular de ciclo profundo tecnología OPzV de 1632 Ah@C10 a 48 V, sumado a equipos de regulación y control de STUDER que permitieron tener un mejor control sobre la operación del grupo electrógeno reduciendo las horas de su funcionamiento.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones remotas de sistemas de telecomunicación que sumado a su flexibilidad, robustez y garantía constituyen las principales razones para su elección.
Resultado del Proyecto
La ejecución del proyecto permitió la reutilización de equipos existentes para la repotenciación de la estación de telecomunicaciones de Cerro Pelado, reduciendo las horas de operación del grupo electrógeno con los consiguientes ahorros en combustible.
Chad: 3 solar Mini-Grids
The challenge
Chad has one of the lowest electrification rates in the world, 4%. UNIDO (United Nations Industrial Development Organization) and the Chadian Ministry of Oil and Energy selected Trama TecnoAmbiental (TTA) for the installation and operation of 3 pilot solar mini-grids as technology demonstration for improving the electrification rate in Chad with a sustainable management model ensuring the operation during the project lifecycle.
The solution
The systems have PV generation of 36 to 45 kWp with OPzS battery storage and diesel generator as back-up. The electricity generated by the solar systems is distributed through an underground line installed in the village and finally delivered to the population through a service-based tariff scheme, based on an electricity dispenser installed at each user', capable to control both energy as well as limiting the current.
Studer's equipment matched the challenging requirements in terms of robustness and reliability in semi-desert isolated areas. In addition, Studer's solution allowed to fully integrate the service-based tariff scheme in to the system, by driving frequency control mode adapted to the management model implemented. The electricity dispensers perform all their functionalities and display the system information to the final user.
Why Studer
Studer ’s high quality and reliable products are suitable to the extreme project conditions. The Studer solution allowed to configure the system to integrate the mini-grid management model functionalities and implement system information display (bonus, restriction) in the smart meters.
Project outcome
The 3 villages in Chad have a reliable electricity service with a local management model in place that will make it sustainable for the next 20 years. The use of the service-based approach integrated in the system has demonstrated many benefits:
- The mini-grids work within their design range with almost no black-outs
- The batteries maintain a good charge with the consequent benefit in term of life-span
- The use of the diesel genset is minimized, reducing the O&M costs
- The overdue payments are avoided
System components
Responsible company
Trama TecnoAmbiental (TTA)
The challenge
Chad has one of the lowest electrification rates in the world, 4%. UNIDO (United Nations Industrial Development Organization) and the Chadian Ministry of Oil and Energy selected Trama TecnoAmbiental (TTA) for the installation and operation of 3 pilot solar mini-grids as technology demonstration for improving the electrification rate in Chad with a sustainable management model ensuring the operation during the project lifecycle.
The solution
The systems have PV generation of 36 to 45 kWp with OPzS battery storage and diesel generator as back-up. The electricity generated by the solar systems is distributed through an underground line installed in the village and finally delivered to the population through a service-based tariff scheme, based on an electricity dispenser installed at each user', capable to control both energy as well as limiting the current.
Studer's equipment matched the challenging requirements in terms of robustness and reliability in semi-desert isolated areas. In addition, Studer's solution allowed to fully integrate the service-based tariff scheme in to the system, by driving frequency control mode adapted to the management model implemented. The electricity dispensers perform all their functionalities and display the system information to the final user.
Why Studer
Studer ’s high quality and reliable products are suitable to the extreme project conditions. The Studer solution allowed to configure the system to integrate the mini-grid management model functionalities and implement system information display (bonus, restriction) in the smart meters.
Project outcome
The 3 villages in Chad have a reliable electricity service with a local management model in place that will make it sustainable for the next 20 years. The use of the service-based approach integrated in the system has demonstrated many benefits:
- The mini-grids work within their design range with almost no black-outs
- The batteries maintain a good charge with the consequent benefit in term of life-span
- The use of the diesel genset is minimized, reducing the O&M costs
- The overdue payments are avoided
Chile - Atacama: Mini-Grid Pan de Azúcar
The Challenge
Inside the Pan de Azúcar National Park in the Atacama region of Chile lies the small fishing cove of Pan de Azúcar, as well as the facilities of the National Forest Corporation (CONAF). The village of 40 houses did not have access to electricity, a grid or electrical installations. The municipality of Chañaral, in collaboration with Chile's Department of Regional and Administrative Development, decided to bring electricity to this village while respecting the national park environment. After much consideration they opted for an energized minigrid as the best option for the village.
Being a remote area, the demands on the quality of the products and installation are extremely high. That is why the combination of FLUX SOLAR, for the implementation, and STUDER equipment is an optimal solution for this requirement.
The solution
To meet the demands of a national park, only a solar system is a viable option due to its minimal visual impact and zero pollution.
Instead of individual solutions, the decision was made to install a main 39kWp plant in panels with a three-phase 48kW distribution network.
This mainly carries the advantages of greater energy availability per investment, and the centralisation of operation and maintenance allows for building a self-sustaining system over time through a corporation that manages the plant.
The energy use of each user is regulated by a pay system with individual meters.
Why STUDER
STUDER is a recognised brand in systems for remote installations owing to the robustness of its equipment. One of the most important reasons is that the equipment offers a minimum level of faults and has several remote monitoring options.
Project outcome
The solar plant manages continuously the supply of electricity to the entire cove and CONAF, generating zero atmospheric and acoustic emissions. Its visual impact is minimal as it can be incorporated into the natural environment of the national park.
The availability of electricity allowed the fishermen to have a higher-quality yield as they are able to freeze their products. This economic activity generates a source of important income and enables the existence of a small artisanal fishing industry. In addition, it has enabled CONAF to utilise centres for study and tourist information.
System components
150 x Canadian Solar CS6P 260Wp panels
Mounting system Alusín Solar Bulnes with variable tilt
6 x MPPT Studer VarioString VS-120 and VS-70 solar chargers
6 x Studer XTH 8000-48 inverters / chargers
48 x Narada Rex 2V 2.000Ah batteries with 192kWh capacity
1 x equipment hut
1 x installation of microgrid underground distribution network measuring 2 km
40 x certified electrical installations for homes with energy meter system
Responsible company
Flux Solar SpA
The Challenge
Inside the Pan de Azúcar National Park in the Atacama region of Chile lies the small fishing cove of Pan de Azúcar, as well as the facilities of the National Forest Corporation (CONAF). The village of 40 houses did not have access to electricity, a grid or electrical installations. The municipality of Chañaral, in collaboration with Chile's Department of Regional and Administrative Development, decided to bring electricity to this village while respecting the national park environment. After much consideration they opted for an energized minigrid as the best option for the village.
Being a remote area, the demands on the quality of the products and installation are extremely high. That is why the combination of FLUX SOLAR, for the implementation, and STUDER equipment is an optimal solution for this requirement.
The solution
To meet the demands of a national park, only a solar system is a viable option due to its minimal visual impact and zero pollution.
Instead of individual solutions, the decision was made to install a main 39kWp plant in panels with a three-phase 48kW distribution network.
This mainly carries the advantages of greater energy availability per investment, and the centralisation of operation and maintenance allows for building a self-sustaining system over time through a corporation that manages the plant.
The energy use of each user is regulated by a pay system with individual meters.
Why STUDER
STUDER is a recognised brand in systems for remote installations owing to the robustness of its equipment. One of the most important reasons is that the equipment offers a minimum level of faults and has several remote monitoring options.
Project outcome
The solar plant manages continuously the supply of electricity to the entire cove and CONAF, generating zero atmospheric and acoustic emissions. Its visual impact is minimal as it can be incorporated into the natural environment of the national park.
The availability of electricity allowed the fishermen to have a higher-quality yield as they are able to freeze their products. This economic activity generates a source of important income and enables the existence of a small artisanal fishing industry. In addition, it has enabled CONAF to utilise centres for study and tourist information.
Chile: High Altitude World Record Expediton
The Challenge
The Swiss Startup Company DDP Innovation develops an electric Off-road transport Vehicle. To promote the new product and prove the technology. The three company founders plan to set a new altitude world record for land vehicles at the 6893m high Ojos del Salado in Chile. The Mountain lies 300 kilometers away from the next power supply and the DDP Innovation set the goal to complete the record 100% carbon neutral. So a way to charge the high voltage Traction battery with solar energy had to be found.
The Solution
The solution was to divide the solar modules into 5 strings of 4 panels, one string is mounted on the vehicle roof and provides power constantly while 4 strings are laid out on the ground during the midday hours to charge the battery. The system will spend around two weeks at an altitude of more than 5000m. The main challenges for the devices in the thin air is reduced dielectric strength of the air and decreased cooling capability. For this reason the maximum PV voltage was reduced to 65V to avoid electrical breakdown inside the devices and the peak power is set to 1480Wp per VT65. The 5 strings of panels are connected 2s2p and each feed one VT65. The power is then converted from 24V to 300V by 2 Brusa BSC624 DC-DC converters.
Why Studer
Apart from the basic functionality of charging the battery, the system had to fulfill special requirements. It has to provide redundancy in case of component failure and it has to work at altitudes up to nearly 7000m. The Studer devices have proven to work under the most extreme conditions which made the first choice for this project. Studer also provided close technical support to calculate the performance of the devices under the special conditions.
Project outcome
The project is still in progress. The vehicle is being built till the end of 2021 and the world record attempt will happen in 2022 or 2023. The mobile solar plant with the Studer devices will become operational by the end of 2021.
More information on the project can be found on www.peakevolution.ch
System components
Solar modules: 20 x Megasol M370-HC120 7.4kWp
MPPT/Chargers: 5 x Studer VT65
Inverter: 1 x Studer AJ2400
DC-DC converter: 2 x Brusa BSC624
Battery: EcoVolta Evo Traction Battery 300V 90kWh
Responsible company
DDP Innovation
The Challenge
The Swiss Startup Company DDP Innovation develops an electric Off-road transport Vehicle. To promote the new product and prove the technology. The three company founders plan to set a new altitude world record for land vehicles at the 6893m high Ojos del Salado in Chile. The Mountain lies 300 kilometers away from the next power supply and the DDP Innovation set the goal to complete the record 100% carbon neutral. So a way to charge the high voltage Traction battery with solar energy had to be found.
The Solution
The solution was to divide the solar modules into 5 strings of 4 panels, one string is mounted on the vehicle roof and provides power constantly while 4 strings are laid out on the ground during the midday hours to charge the battery. The system will spend around two weeks at an altitude of more than 5000m. The main challenges for the devices in the thin air is reduced dielectric strength of the air and decreased cooling capability. For this reason the maximum PV voltage was reduced to 65V to avoid electrical breakdown inside the devices and the peak power is set to 1480Wp per VT65. The 5 strings of panels are connected 2s2p and each feed one VT65. The power is then converted from 24V to 300V by 2 Brusa BSC624 DC-DC converters.
Why Studer
Apart from the basic functionality of charging the battery, the system had to fulfill special requirements. It has to provide redundancy in case of component failure and it has to work at altitudes up to nearly 7000m. The Studer devices have proven to work under the most extreme conditions which made the first choice for this project. Studer also provided close technical support to calculate the performance of the devices under the special conditions.
Project outcome
The project is still in progress. The vehicle is being built till the end of 2021 and the world record attempt will happen in 2022 or 2023. The mobile solar plant with the Studer devices will become operational by the end of 2021.
More information on the project can be found on www.peakevolution.ch
Chile: Hybrid micro-grid at 4100 meters above sea level
The challenge
Visviri is Chile’s northernmost village, situated close to the Bolivian border, at more than 4000 meters above sea level. To stimulate the self-sustainability by improving energy access to communities far away from conventional energy sources, Visviri’s Centre for collection and processing of camelid fibre (for example Alpaca) was equipped with a solar hybrid micro-grid as part of the 5-year "Ayllú Solar" project, originated by the Chilean Solar Energy Research Centre, SERC.
Their aim is to promote viable and cost-effective projects among the Chilean population in the Arica and Parinacota region that encourage large-scale use of solar energy, a resource in abundance in northern Chile. They are funded by the BHP Billiton Foundation, who works to address some of the most critical global sustainable development challenges.
The solution
A 26.4 kWp hybrid solar micro-grid system in three-phase with 2260 Ah in storage and three Studer inverter/chargers of 8 kWp was set up. The simple and robust system has 10 single-axis solar trackers forming the three-phase line allowing for a production without interruptions and backup in case of natural disasters. Remote monitoring of the system guarantees its optimized operation and life expectancy.
To save system costs the electrical solution was designed to fit inside a container, pre-assembled in a bigger city and then sent to the final destination. The modular design and adaptability of containerized solar systems makes them ideal for any electric project in rural areas.
Why Studer
The reason for using Studer power electronics is the versatility of the resulting systems and the guaranteed functioning at altitudes exceeding 4000 meters above sea level. Also, in Chile the after sales service on Studer equipment is very good.
The project outcome
Today 100% of the centre’s electrical production is powered by solar energy and their production capacity is improved. As local workers were integrated in all parts of the project, from conception and design to execution, the community know how to operate the system themselves and have trust in the technology.
SERC hopes that these positive results will help improve the people’s confidence in renewable energies and one day transform Arica-Chile into the sunny capital of South America.
System components
3 x STUDER Xtender inverter/chargers XTH 8000-48
80 x Jinko solar panels 330Wp
48 x Sonnenschein batteries 2V and 1130Ah in C120
5 x STUDER VarioTrack MPPT solar charge controller VT-80
3 x combination cabinet MNDC 250A
1 x REC container adapted for battery equipment
10 x Solar trackers, one axis, for 8 PV panels of 72 cells
Responsible company
Solar Trust SpA
The challenge
Visviri is Chile’s northernmost village, situated close to the Bolivian border, at more than 4000 meters above sea level. To stimulate the self-sustainability by improving energy access to communities far away from conventional energy sources, Visviri’s Centre for collection and processing of camelid fibre (for example Alpaca) was equipped with a solar hybrid micro-grid as part of the 5-year "Ayllú Solar" project, originated by the Chilean Solar Energy Research Centre, SERC.
Their aim is to promote viable and cost-effective projects among the Chilean population in the Arica and Parinacota region that encourage large-scale use of solar energy, a resource in abundance in northern Chile. They are funded by the BHP Billiton Foundation, who works to address some of the most critical global sustainable development challenges.
The solution
A 26.4 kWp hybrid solar micro-grid system in three-phase with 2260 Ah in storage and three Studer inverter/chargers of 8 kWp was set up. The simple and robust system has 10 single-axis solar trackers forming the three-phase line allowing for a production without interruptions and backup in case of natural disasters. Remote monitoring of the system guarantees its optimized operation and life expectancy.
To save system costs the electrical solution was designed to fit inside a container, pre-assembled in a bigger city and then sent to the final destination. The modular design and adaptability of containerized solar systems makes them ideal for any electric project in rural areas.
Why Studer
The reason for using Studer power electronics is the versatility of the resulting systems and the guaranteed functioning at altitudes exceeding 4000 meters above sea level. Also, in Chile the after sales service on Studer equipment is very good.
The project outcome
Today 100% of the centre’s electrical production is powered by solar energy and their production capacity is improved. As local workers were integrated in all parts of the project, from conception and design to execution, the community know how to operate the system themselves and have trust in the technology.
SERC hopes that these positive results will help improve the people’s confidence in renewable energies and one day transform Arica-Chile into the sunny capital of South America.
Chile: SOLAR PRIORITY IN HOMES
The Challenge
Chile is a seismic country and there are dangers that can put the electricity supply at risk, be it floods, volcanic eruptions, fires, or, for example, the snowstorm that hit Santiago in July 2017 leaving 200,000 people without electricity for several days.
Chile's law of distributed generation (law 20.571) both allows the connection of self-consumption photovoltaic systems and the sale of energy surpluses. However as the tariffs are approximately 60% of the purchase rate it is economically interesting to increase a household's self-consumption, reducing the electricity bills as well as having autonomous supply in the event of power outages.
All these requirements can be perfectly met by a Studer system with solar priority. Take this 380 m2 private villa with electrical appliances such as air conditioning, a swimming pool and an electric oven and an annual electricity consumption of approximately 8,000 kWh as an example.
The solution
The house has a grid connection with single-phase 220V, 50Hz and 40A. The XTM 4000-48 acts as the heart of the solar system, programmed with solar priority and active Smart-Boost. The house can thus take full advantage of solar generation for self-consumption as it not only supplies itself with the solar electricity generated at the time, but also uses the batteries to store the energy and deliver it to the house. The battery is always kept at least 30% charged to ensure reliable supply. The XTM only supplements the supply with electricity from the grid in the event of very high consumption.
It is estimated that thanks to the implemented system, the house will be able to reduce its electric bill by more than 80%, as well as having the security of being able to operate continuously and without limits should the electric grid fail.
Why STUDER
STUDER enables the implementation of special applications thanks to the wide range of programming options. Additionally, with the XCOM LAN, the user can analyse the behaviour of their system from anywhere in the world and make adjustments if necessary. Together with the SIMPLIPHI batteries that allow 10,000 cycles of useful life and the programmed loading and unloading framework in STUDER equipment, especially for this type of LFP batteries, the installed solution guarantees a reliable solar power supply with an expectation of at least 20 years of useful life.
Project outcome
In its first months of operation, the system was already able to demonstrate its excellent performance and the electricity bill was reduced with more than 50% despite it being winter.
System components
16 x photovoltaic modules with 260Wp each
1 x VS-70 STUDER charge controller
1 x XTM 4000-48 STUDER inverter
1 x RCC-02 control system
1 x X-Com LAN STUDER communication device
1 x BTS 01 STUDER battery temperature sensor
1 x SBM-02 STUDER battery monitor
1 x SBM-PS-02 STUDER voltage adapter
2 x lithium iron phosphate batteries SIMPLIPHI 3.4, 48V, at 3.4kWh capacity each
Responsible company
STC Sunbelt SpA
The Challenge
Chile is a seismic country and there are dangers that can put the electricity supply at risk, be it floods, volcanic eruptions, fires, or, for example, the snowstorm that hit Santiago in July 2017 leaving 200,000 people without electricity for several days.
Chile's law of distributed generation (law 20.571) both allows the connection of self-consumption photovoltaic systems and the sale of energy surpluses. However as the tariffs are approximately 60% of the purchase rate it is economically interesting to increase a household's self-consumption, reducing the electricity bills as well as having autonomous supply in the event of power outages.
All these requirements can be perfectly met by a Studer system with solar priority. Take this 380 m2 private villa with electrical appliances such as air conditioning, a swimming pool and an electric oven and an annual electricity consumption of approximately 8,000 kWh as an example.
The solution
The house has a grid connection with single-phase 220V, 50Hz and 40A. The XTM 4000-48 acts as the heart of the solar system, programmed with solar priority and active Smart-Boost. The house can thus take full advantage of solar generation for self-consumption as it not only supplies itself with the solar electricity generated at the time, but also uses the batteries to store the energy and deliver it to the house. The battery is always kept at least 30% charged to ensure reliable supply. The XTM only supplements the supply with electricity from the grid in the event of very high consumption.
It is estimated that thanks to the implemented system, the house will be able to reduce its electric bill by more than 80%, as well as having the security of being able to operate continuously and without limits should the electric grid fail.
Why STUDER
STUDER enables the implementation of special applications thanks to the wide range of programming options. Additionally, with the XCOM LAN, the user can analyse the behaviour of their system from anywhere in the world and make adjustments if necessary. Together with the SIMPLIPHI batteries that allow 10,000 cycles of useful life and the programmed loading and unloading framework in STUDER equipment, especially for this type of LFP batteries, the installed solution guarantees a reliable solar power supply with an expectation of at least 20 years of useful life.
Project outcome
In its first months of operation, the system was already able to demonstrate its excellent performance and the electricity bill was reduced with more than 50% despite it being winter.
Colombia: Casa de la MUJER, Hemeva
The challenge
10% of Colombia's 49 Million population live in the country's border areas without access to the national grid. Power supply in these areas is typically generated from community diesel generators that supply power for a few hours a day when diesel is available.
The small textile factory "Casa de la Mujer - Chejuru" in the Selva del Mataven Unified Indigenous Reservoir (composed of 92 communities), is only accessible by boat during the winter when the water level in the rivers are high enough for transports. During summer the supply of diesel is scarce and it is impossible to generate electricity, even for a few hours.
For a sustainable development of these areas Colombia's government has launched the initiative “Plan Fronteras para la Prosperidad” led by the Ministry of Foreign Affairs. The goal is to encourage the development of income generating companies creating a financially sustainable solution over time by providing a reliable and continuous power supply during the working day through off-grid electrification.
The solution
The 7 kWp PV system at "Casa de la Mujer – Chejuru" provides reliable and stable energy supply to power the operation of 25 sewing machines and two filleting machines to produce, market and sell clothing to the local population.
The offered solution based on solar generation and battery storage avoids the use of diesel electric generators, saving 100% of diesel consumption and thereby reducing the CO2 emissions with 90 to 100 MT per year. The repayment time for the project is estimated to less than 5 years and the installation's life-time to 25 years, with a planned replacement of the batteries after 12 years (with adequate maintenance).
The local community actively participated in the project for a concerted, inclusive and adequate solution in line with their expectations, needs and long-term vision.
Why STUDER
STUDER is a recognised brand in solution systems for isolated installations owing to the robustness and reliability of its equipment, as well as the high integrability of its equipment for optimal operation and local monitoring. The most important reasons are that they feature a very low fault level and an operating logic designed and developed to extend the life of the batteries.
Project outcome
Project sustainability will be achieved through commercialisation of the produced clothes to nearby communities and additional economic benefits is obtained by sharing the electricity with the community's other company "Cooperativa de Artesanos" sending handicrafts to local and international markets.
By encouraging the development of a durable financial solution for these communities the Colombian government also seek to counteract the deforestation of these areas vital for the environmental balance of our planet.
System components
1 x XTH 6000-48-01 STUDER inverter/charger
22 x 320Wp ETSolar solar panels
8 x SIND 06 1225 TROJAN stationary battery elements
1 x VS-120 STUDER solar controller
1 x BSP 500 STUDER battery monitor
1 x RCC-03 STUDER display
1 x battery cabinet
1 x guard cabinet
Responsible company
Hemeva S.A.S
The challenge
10% of Colombia's 49 Million population live in the country's border areas without access to the national grid. Power supply in these areas is typically generated from community diesel generators that supply power for a few hours a day when diesel is available.
The small textile factory "Casa de la Mujer - Chejuru" in the Selva del Mataven Unified Indigenous Reservoir (composed of 92 communities), is only accessible by boat during the winter when the water level in the rivers are high enough for transports. During summer the supply of diesel is scarce and it is impossible to generate electricity, even for a few hours.
For a sustainable development of these areas Colombia's government has launched the initiative “Plan Fronteras para la Prosperidad” led by the Ministry of Foreign Affairs. The goal is to encourage the development of income generating companies creating a financially sustainable solution over time by providing a reliable and continuous power supply during the working day through off-grid electrification.
The solution
The 7 kWp PV system at "Casa de la Mujer – Chejuru" provides reliable and stable energy supply to power the operation of 25 sewing machines and two filleting machines to produce, market and sell clothing to the local population.
The offered solution based on solar generation and battery storage avoids the use of diesel electric generators, saving 100% of diesel consumption and thereby reducing the CO2 emissions with 90 to 100 MT per year. The repayment time for the project is estimated to less than 5 years and the installation's life-time to 25 years, with a planned replacement of the batteries after 12 years (with adequate maintenance).
The local community actively participated in the project for a concerted, inclusive and adequate solution in line with their expectations, needs and long-term vision.
Why STUDER
STUDER is a recognised brand in solution systems for isolated installations owing to the robustness and reliability of its equipment, as well as the high integrability of its equipment for optimal operation and local monitoring. The most important reasons are that they feature a very low fault level and an operating logic designed and developed to extend the life of the batteries.
Project outcome
Project sustainability will be achieved through commercialisation of the produced clothes to nearby communities and additional economic benefits is obtained by sharing the electricity with the community's other company "Cooperativa de Artesanos" sending handicrafts to local and international markets.
By encouraging the development of a durable financial solution for these communities the Colombian government also seek to counteract the deforestation of these areas vital for the environmental balance of our planet.
Colombia: Centro Medico
El Proyecto
La Solución
Con un generador solar de 960 Wp y un banco de baterías de 750Ah/24 Vdc, se logra entregar energía suficiente para que se puedan conectar los equipos médicos principales como los monitores, el aspirador, el electrocardiograma, entre otros. Los elementos de consulta, como le portátil y la impresora. Y también cargas como iluminación, ventilación y una nevera pequeña.
Por Qué STUDER
STUDER es una marca con un período de garantía amplio, soporte técnico y versatilidad en configuraciones. Adicionalmente, la simplicidad de su diseño ayuda a que el usuario pueda manipular el equipo fácilmente. Una de las característica más importante de sus inversores, es el B.L.O., porque ayuda a extender la vida útil de las baterías, lo cual es muy valioso en zonas remotas.
Resultado del Proyecto
La solución ofrecida de 2.250 Wh/día útiles, permite la utilización de los equipos médicos para las necesidades principales como los partos y las consultas generales, a lo largo del día. Anteriormente, tenían servicio de energía 3 horas diarias en la noche, ahora ya no utilizan el generador y la comunidad es la encargada del mantenimiento del sistema.
System components
1 x Inversor / Cargador AJ-1300-24-01 STUDER.
3 x Paneles Solares de 320Wp ET Solar
12 x Batería AGM de 750Ah/2V
1 x Regulador solar PWM Morningstar de 45A
1 x Gabinete para albergar controlador e inversor
1 x Rack de baterías cubierto
Responsible company
COANTEC SAS
El Proyecto
La Solución
Con un generador solar de 960 Wp y un banco de baterías de 750Ah/24 Vdc, se logra entregar energía suficiente para que se puedan conectar los equipos médicos principales como los monitores, el aspirador, el electrocardiograma, entre otros. Los elementos de consulta, como le portátil y la impresora. Y también cargas como iluminación, ventilación y una nevera pequeña.
Por Qué STUDER
STUDER es una marca con un período de garantía amplio, soporte técnico y versatilidad en configuraciones. Adicionalmente, la simplicidad de su diseño ayuda a que el usuario pueda manipular el equipo fácilmente. Una de las característica más importante de sus inversores, es el B.L.O., porque ayuda a extender la vida útil de las baterías, lo cual es muy valioso en zonas remotas.
Resultado del Proyecto
La solución ofrecida de 2.250 Wh/día útiles, permite la utilización de los equipos médicos para las necesidades principales como los partos y las consultas generales, a lo largo del día. Anteriormente, tenían servicio de energía 3 horas diarias en la noche, ahora ya no utilizan el generador y la comunidad es la encargada del mantenimiento del sistema.
Colombia: Departamento de la Guajira Municipio de Rioacha
El Proyecto
Beneficiado: Centro educativo rural Caracas Ruleya.
La Cancillería de Colombia dentro de su división de fronteras aunando esfuerzos para soluciones energéticas en zonas no interconectadas realizo un convenio interadministrativo con EMPULEG (Empresa de servicios públicos de Leguizamo – Putumayo).
La Cancillería Colombiana, con el fin de dar soluciones energéticas y además brindando un beneficio a la comunidad, tomó la iniciativa de instalar soluciones de energía solar fotovoltaica en las institucións educativas del departamento de la Guajira. Este departamento es zona de frontera con la república de la Venezuela y está limitado por el acceso a la energía y falta de infraestructura de la región.
En este sentido, la Cancillería Colombiana pensando en mejorar la calidad de vida de los estudiantes y su acceso a las nuevas tecnologías de información y comunicación (TICs) suministró energía eléctrica con paneles solares y equipos STUDER como solución para el sistema aislado de la red.
Dentro el proceso de instalación se realizó unas charlas con los docentes del centro educativo como fue el mantenimiento de los panales solares, y reactivar el sistema si se llega a presentar un corto, limpieza del grupo de baterías.
La Solución
El objetivo del proyecto fue energizar de manera confiable la institución educativa, ya que la institución había recibido equipos de cómputo para aulas de informática, pero la institución no contaba con red eléctrica ni grupo generador para el uso apropiado de estos sistemas.
Pensando en la comodidad de los estudiantes y en minimizar el impacto ecológico en la región se optó por un sistema completamente aislado (sin apoyo en generadores diesel) con los equipos anteriormente mencionados.
Por Qué STUDER
STUDER es una marca reconocida en equipos especializados para generar soluciones fotovoltaicas aisladas. Debido a la distancia, sumado al difícil acceso en la región STUDER es la solución ideal gracias a la robustez y alta confiabilidad de los equipos.
Resultado del Proyecto
La solución instalada ha permitido que los estudiantes tengan acceso a las nuevas TICs y ayudas didácticas electrónicas mejorando así su formación académica.
System components
2 x Inversor/Cargador STUDER Xtender XTM 4000-48-01
2 x Regulador solar MPPT STUDER VarioTrack VT-80
16 x Paneles Solares policristalinos de 260Wp
24 x Baterías BAE 2V y 1050Ah en C100
1 x Programador y Datalogger STUDER RCC-02
Responsible company
EMPULEG ESP & ENERGÍA Y MOVILIDAD(E&M)
El Proyecto
Beneficiado: Centro educativo rural Caracas Ruleya.
La Cancillería de Colombia dentro de su división de fronteras aunando esfuerzos para soluciones energéticas en zonas no interconectadas realizo un convenio interadministrativo con EMPULEG (Empresa de servicios públicos de Leguizamo – Putumayo).
La Cancillería Colombiana, con el fin de dar soluciones energéticas y además brindando un beneficio a la comunidad, tomó la iniciativa de instalar soluciones de energía solar fotovoltaica en las institucións educativas del departamento de la Guajira. Este departamento es zona de frontera con la república de la Venezuela y está limitado por el acceso a la energía y falta de infraestructura de la región.
En este sentido, la Cancillería Colombiana pensando en mejorar la calidad de vida de los estudiantes y su acceso a las nuevas tecnologías de información y comunicación (TICs) suministró energía eléctrica con paneles solares y equipos STUDER como solución para el sistema aislado de la red.
Dentro el proceso de instalación se realizó unas charlas con los docentes del centro educativo como fue el mantenimiento de los panales solares, y reactivar el sistema si se llega a presentar un corto, limpieza del grupo de baterías.
La Solución
El objetivo del proyecto fue energizar de manera confiable la institución educativa, ya que la institución había recibido equipos de cómputo para aulas de informática, pero la institución no contaba con red eléctrica ni grupo generador para el uso apropiado de estos sistemas.
Pensando en la comodidad de los estudiantes y en minimizar el impacto ecológico en la región se optó por un sistema completamente aislado (sin apoyo en generadores diesel) con los equipos anteriormente mencionados.
Por Qué STUDER
STUDER es una marca reconocida en equipos especializados para generar soluciones fotovoltaicas aisladas. Debido a la distancia, sumado al difícil acceso en la región STUDER es la solución ideal gracias a la robustez y alta confiabilidad de los equipos.
Resultado del Proyecto
La solución instalada ha permitido que los estudiantes tengan acceso a las nuevas TICs y ayudas didácticas electrónicas mejorando así su formación académica.
Colombia: Escuela en Tarapacá
El Proyecto
La Solución
Con un generador solar de 2,88 kWp y un banco de baterías de 1000Ah/48 Vdc, se logra entregar energía suficiente para que se puedan conectar 30 portátiles, un video beam, un rack de comunicaciones, un router y una impresora. Ahora, la sala la usan en la mañana para los niños de la institución y en la noche se utiliza para clases con el SENA.
Por Qué STUDER
STUDER es una marca con un período de garantía amplio (10 años), soporte técnico y versatilidad en configuraciones. Adicionalmente, la simplicidad de su diseño ayuda a que el usuario pueda manipular el equipo fácilmente. Una de las característica más importante de sus inversores, es el BLO, porque ayuda a extender la vida útil de las baterías, lo cual es muy valioso en zonas remotas.
Resultado del Proyecto
La solución ofrecida de 6200 Wh/día útiles, permite la utilización de la sala de informática, en las horas de la mañana, mejorando la educación de los niños de la Institución Educativa Villa Carmen. Adicionalmente, mejoró la conectividad del Internet, pues ahora es de 24 horas, gracias al respaldo del banco de baterías con autonomía de 3 días.
System components
1 x Inversor / Cargador XTENDER XTM-4000-48-01 STUDER.
9 x Paneles Solares de 320Wp ET Solar
24 x Batería AGM de 1000Ah/2V
1 x Regulador solar MPPT Morningstar de 60A
1 x Gabinete para albergar controlador e inversor
1 x Rack de baterías cubierto
Responsible company
COANTEC SAS
El Proyecto
La Solución
Con un generador solar de 2,88 kWp y un banco de baterías de 1000Ah/48 Vdc, se logra entregar energía suficiente para que se puedan conectar 30 portátiles, un video beam, un rack de comunicaciones, un router y una impresora. Ahora, la sala la usan en la mañana para los niños de la institución y en la noche se utiliza para clases con el SENA.
Por Qué STUDER
STUDER es una marca con un período de garantía amplio (10 años), soporte técnico y versatilidad en configuraciones. Adicionalmente, la simplicidad de su diseño ayuda a que el usuario pueda manipular el equipo fácilmente. Una de las característica más importante de sus inversores, es el BLO, porque ayuda a extender la vida útil de las baterías, lo cual es muy valioso en zonas remotas.
Resultado del Proyecto
La solución ofrecida de 6200 Wh/día útiles, permite la utilización de la sala de informática, en las horas de la mañana, mejorando la educación de los niños de la Institución Educativa Villa Carmen. Adicionalmente, mejoró la conectividad del Internet, pues ahora es de 24 horas, gracias al respaldo del banco de baterías con autonomía de 3 días.
Colombia: Estación Policia Florida, Colenergy
El Proyecto
La finalidad del proyecto fue gestionar diferentes fuentes de energía para garantizar la operación de la línea de emergencia 123 utilizando un sistema off grid como back up y así mejorar la confiabilidad del servicio de emergencia y seguridad ciudadana. Administrar la energía mediante la separación de cargas esenciales y no esenciales.
Además, realizar acciones de ahorro en el costo de energía por medio de un sistema on grid, y un uso eficiente de la energía mediante la educación y protección del medio ambiente. Reduciendo así, el impacto negativo en el medio ambiente en procesos y servicios que presta la institución.
Siguiendo esta política la Policía Nacional, en el proceso de modernización de infraestructura, ha optado por implementar sistemas de energías alternativas y amigables con el medio ambiente.
Es por ello que la propuesta de un sistema fotovoltaico híbrido por parte de COLENERGY SAS, utilizando su experiencia en diseños, suministro e instalación equipos, en combinación con STUDER es una solución muy valorada por LA POLICIA NACIONAL para trabajar en zonas céntricas y remotas, acumulando la energía producida por los módulos solares en bancos de baterías y poder así, disminuir el consumo de energía eléctrica de la red.
La Solución
Para cumplir con el objetivo de disminuir el consumo de energía de la red, y aumentar la confiabilidad del sistema se configuró una solución que involucra inversores híbridos definidos para unas cargas esenciales, las cuales están alimentadas todo el tiempo, porque corresponden al sistema de emergencia de la Policía. A la vez está apoyada con el un sistema on grid que permite un ahorro en el consumo.
Por Qué STUDER
STUDER es una marca reconocida en sistemas híbridos. Estos procuran una gran flexibilidad en la alimentación y una mayor independencia con respecto a una u otra de las fuentes de energía. La alimentación de aparatos en corriente alterna (AC) se hace directamente desde la fuente de energía gracias al relé de transferencia o desde la batería con la función inversor.
Resultado del Proyecto
El resultado es la prevención de la contaminación, cumplimiento y control de la legislación, y el control de aspectos e impactos ambientales asociadas a las instalaciones, procesos y servicios gracias a la gestión de la energía fotovoltaica gestionada por los equipos STUDER.
System components
144 x Módulos Fotovoltaicos 340W
1 x Inversor de Inyección a la red 27.6 kW, 30kWp/1000Vdc
6 x Inversores STUDER XTM 4000-48-01
4 x Reguladores STUDER MPPT VS-120
Banco de Baterías de 24 unidades de 2V de 3089 Ah/C10
Responsible company
COLENERGY SAS
El Proyecto
La finalidad del proyecto fue gestionar diferentes fuentes de energía para garantizar la operación de la línea de emergencia 123 utilizando un sistema off grid como back up y así mejorar la confiabilidad del servicio de emergencia y seguridad ciudadana. Administrar la energía mediante la separación de cargas esenciales y no esenciales.
Además, realizar acciones de ahorro en el costo de energía por medio de un sistema on grid, y un uso eficiente de la energía mediante la educación y protección del medio ambiente. Reduciendo así, el impacto negativo en el medio ambiente en procesos y servicios que presta la institución.
Siguiendo esta política la Policía Nacional, en el proceso de modernización de infraestructura, ha optado por implementar sistemas de energías alternativas y amigables con el medio ambiente.
Es por ello que la propuesta de un sistema fotovoltaico híbrido por parte de COLENERGY SAS, utilizando su experiencia en diseños, suministro e instalación equipos, en combinación con STUDER es una solución muy valorada por LA POLICIA NACIONAL para trabajar en zonas céntricas y remotas, acumulando la energía producida por los módulos solares en bancos de baterías y poder así, disminuir el consumo de energía eléctrica de la red.
La Solución
Para cumplir con el objetivo de disminuir el consumo de energía de la red, y aumentar la confiabilidad del sistema se configuró una solución que involucra inversores híbridos definidos para unas cargas esenciales, las cuales están alimentadas todo el tiempo, porque corresponden al sistema de emergencia de la Policía. A la vez está apoyada con el un sistema on grid que permite un ahorro en el consumo.
Por Qué STUDER
STUDER es una marca reconocida en sistemas híbridos. Estos procuran una gran flexibilidad en la alimentación y una mayor independencia con respecto a una u otra de las fuentes de energía. La alimentación de aparatos en corriente alterna (AC) se hace directamente desde la fuente de energía gracias al relé de transferencia o desde la batería con la función inversor.
Resultado del Proyecto
El resultado es la prevención de la contaminación, cumplimiento y control de la legislación, y el control de aspectos e impactos ambientales asociadas a las instalaciones, procesos y servicios gracias a la gestión de la energía fotovoltaica gestionada por los equipos STUDER.
Colombia: Lechería La Viena 100% Solar, split-phase
El Proyecto
La Lechería La Viena está localizada en el área rural del municipio de Chinchiná, departamento de Caldas. La lechería se construyó hace 6 meses teniendo en cuentas las mejores prácticas en el manejo de ganado de leche en términos de higiene y sostenibilidad. En el momento se ordeñan 108 vacas en dos turnos con una producción estimada de 3000 litros diarios.
La Solución
El proyecto produce leche con energía 100% solar con un impacto por producción de energía de cero carbono. Se instala entonces un sistema de 24.5 kW totalmente aislado donde los inversores están conectados en Split phase y en paralelo donde cada fase tiene 12 kW de potencia, los controladores de carga están conectados en paralelo a una banco de baterías en común. El cuarto de almacenamiento de los equipos fue diseño con adecuada ventilación y cerramiento para proteger todos los componentes de bichos y animales.
El sistema alimenta bombas de vacíos, de succión, tanques de enfriamiento, las cercas eléctricas y la casa donde viven los operarios de la lechería.
Por Qué STUDER
STUDER es una marca reconocida en sistemas de soluciones para instalaciones solares fotovoltaicas aisladas y robustez de sus equipos para una agro industrial como esta donde se necesita confiabilidad en la producción de energía diaria.
Resultado del Proyecto
La solución implementada ahorro en el costo montaje de llevar la red hasta la lechería y/o alternativa de tener una planta diesel. El objetivo es producir leche con energía 100% solar con un impacto por producción de energía de cero carbono. El periodo de retorno de este proyecto está alrededor de los 7 años.
Siendo este el primer proyecto piloto de esta naturaleza en Colombia esperamos replicarlo en otras lecherías la cuales no tienen acceso a la red eléctrica a convencional y/o donde el consumo de diesel no es rentable y contaminante.
Próximamente se presentará el proyecto como caso de estudio de éxito en la ANALAC- Asociación Nacional de Productores de Leche y el BID-Banco Interamericano de Desarrollo.
System components
4 x XTH 6000-48, STUDER
98 x Paneles Solares Solarworld 250W
3 x VS 120, STUDER
1 x VS 70, STUDER
1 x Banco de Baterías OPzV BAE de 1650Ah a 48V
Protecciones y SPDs ABB para todos los componentes
Cableado PV Flex Helukabel
Cajas de conexión Spelsberg
Responsible company
EnerSolax
El Proyecto
La Lechería La Viena está localizada en el área rural del municipio de Chinchiná, departamento de Caldas. La lechería se construyó hace 6 meses teniendo en cuentas las mejores prácticas en el manejo de ganado de leche en términos de higiene y sostenibilidad. En el momento se ordeñan 108 vacas en dos turnos con una producción estimada de 3000 litros diarios.
La Solución
El proyecto produce leche con energía 100% solar con un impacto por producción de energía de cero carbono. Se instala entonces un sistema de 24.5 kW totalmente aislado donde los inversores están conectados en Split phase y en paralelo donde cada fase tiene 12 kW de potencia, los controladores de carga están conectados en paralelo a una banco de baterías en común. El cuarto de almacenamiento de los equipos fue diseño con adecuada ventilación y cerramiento para proteger todos los componentes de bichos y animales.
El sistema alimenta bombas de vacíos, de succión, tanques de enfriamiento, las cercas eléctricas y la casa donde viven los operarios de la lechería.
Por Qué STUDER
STUDER es una marca reconocida en sistemas de soluciones para instalaciones solares fotovoltaicas aisladas y robustez de sus equipos para una agro industrial como esta donde se necesita confiabilidad en la producción de energía diaria.
Resultado del Proyecto
La solución implementada ahorro en el costo montaje de llevar la red hasta la lechería y/o alternativa de tener una planta diesel. El objetivo es producir leche con energía 100% solar con un impacto por producción de energía de cero carbono. El periodo de retorno de este proyecto está alrededor de los 7 años.
Siendo este el primer proyecto piloto de esta naturaleza en Colombia esperamos replicarlo en otras lecherías la cuales no tienen acceso a la red eléctrica a convencional y/o donde el consumo de diesel no es rentable y contaminante.
Próximamente se presentará el proyecto como caso de estudio de éxito en la ANALAC- Asociación Nacional de Productores de Leche y el BID-Banco Interamericano de Desarrollo.
Colombia: Municipio de Puerto Leguizamo
El Proyecto
Beneficiado: Centro Educativo Rural.
La Cancillería de Colombia dentro de su división de fronteras aunando esfuerzos para soluciones energéticas en zonas no interconectadas realizó un convenio interadministrativo con EMPULEG (Empresa de Servicios Públicos de Leguizamo – Putumayo).
La cancillería colombiana, con el fin de dar soluciones energéticas y además brindando un beneficio a la comunidad, tomó la iniciativa de instalar soluciones de energía solar fotovoltaica en varias instituciones educativas del departamento de Putumayo. Este departamento es zona de frontera con la República del Ecuador, y está limitado al acceso a la energía por falta de infraestructura de la región.
En este sentido, la Cancillería Colombiana pensando en mejorar la calidad de vida de los estudiantes y su acceso a las nuevas tecnologías de información y comunicación (TICs) suministró energía eléctrica con paneles solares y equipos STUDER como solución para el sistema aislado de la red.
La solucíon
El objetivo del proyecto fue energizar de manera confiable la institución educativa, ya que la institución había recibido equipos de cómputo para aulas de informática, pero la institución no contaba con red eléctrica ni grupo generador para el uso apropiado de estos sistemas.
Pensando en la comodidad de los estudiantes y en minimizar el impacto ecológico en la región se optó por un sistema completamente aislado (sin apoyo en generadores diesel) con los equipos anteriormente mencionados.
Por Qué STUDER
STUDER es una marca reconocida en equipos especializados para generar soluciones fotovoltaicas aisladas. Debido a la distancia, sumado al difícil acceso en la región STUDER es la solución ideal gracias a la robustez y alta confiabilidad de los equipos.
Resultado del Proyecto
La solución instalada ha permitido que los estudiantes tengan acceso a las nuevas TICs y ayudas didácticas electrónicas mejorando así su formación académica.
System components
1 x Inversor/cargador STUDER XTH 3000-12
2 x Regulador solar MPPT STUDER VarioTrack VT-80
8 x Paneles Solares policristalinos de 260W
6 x baterías estacionarias OPzV 500Ah C100 NARADA
1 x Gestor de la instalación STUDER RCC-02
Responsible company
EMPULEG ESP
El Proyecto
Beneficiado: Centro Educativo Rural.
La Cancillería de Colombia dentro de su división de fronteras aunando esfuerzos para soluciones energéticas en zonas no interconectadas realizó un convenio interadministrativo con EMPULEG (Empresa de Servicios Públicos de Leguizamo – Putumayo).
La cancillería colombiana, con el fin de dar soluciones energéticas y además brindando un beneficio a la comunidad, tomó la iniciativa de instalar soluciones de energía solar fotovoltaica en varias instituciones educativas del departamento de Putumayo. Este departamento es zona de frontera con la República del Ecuador, y está limitado al acceso a la energía por falta de infraestructura de la región.
En este sentido, la Cancillería Colombiana pensando en mejorar la calidad de vida de los estudiantes y su acceso a las nuevas tecnologías de información y comunicación (TICs) suministró energía eléctrica con paneles solares y equipos STUDER como solución para el sistema aislado de la red.
La solucíon
El objetivo del proyecto fue energizar de manera confiable la institución educativa, ya que la institución había recibido equipos de cómputo para aulas de informática, pero la institución no contaba con red eléctrica ni grupo generador para el uso apropiado de estos sistemas.
Pensando en la comodidad de los estudiantes y en minimizar el impacto ecológico en la región se optó por un sistema completamente aislado (sin apoyo en generadores diesel) con los equipos anteriormente mencionados.
Por Qué STUDER
STUDER es una marca reconocida en equipos especializados para generar soluciones fotovoltaicas aisladas. Debido a la distancia, sumado al difícil acceso en la región STUDER es la solución ideal gracias a la robustez y alta confiabilidad de los equipos.
Resultado del Proyecto
La solución instalada ha permitido que los estudiantes tengan acceso a las nuevas TICs y ayudas didácticas electrónicas mejorando así su formación académica.
Colombia: Off-Grid System Water Pumping Station
The challenge
The water distribution system of the Colombian town Rubiales in the Meta department was previously using a diesel generator for its pumping station. As both fuel and maintenance of a diesel generator is expensive, they were looking for a renewable energy system to replace it completely. In Colombia hydropower accounts for about two thirds of the generation capacity (2016).
The solution
This is a complete off-grid system for a pumping station with two submerged pumps. One pump draws water from an 80m deep well into an 80m3 water storage tank. The second pump is transferring water from that tank to a 50m3 storage tank in a water tower located 60 m above ground. The water then flows by gravity to the town users, about 100 homes.
The solar system is composed of a 54 kWp solar field, four 48V battery banks each of 2405Ah C-100, nine solar charge controllers in parallel and three inverter/chargers in a 3-phase system configuration.
Why Studer
For this installation Studer products were chosen due to their high product quality and their excellent communication between solar charge controllers and inverter/chargers making them easy to install and to commission.
Project outcome
The habitants of the Rubiales town is now solely using solar power for their local aqueduct. As additional benefits, its operation is silent and there is no pollution.
Replacing the existing diesel generator with an off-grid system to power the pumping station was not only a technical challenge but it also meant a reorganisation of the pumping stations running times in order to make the system efficient. The pumps are still running 9 hours per day; however, they start a few hours later in order to fully benefit from the power generation close to midday when the sun is at its peak. In the beginning, this change was difficult for the people as they were used to having the water supply already at five o'clock in the morning.
Currently some users do not have water tanks, meters or valves to close the pipes and the clear water waste is big, approximately 30% of the water supply. If they would put in valves to close the pipes and save the water the need for pumping hours would decrease, the availability to water be extended and they could supply water to new users.
System components
Responsible company
Hemeva S.A.S
The challenge
The water distribution system of the Colombian town Rubiales in the Meta department was previously using a diesel generator for its pumping station. As both fuel and maintenance of a diesel generator is expensive, they were looking for a renewable energy system to replace it completely. In Colombia hydropower accounts for about two thirds of the generation capacity (2016).
The solution
This is a complete off-grid system for a pumping station with two submerged pumps. One pump draws water from an 80m deep well into an 80m3 water storage tank. The second pump is transferring water from that tank to a 50m3 storage tank in a water tower located 60 m above ground. The water then flows by gravity to the town users, about 100 homes.
The solar system is composed of a 54 kWp solar field, four 48V battery banks each of 2405Ah C-100, nine solar charge controllers in parallel and three inverter/chargers in a 3-phase system configuration.
Why Studer
For this installation Studer products were chosen due to their high product quality and their excellent communication between solar charge controllers and inverter/chargers making them easy to install and to commission.
Project outcome
The habitants of the Rubiales town is now solely using solar power for their local aqueduct. As additional benefits, its operation is silent and there is no pollution.
Replacing the existing diesel generator with an off-grid system to power the pumping station was not only a technical challenge but it also meant a reorganisation of the pumping stations running times in order to make the system efficient. The pumps are still running 9 hours per day; however, they start a few hours later in order to fully benefit from the power generation close to midday when the sun is at its peak. In the beginning, this change was difficult for the people as they were used to having the water supply already at five o'clock in the morning.
Currently some users do not have water tanks, meters or valves to close the pipes and the clear water waste is big, approximately 30% of the water supply. If they would put in valves to close the pipes and save the water the need for pumping hours would decrease, the availability to water be extended and they could supply water to new users.
Colombia: Oxígeno O2 verde con energía solar 2020
El Proyecto
El Hospital San Juan de Dios ubicado en Puerto Carreño, capital del departamento de Vichada en Colombia brinda servicios de salud de
forma integral.
En Puerto Carreño existen permanentes cortes de energía, intermitencia e interrupción del fluido eléctrico, energía de baja calidad y
racionamientos de energía con"nuos. El Hospital San Juan de Dios desea mejorar su abastecimiento energé"co y contar con un servicio de
energía eléctrica seguro, permanente y estable. La nueva Planta Generadora de Oxigeno fabricada por SPEAL Internacional genera
oxígeno hasta de un 95% de pureza que pasa a las estaciones de llenado compuestas por un compresor de alta presión y un manifold
(colector de gases) para interconectar cilindros (balas) de alta presión de diferentes capacidades, este sistema le permite envasar el
oxigeno que posteriormente se u"lizan para tratar pacientes con afectaciones respiratorias, como el COVID-19. La solución solar híbrida
desarrollada genera energía eléctrica para alimentar la planta generadora de oxígeno, las estaciones de llenado de cilindro y el sistema de
red de distribución de gases medicinales.
La Solución
Solución trifásica híbrida de energía solar para la generación de energía eléctrica para alimentar los equipos de producción de oxígeno verde O2 de grado clínico para el Hospital de Puerto Carreño. Este proyecto fue desarrollado por PRO SOLAR S.A.S. y ERC Ltda Energías Renovables de Colombia para SPEAL y cuenta con la mejor tecnología para ofrecer un sistema energé#co confiable y seguro. Proyecto 100% Sostenible.El sistema fotovoltaico cuenta con 19.875kWp (ampliables) en módulos fotovoltaicos de silicio monocristalino de 375Wp cada uno. El subsistema de almacenamiento está compuesto por un banco a 48V de 54.750kWh de capacidad. Las baterías y la solución
“Plug&Play” están instaladas en un cuarto técnico con aire acondicionado de tecnología inverter y con una temperatura regulada a 25 °C. El Sistema Híbrido Trifásico aprovecha la función de Smart boost con la que cuenta STUDER en los Xtender para asistencia a la fuente, la cual permite la suma de la potencia de los inversores con la de otra fuente que en este caso puede ser la red eléctrica o el grupo electrógeno del hospital.
Por Qué STUDER
STUDER es confiable, seguro y preciso. El soporte técnico y calidad humana en su equipo de trabajo es extraordinario. Los equipos que fabrican son de calidad premium, robustos, alta tecnología, la comunicación es abierta, los reportes y nivel de detalle con el que se puede analizar los sistemas fotovoltaicos es profundo. La garan%a y seguridad de ofrecer un sistema lo más perfecto posible, que nos permita seguir desarrollando proyectos, tener una relación a largo plazo con nuestros clientes y dormir tranquilo y seguro de que todo funciona según lo esperado, con la mejor tecnología y con la certeza de que si pasará algo inesperado con STUDER lo voy a solucionar.
Resultado del Proyecto
La Planta Generadora de Oxígeno, las estaciones de llenado de cilindro y el sistema de red de distribución de gases medicinales actualmente es alimentada con la solución híbrida solar trifásica, se espera la ampliación del sistema y el desarrollo de más proyectos sostenibles similares.
System components
Solución Híbrida Solar Trifásica de 18 KVA compuesta por:
3 x Inversor bidireccional XTH 6000-48-01 Studer
3 x Controlador de carga MPPT VS-120 Studer
24 x Elementos de 2V OPzV 1140 Ah en C100 de BAE
1 x Sistema de control remoto y centro programación RCC-03 Studer
1 x Set de comunicaciones por Internet XCom-LAN Studer
1 x Controlador estado de carga batería BSP Studer
1 x Sensor temperatura baterías BTS-01 Studer
53 x Módulos Fotovoltaicos de Silico Monocristalino de 375 Wp Double Glass con tecnología de Grafeno ZN SHINE SOLAR
1 x Gabinete “Plug&Play” con todas las protecciones en DC y AC integradas, RETIE, monitoreo, barraje de neutros y #erra. PRO SOLAR S.A.S.
Responsible company
Pro Solar S.A.S.
El Proyecto
El Hospital San Juan de Dios ubicado en Puerto Carreño, capital del departamento de Vichada en Colombia brinda servicios de salud de
forma integral.
En Puerto Carreño existen permanentes cortes de energía, intermitencia e interrupción del fluido eléctrico, energía de baja calidad y
racionamientos de energía con"nuos. El Hospital San Juan de Dios desea mejorar su abastecimiento energé"co y contar con un servicio de
energía eléctrica seguro, permanente y estable. La nueva Planta Generadora de Oxigeno fabricada por SPEAL Internacional genera
oxígeno hasta de un 95% de pureza que pasa a las estaciones de llenado compuestas por un compresor de alta presión y un manifold
(colector de gases) para interconectar cilindros (balas) de alta presión de diferentes capacidades, este sistema le permite envasar el
oxigeno que posteriormente se u"lizan para tratar pacientes con afectaciones respiratorias, como el COVID-19. La solución solar híbrida
desarrollada genera energía eléctrica para alimentar la planta generadora de oxígeno, las estaciones de llenado de cilindro y el sistema de
red de distribución de gases medicinales.
La Solución
Solución trifásica híbrida de energía solar para la generación de energía eléctrica para alimentar los equipos de producción de oxígeno verde O2 de grado clínico para el Hospital de Puerto Carreño. Este proyecto fue desarrollado por PRO SOLAR S.A.S. y ERC Ltda Energías Renovables de Colombia para SPEAL y cuenta con la mejor tecnología para ofrecer un sistema energé#co confiable y seguro. Proyecto 100% Sostenible.El sistema fotovoltaico cuenta con 19.875kWp (ampliables) en módulos fotovoltaicos de silicio monocristalino de 375Wp cada uno. El subsistema de almacenamiento está compuesto por un banco a 48V de 54.750kWh de capacidad. Las baterías y la solución
“Plug&Play” están instaladas en un cuarto técnico con aire acondicionado de tecnología inverter y con una temperatura regulada a 25 °C. El Sistema Híbrido Trifásico aprovecha la función de Smart boost con la que cuenta STUDER en los Xtender para asistencia a la fuente, la cual permite la suma de la potencia de los inversores con la de otra fuente que en este caso puede ser la red eléctrica o el grupo electrógeno del hospital.
Por Qué STUDER
STUDER es confiable, seguro y preciso. El soporte técnico y calidad humana en su equipo de trabajo es extraordinario. Los equipos que fabrican son de calidad premium, robustos, alta tecnología, la comunicación es abierta, los reportes y nivel de detalle con el que se puede analizar los sistemas fotovoltaicos es profundo. La garan%a y seguridad de ofrecer un sistema lo más perfecto posible, que nos permita seguir desarrollando proyectos, tener una relación a largo plazo con nuestros clientes y dormir tranquilo y seguro de que todo funciona según lo esperado, con la mejor tecnología y con la certeza de que si pasará algo inesperado con STUDER lo voy a solucionar.
Resultado del Proyecto
La Planta Generadora de Oxígeno, las estaciones de llenado de cilindro y el sistema de red de distribución de gases medicinales actualmente es alimentada con la solución híbrida solar trifásica, se espera la ampliación del sistema y el desarrollo de más proyectos sostenibles similares.
Costa Rica: Barber´s House
El Proyecto
Hace unos 5 años la familia Barber decidió instalarse en Costa Rica en las montañas de Palmar Norte, localizado en la provincia de Puntarenas en el sur del país. Desde su finca dirigen sus negocios internacionales, y han iniciado un pequeño proyecto de servicio de alquiler de viviendas vacacionales orientado para los amantes de la naturaleza.
Dado que sus negocios se operan vía remota, el señor Barber requiere contar con servicios como Internet, electricidad, A/C, seguridad. También necesita servicios para la casa de huéspedes como lavandería, piscina, etc. Por esta razón contaba con un sistema de generación solar. El problema es que este sistema no lograba satisfacer toda la demanda de dos casas completas y los servicios generales.
La propuesta de valor que Interdinamica hizo, consistía en repotenciar el sistema. Por un lado, se incluye un nuevo campo fotovoltaico, agregándolo al existente. Por otro lado, se instalan los nuevos inversores/cargadores STUDER de mayor potencia, capaces de satisfacer la nueva demanda pico. Por último, se añade un nuevo grupo de baterías y se hace una gestión inteligente con la que el grupo electrógeno SDMO pasará a usarse únicamente en casos de emergencia.
La Solución
Se platea la repotenciación y sustitución de equipos de potencia que existían en la casa Barber para obtener una solución eficaz para la operación de la casa principal y la casa de huéspedes, con el fin de reducir la operación del grupo electrógeno a uso de emergencia únicamente.
Se instala un arreglo nuevo fotovoltaico de 5.28kWp que se suma a los 4 kWp anteriores, para disponer de un total de 9.28kWp instalados.
Para el nuevo campo fotovoltaico se decide instalar 2 reguladores solares MPPT VT-80 y un nuevo banco de baterías con capacidad de 2200Ah en C100 a 48V.
Con los 2 nuevos inversores XTH 6000-48-01 se cubre toda la demanda del sistema eléctrico en split phase, 120/240Vac. Con todo esto se consigue cubrir las necesidades de los Barber.
Por Qué STUDER
STUDER brinda sistemas mucho más robustos y flexibles, con mejores prestaciones que cualquier otro fabricante. Alarga los tiempos de autonomía, mejorando la recarga de baterías, vida útil de baterías y reduciendo los períodos de recarga. Además, hay que destacar la garantía extendida que se da de fábrica. Todo ello, hace que los equipos tengan condiciones de retorno de inversión muy deseables para cualquier proyecto.
Resultado del Proyecto
La ejecución del proyecto permitió la reutilización de equipos existentes para la repotenciación del sistema Barber, permitió brindar la estabilidad eléctrica para el proyecto, reducir al mínimo el uso de grupo electrógeno y garantizar la operación automática de las fuentes de generación solar y diésel. El cliente ahora cuenta con un suministro de energía estable 24/7 y puede dar atención a su negocio sin problemas mediante teletrabajo, brindando servicio continuo a los huéspedes alojados en su nuevo proyecto.
System components
2 x Regulador MPPT VT-80 Studer
2 x Inversores XTH-6000-48-01 Studer
1 x Sistema de control RCC-02 Studer
1 x Monitor estado de baterías BSP Studer
1 x Sensor de temperatura BTS-01 Studer
16 x Paneles Solares de 330Wp
16 x Baterías ROLLS 6CS25PS, total 2200Ah en C100
Responsible company
Interdinamica Energía
El Proyecto
Hace unos 5 años la familia Barber decidió instalarse en Costa Rica en las montañas de Palmar Norte, localizado en la provincia de Puntarenas en el sur del país. Desde su finca dirigen sus negocios internacionales, y han iniciado un pequeño proyecto de servicio de alquiler de viviendas vacacionales orientado para los amantes de la naturaleza.
Dado que sus negocios se operan vía remota, el señor Barber requiere contar con servicios como Internet, electricidad, A/C, seguridad. También necesita servicios para la casa de huéspedes como lavandería, piscina, etc. Por esta razón contaba con un sistema de generación solar. El problema es que este sistema no lograba satisfacer toda la demanda de dos casas completas y los servicios generales.
La propuesta de valor que Interdinamica hizo, consistía en repotenciar el sistema. Por un lado, se incluye un nuevo campo fotovoltaico, agregándolo al existente. Por otro lado, se instalan los nuevos inversores/cargadores STUDER de mayor potencia, capaces de satisfacer la nueva demanda pico. Por último, se añade un nuevo grupo de baterías y se hace una gestión inteligente con la que el grupo electrógeno SDMO pasará a usarse únicamente en casos de emergencia.
La Solución
Se platea la repotenciación y sustitución de equipos de potencia que existían en la casa Barber para obtener una solución eficaz para la operación de la casa principal y la casa de huéspedes, con el fin de reducir la operación del grupo electrógeno a uso de emergencia únicamente.
Se instala un arreglo nuevo fotovoltaico de 5.28kWp que se suma a los 4 kWp anteriores, para disponer de un total de 9.28kWp instalados.
Para el nuevo campo fotovoltaico se decide instalar 2 reguladores solares MPPT VT-80 y un nuevo banco de baterías con capacidad de 2200Ah en C100 a 48V.
Con los 2 nuevos inversores XTH 6000-48-01 se cubre toda la demanda del sistema eléctrico en split phase, 120/240Vac. Con todo esto se consigue cubrir las necesidades de los Barber.
Por Qué STUDER
STUDER brinda sistemas mucho más robustos y flexibles, con mejores prestaciones que cualquier otro fabricante. Alarga los tiempos de autonomía, mejorando la recarga de baterías, vida útil de baterías y reduciendo los períodos de recarga. Además, hay que destacar la garantía extendida que se da de fábrica. Todo ello, hace que los equipos tengan condiciones de retorno de inversión muy deseables para cualquier proyecto.
Resultado del Proyecto
La ejecución del proyecto permitió la reutilización de equipos existentes para la repotenciación del sistema Barber, permitió brindar la estabilidad eléctrica para el proyecto, reducir al mínimo el uso de grupo electrógeno y garantizar la operación automática de las fuentes de generación solar y diésel. El cliente ahora cuenta con un suministro de energía estable 24/7 y puede dar atención a su negocio sin problemas mediante teletrabajo, brindando servicio continuo a los huéspedes alojados en su nuevo proyecto.
Cyprus: Off-grid system for trout farm
The Challenge
There is not much freshwater available on Cyprus. For this reason most freshwater fish farms are small-scale and located in the mountains far away from the utility grid, where they use springs and rivers as water intake. Initially this facility was completely powered by diesel. However, as the need for power grew steadily, it became too expensive to run the farm only on diesel and the fish farmer started to look for alternative energy solutions.
The Solution
A trout farm needs to run machines, pumps and industrial refrigerators for its operation. Such loads necessitate electric power in three-phase. Situated close to a small stream, this fish farm can take advantage of both solar and hydraulic power in its new energy system.
Why Studer
It was the reliability of Studer Innotec's products, knowing that they would do the job without problems or malfunctioning, that made them the natural choice for this remote installation.
Project outcome
The three-phase 240VAC system has been working perfectly since its installation providing the trout farm and its staff with enough energy to successfully operate the facility with machines and pumps. After harvest, the fish is immediately stored in large refrigerators at -38˚C keeping them fresh until the transport to the distribution channels.
There are plans to extend the system by adding three more hydro turbines to provide even further power.
System components
Responsible company
Pals
The Challenge
There is not much freshwater available on Cyprus. For this reason most freshwater fish farms are small-scale and located in the mountains far away from the utility grid, where they use springs and rivers as water intake. Initially this facility was completely powered by diesel. However, as the need for power grew steadily, it became too expensive to run the farm only on diesel and the fish farmer started to look for alternative energy solutions.
The Solution
A trout farm needs to run machines, pumps and industrial refrigerators for its operation. Such loads necessitate electric power in three-phase. Situated close to a small stream, this fish farm can take advantage of both solar and hydraulic power in its new energy system.
Why Studer
It was the reliability of Studer Innotec's products, knowing that they would do the job without problems or malfunctioning, that made them the natural choice for this remote installation.
Project outcome
The three-phase 240VAC system has been working perfectly since its installation providing the trout farm and its staff with enough energy to successfully operate the facility with machines and pumps. After harvest, the fish is immediately stored in large refrigerators at -38˚C keeping them fresh until the transport to the distribution channels.
There are plans to extend the system by adding three more hydro turbines to provide even further power.
Ecuador: 1500 Instalaciones de Electrificación Rural
El Proyecto
El proyecto contempla la electrificación de comunidades Shuar en la provincia de Morona Santiago, con el uso de energías renovables, liderada por la Empresa Eléctrica Regional Centro Sur C. A. por intermedio de la Unidad de Energías Renovables, donde se implementaron 1.500 sistemas solares fotovoltaicos individuales de 150Wp.
Este proyecto es financiado por el MEER (Ministerio de Electricidad y Energía Renovable), y por la Empresa Eléctrica Centro Sur, destinado a proveer de energía a los sectores menos atendidos de la población, cumpliendo con su responsabilidad social de atender con energía eléctrica a la población de su región de concesión.
La Solución
En total el proyecto da solución eléctrica por medio de sistemas solares residenciales que a demás de preservar le medio ambiente y el entorno, mejoran la calidad de vida de las poblaciones extremadamente alejadas proporcionando energía para iluminación, radio, computador, televisor, DVD, cargador de pilas, linternas.
Por Qué STUDER
Se consideró la instalación de este equipo por las protecciones eléctricas ofrecidas, por su nivel de protección IP, y por desempeño y por su robustez.
Resultado del Proyecto
Las instalaciones realizadas han permitido a familias mejorar su calidad de vida, disponiendo en sus hogares de electricidad para satisfacer necesidades básicas tales como iluminación y el acceso a escuchar la radio, televisión, etc., de lo que estuvieron privados por el aislamiento con respecto a los centros poblados del país.
Ha mejorado su nivel de educación, y ahora pueden acceder al servicio, con una organización de sostenibilidad del proyecto, por medio del mismo mantenimiento de la EECS, y el empoderamiento de la comunidad al proyecto.
System components
1 x Inversor marca STUDER AJ 275-12-01
1 x Panel de 150 Wp
1 x Batería libre de mantenimiento de 150 Ah 12 Vdc
1 x Regulador de 12 Vdc 20 Amp
3 x Focos ahorradores de 15 W, 110Vac & 60 Hz
Responsible company
EnerPro Cía Ltda
El Proyecto
El proyecto contempla la electrificación de comunidades Shuar en la provincia de Morona Santiago, con el uso de energías renovables, liderada por la Empresa Eléctrica Regional Centro Sur C. A. por intermedio de la Unidad de Energías Renovables, donde se implementaron 1.500 sistemas solares fotovoltaicos individuales de 150Wp.
Este proyecto es financiado por el MEER (Ministerio de Electricidad y Energía Renovable), y por la Empresa Eléctrica Centro Sur, destinado a proveer de energía a los sectores menos atendidos de la población, cumpliendo con su responsabilidad social de atender con energía eléctrica a la población de su región de concesión.
La Solución
En total el proyecto da solución eléctrica por medio de sistemas solares residenciales que a demás de preservar le medio ambiente y el entorno, mejoran la calidad de vida de las poblaciones extremadamente alejadas proporcionando energía para iluminación, radio, computador, televisor, DVD, cargador de pilas, linternas.
Por Qué STUDER
Se consideró la instalación de este equipo por las protecciones eléctricas ofrecidas, por su nivel de protección IP, y por desempeño y por su robustez.
Resultado del Proyecto
Las instalaciones realizadas han permitido a familias mejorar su calidad de vida, disponiendo en sus hogares de electricidad para satisfacer necesidades básicas tales como iluminación y el acceso a escuchar la radio, televisión, etc., de lo que estuvieron privados por el aislamiento con respecto a los centros poblados del país.
Ha mejorado su nivel de educación, y ahora pueden acceder al servicio, con una organización de sostenibilidad del proyecto, por medio del mismo mantenimiento de la EECS, y el empoderamiento de la comunidad al proyecto.
Ecuador: Gobierno autonomo descenralizado Parroquial de Montalvo
El Proyecto
El GADP de Montalvo ubicado en la mitad de la selva del Ecuador, para realizar sus funciones tenían que viajar semanalmente a la Capital de la Provincia de Pastaza, ya sea por avioneta o en canoa, en cuyo caso el viaje es de 8 horas hasta el Puerto Canelos y 2 horas más en carro hasta la ciudad del Puyo.
Esto significaba un gran gasto del presupuesto en pago de viajes, alimentación y hospedaje, limitando mucho sus obras en la comunidad. Por tal motivo, se decidieron a construir las oficinas en el centro poblado, teniendo todos los equipos y sistemas de comunicación necesarios.
Para satisfacer la demanda de energía se tenían las opciones de un grupo electrógeno a diésel o un sistema fotovoltaico. La primera opción significaba que cada 15 días se debía viajar en canoa a la capital teniendo un costo de 400USD, incluyendo el costo del combustible, por lo cual se decidió que el sistema de energía solar es la opción más viable.
El sistema fotovoltaico debe satisfacer la demanda de energía de 6 oficinas con iluminación, computadoras, impresoras, equipos varios y el sistema de internet satelital, para que los funcionarios puedan trabajar por lo menos 8 horas al día y brindar internet a las personas de la comunidad por 24 horas.
La Solución
Para el diseño del sistema del GADP de Montalvo, se estimó la demanda de energía en 35kWh al día y una demanda de potencia máxima de 6kVA para equipos en sistema split phase 120-240Vac. El sistema fotovoltaico tiene 13KWp de potencia en paneles solares, 48 baterías estacionarias de 150Ah y electrolito de GEL, los controladores MPPT de 80 amperios y dos inversores de 4kVA cada uno. Se tomaron en cuenta la limitación del transporte por vía fluvial para el diseño y construcción de estructuras.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones remotas de equipos y que sumado a su flexibilidad, robustez y 10 años de garantía constituyen las principales razones para su elección.
Resultado del Proyecto
La ejecución del proyecto permitió a la Junta Parroquial de Montalvo realizar sus labores de manera más eficiente al ahorrar los recursos y reducir sus viajes a la ciudad del Puyo, además de ser mas amigables con el medio ambiente al descartar el uso de combustibles fósiles.
System components
3 x Controladores de carga STUDER VT-80
1 x Sistema de control STUDER RCC-02
2 x Inversores STUDER XTM 4000-48-01
48 x Paneles Solares de 270Wp
48 x Baterías de GEL de 150Ah@C10/12VDC
Responsible company
ProViento S.A.
El Proyecto
El GADP de Montalvo ubicado en la mitad de la selva del Ecuador, para realizar sus funciones tenían que viajar semanalmente a la Capital de la Provincia de Pastaza, ya sea por avioneta o en canoa, en cuyo caso el viaje es de 8 horas hasta el Puerto Canelos y 2 horas más en carro hasta la ciudad del Puyo.
Esto significaba un gran gasto del presupuesto en pago de viajes, alimentación y hospedaje, limitando mucho sus obras en la comunidad. Por tal motivo, se decidieron a construir las oficinas en el centro poblado, teniendo todos los equipos y sistemas de comunicación necesarios.
Para satisfacer la demanda de energía se tenían las opciones de un grupo electrógeno a diésel o un sistema fotovoltaico. La primera opción significaba que cada 15 días se debía viajar en canoa a la capital teniendo un costo de 400USD, incluyendo el costo del combustible, por lo cual se decidió que el sistema de energía solar es la opción más viable.
El sistema fotovoltaico debe satisfacer la demanda de energía de 6 oficinas con iluminación, computadoras, impresoras, equipos varios y el sistema de internet satelital, para que los funcionarios puedan trabajar por lo menos 8 horas al día y brindar internet a las personas de la comunidad por 24 horas.
La Solución
Para el diseño del sistema del GADP de Montalvo, se estimó la demanda de energía en 35kWh al día y una demanda de potencia máxima de 6kVA para equipos en sistema split phase 120-240Vac. El sistema fotovoltaico tiene 13KWp de potencia en paneles solares, 48 baterías estacionarias de 150Ah y electrolito de GEL, los controladores MPPT de 80 amperios y dos inversores de 4kVA cada uno. Se tomaron en cuenta la limitación del transporte por vía fluvial para el diseño y construcción de estructuras.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones remotas de equipos y que sumado a su flexibilidad, robustez y 10 años de garantía constituyen las principales razones para su elección.
Resultado del Proyecto
La ejecución del proyecto permitió a la Junta Parroquial de Montalvo realizar sus labores de manera más eficiente al ahorrar los recursos y reducir sus viajes a la ciudad del Puyo, además de ser mas amigables con el medio ambiente al descartar el uso de combustibles fósiles.
Egypt: Off-grid system for street-lighting
The challenge
Conventional street-lighting projects and installations face difficulties regarding the ongoing system maintenance. When the batteries are installed in enclosures on the poles, especially in desert-like climates like Egypt, the environment is very harsh which effects the lifespan of the batteries.
Keeping the solar panels clean and sand/dust free in desert environments is also a big challenge and it makes ongoing system maintenance of single street-light installations very problematic.
The solution
With a centralized system, it is possible to not only better control the environment where the batteries and power electronics is installed, but the maintenance is also much more manageable. With a centralized PV array, it is also significantly easier to clean and maintain the solar panels ensuring maximum yield.
Why STUDER
Because of the location of the system, reliability of the equipment was critically important. The temperatures and dust levels in this part of Egypt gets very high and the Studer devices robustness and performance in harsh climates appealed to the customer - by registering the system installation, the customer could also access the Studer 10-year warranty. The setup of the system is also easy in terms of the charge cycle of the batteries because the VarioString units are synchronized with the Xtenders. The generator auto-start is also managed very easily by battery SOC, voltage and/or time of day.
Project outcome
With this system design, because of the improved environment and maintenance procedures, the lifespan of system components is prolonged. The PV array is ensuring the full re-charge of the battery bank and the Studer power electronics, managing all aspects of the system functionality. Because of the remote communication capabilities, the system can also be managed from anywhere in the world via the Studer portal.
System components
128 kWp PV solar modules
192x 2V battery cells each C20=3780 Ah, OPzS Tubular Batteries
12x STUDER Xtender inverter/charger, XTH 6000-48, 230Vac / 50Hz
20x STUDER VarioString solar charge controller, VS-120
4x STUDER remote control RCC-03
2x STUDER Xcom-LAN communication device
2x STUDER BSP-1200 battery status processors
1x STUDER BTS-01
Responsible company
Hammer Electric S.A.E
The challenge
Conventional street-lighting projects and installations face difficulties regarding the ongoing system maintenance. When the batteries are installed in enclosures on the poles, especially in desert-like climates like Egypt, the environment is very harsh which effects the lifespan of the batteries.
Keeping the solar panels clean and sand/dust free in desert environments is also a big challenge and it makes ongoing system maintenance of single street-light installations very problematic.
The solution
With a centralized system, it is possible to not only better control the environment where the batteries and power electronics is installed, but the maintenance is also much more manageable. With a centralized PV array, it is also significantly easier to clean and maintain the solar panels ensuring maximum yield.
Why STUDER
Because of the location of the system, reliability of the equipment was critically important. The temperatures and dust levels in this part of Egypt gets very high and the Studer devices robustness and performance in harsh climates appealed to the customer - by registering the system installation, the customer could also access the Studer 10-year warranty. The setup of the system is also easy in terms of the charge cycle of the batteries because the VarioString units are synchronized with the Xtenders. The generator auto-start is also managed very easily by battery SOC, voltage and/or time of day.
Project outcome
With this system design, because of the improved environment and maintenance procedures, the lifespan of system components is prolonged. The PV array is ensuring the full re-charge of the battery bank and the Studer power electronics, managing all aspects of the system functionality. Because of the remote communication capabilities, the system can also be managed from anywhere in the world via the Studer portal.
El Salvador: Electrificación Rural - Isla Perico
El Proyecto
La Iniciativa Regional de Energía Limpia (RCEI) auspiciado por la Agencia de los Estados Unidos para el Desarrollo Internacional (USAID) sometió a concurso público lo siguiente:
“Contratación del suministro, instalación y puesta en funcionamiento de 33 sistemas solares aislados en la comunidad de la Isla Perico en la bahía del departamento de la Unión en El Salvador con el propósito de llevar una solución de mejora en el estilo de vida a los pobladores de dicho lugar, para el desarrollo social y económico de la comunidad“.
Ingeniería solar (división SEESA), empresa con mas de 15 años en el desarrollo de sistemas solares en el país y comprometida con la implementación de energías renovables, trazó el objetivo estratégico en respetar su entorno y cuidar el medio ambiente, como empresa responsable que es con el medio ambiente.
Es por ello por lo que a solicitud de la iniciativa de USAID en cuanto a los términos de referencia y características de los equipos, se encontró en STUDER una solución muy valorada por SEESA para trabajar en zonas con entorno y condiciones climáticas muy adversas, propias de la bahía.
La Solución
Suministrar equipos de alta tecnología para la generación de energía eléctrica a través de sistemas fotovoltaicos a los habitantes de la Isla Perico. Gracias a esto se cumple con el objetivo de mejorar su desarrollo social y comercial en la zona.
Por Qué STUDER
STUDER cumple con los estándares de trabajo que exige las normas establecidas por USAID para dotar de una mejor vida a los habitantes. La serie de inversores AJ de STUDER cumple con todos los requisitos de calidad y confiabilidad requeridos por USAID.
Resultado del Proyecto
La solución ofrece una mejor calidad de vida a las personas de la isla, lo cual beneficia en el desarrollo comercial para cada uno de los habitantes incrementando su producción pesquera. Se consigue eliminar el consumo de gasolina que se utilizaba para la iluminación.
System components
1 x Inversor AJ 500-12-01 STUDER
1 x Panel Solares de 190W a 12V. EverExceed
1 x Batería Litio-ion LiFePo4 100Ah
1 x Regulador solar PS-MPPT-25-PS- MORNINGSTAR
Protecciones eléctricas
Responsible company
Suministros Eléctricos y Electrónicos S.A (SEESA)
El Proyecto
La Iniciativa Regional de Energía Limpia (RCEI) auspiciado por la Agencia de los Estados Unidos para el Desarrollo Internacional (USAID) sometió a concurso público lo siguiente:
“Contratación del suministro, instalación y puesta en funcionamiento de 33 sistemas solares aislados en la comunidad de la Isla Perico en la bahía del departamento de la Unión en El Salvador con el propósito de llevar una solución de mejora en el estilo de vida a los pobladores de dicho lugar, para el desarrollo social y económico de la comunidad“.
Ingeniería solar (división SEESA), empresa con mas de 15 años en el desarrollo de sistemas solares en el país y comprometida con la implementación de energías renovables, trazó el objetivo estratégico en respetar su entorno y cuidar el medio ambiente, como empresa responsable que es con el medio ambiente.
Es por ello por lo que a solicitud de la iniciativa de USAID en cuanto a los términos de referencia y características de los equipos, se encontró en STUDER una solución muy valorada por SEESA para trabajar en zonas con entorno y condiciones climáticas muy adversas, propias de la bahía.
La Solución
Suministrar equipos de alta tecnología para la generación de energía eléctrica a través de sistemas fotovoltaicos a los habitantes de la Isla Perico. Gracias a esto se cumple con el objetivo de mejorar su desarrollo social y comercial en la zona.
Por Qué STUDER
STUDER cumple con los estándares de trabajo que exige las normas establecidas por USAID para dotar de una mejor vida a los habitantes. La serie de inversores AJ de STUDER cumple con todos los requisitos de calidad y confiabilidad requeridos por USAID.
Resultado del Proyecto
La solución ofrece una mejor calidad de vida a las personas de la isla, lo cual beneficia en el desarrollo comercial para cada uno de los habitantes incrementando su producción pesquera. Se consigue eliminar el consumo de gasolina que se utilizaba para la iluminación.
Eritrea: Back-up System
The challenge
At the Orotta hospital, in Asmara, Eritrea, wards such as the children's paediatric cardiac surgery and neonatology are extremely sensitive to power failure. As the Eritrean grid is not stable, the hospital needs to secure the existing electrical installations. Until now, the hospital used a diesel generator as backup but the solar irradiance in Eritrea is very high which makes it extremely favourable for the use of PV. Therefore, a PV system was chosen to guarantee a reliable power supply for the Orotta hospital in case of power failure.
The solution
The new backup solar system with priority loads provides two vital hospital wards with secure and uninterruptible power supply. Now a battery bank, which is additionally solar fed with a PV-generator, supplies the most important consumers in the operating theatre and the maternity room without interruption during power blackouts.
The system is designed to provide 60kWh of daily production with the inverter/chargers providing a 42kW peak load. This way, it can provide around seven hours of power during operation daily without grid or diesel generator, and four hours without sun.
PV generator 14,4 kWp, Battery bank 124 kWh storage capacity.
For the power management, components from Studer Innotec are used: three VarioTrack MPPT charge controllers, VT-80, six Xtender inverter/chargers XTH 8000-48 and a remote control guarantee a reliable energy management.
The system, installed by the Phaesun Asmara team, has been financed by the non-profit organisation Archemed which supports public hospitals.
Why Studer
Perfect electronics to guarantee the power supply without interruptions.
Project outcome
The doctors, nurses and patients at the Orotta hospital are now equipped with a reliable backup solar system to guarantee that there will always be a sufficient energy supply and that there is no risk that lights or medical appliances will shut down during an operation.
System components
Responsible company
Phaesun
The challenge
At the Orotta hospital, in Asmara, Eritrea, wards such as the children's paediatric cardiac surgery and neonatology are extremely sensitive to power failure. As the Eritrean grid is not stable, the hospital needs to secure the existing electrical installations. Until now, the hospital used a diesel generator as backup but the solar irradiance in Eritrea is very high which makes it extremely favourable for the use of PV. Therefore, a PV system was chosen to guarantee a reliable power supply for the Orotta hospital in case of power failure.
The solution
The new backup solar system with priority loads provides two vital hospital wards with secure and uninterruptible power supply. Now a battery bank, which is additionally solar fed with a PV-generator, supplies the most important consumers in the operating theatre and the maternity room without interruption during power blackouts.
The system is designed to provide 60kWh of daily production with the inverter/chargers providing a 42kW peak load. This way, it can provide around seven hours of power during operation daily without grid or diesel generator, and four hours without sun.
PV generator 14,4 kWp, Battery bank 124 kWh storage capacity.
For the power management, components from Studer Innotec are used: three VarioTrack MPPT charge controllers, VT-80, six Xtender inverter/chargers XTH 8000-48 and a remote control guarantee a reliable energy management.
The system, installed by the Phaesun Asmara team, has been financed by the non-profit organisation Archemed which supports public hospitals.
Why Studer
Perfect electronics to guarantee the power supply without interruptions.
Project outcome
The doctors, nurses and patients at the Orotta hospital are now equipped with a reliable backup solar system to guarantee that there will always be a sufficient energy supply and that there is no risk that lights or medical appliances will shut down during an operation.
France: Armoire SUN.CONNECT 8kVA avec batteries Nickel-Fer
Le Défi
Réduire les consommations du client en journée, augmenter le taux d’auto-consommation grâce au stockage, apporter une solution batterie fiable, low-tech, robuste, et sécuriser l’alimentation électrique de l’habitation. Fournir un système solaire rapide à installer dans une armoire pré-intégrée et pré-configurée, afin de gagner du temps en commissioning et en installation chez le client final.
Pourquoi STUDER
Les onduleurs Studer répondent aux caractéristiques spécifiques de tension des batteries Nickel-Fer (plage de tension de travail plus large que n’importe quel autre onduleur sur le marché). La durée de vie des appareils Studer est élevée et nous pouvons proposer à notre client une garantie de 10 ans sur l’électronique de conversion et de puissance. De plus, la grande flexibilité de paramétrage des appareils Studer nous permet une finesse de réglage inégalée sur le marché des onduleurs batteries, notamment sur l’aspect gestion de cycle batterie.
La Solution
Afin de proposer un système Solaire hybride fiable avec des composants européens, nous avons tout logiquement fait le choix de composants Studer Innotec. Leur grande qualité de fabrication et leur fiabilité légendaire nous permet de proposer à nos clients finaux des systems hybrides de grande qualité. Le client consomme désormais majoritairement en journée au fil du soleil grâce aux deux chargeurs VarioString VS-70, et le complement est apporté par l’énergie stockée dans les batteries, en configuration battery priority. Nous intégrons tous les composants Studer en solution pré-câblée dans une armoire SUN.CONNECT, afin de proposer à nos clients et à notre reseau d’installateurs des systems clefs en mains, rapide à installer, et pré-configurés.
Les résultats du projet
Le taux d’autarcie du client depuis l’installation du système Solaire est d’environ 70%, et le projet a terme est de se déconnecter définitivement d’EDF. Les systems Studer sont évolutifs et nous pourrons rajouter ultérieurement un troisième chargeur VS-70 si necessaire.
System components
1x XTH-8000-48V
2x VS-70
1x RCC-03
BSP 500
20x Trina Solar 375Wc
Parc Nickel-Fer 500Ah-48V
Responsible company
Perma-Batteries
Le Défi
Réduire les consommations du client en journée, augmenter le taux d’auto-consommation grâce au stockage, apporter une solution batterie fiable, low-tech, robuste, et sécuriser l’alimentation électrique de l’habitation. Fournir un système solaire rapide à installer dans une armoire pré-intégrée et pré-configurée, afin de gagner du temps en commissioning et en installation chez le client final.
Pourquoi STUDER
Les onduleurs Studer répondent aux caractéristiques spécifiques de tension des batteries Nickel-Fer (plage de tension de travail plus large que n’importe quel autre onduleur sur le marché). La durée de vie des appareils Studer est élevée et nous pouvons proposer à notre client une garantie de 10 ans sur l’électronique de conversion et de puissance. De plus, la grande flexibilité de paramétrage des appareils Studer nous permet une finesse de réglage inégalée sur le marché des onduleurs batteries, notamment sur l’aspect gestion de cycle batterie.
La Solution
Afin de proposer un système Solaire hybride fiable avec des composants européens, nous avons tout logiquement fait le choix de composants Studer Innotec. Leur grande qualité de fabrication et leur fiabilité légendaire nous permet de proposer à nos clients finaux des systems hybrides de grande qualité. Le client consomme désormais majoritairement en journée au fil du soleil grâce aux deux chargeurs VarioString VS-70, et le complement est apporté par l’énergie stockée dans les batteries, en configuration battery priority. Nous intégrons tous les composants Studer en solution pré-câblée dans une armoire SUN.CONNECT, afin de proposer à nos clients et à notre reseau d’installateurs des systems clefs en mains, rapide à installer, et pré-configurés.
Les résultats du projet
Le taux d’autarcie du client depuis l’installation du système Solaire est d’environ 70%, et le projet a terme est de se déconnecter définitivement d’EDF. Les systems Studer sont évolutifs et nous pourrons rajouter ultérieurement un troisième chargeur VS-70 si necessaire.
France: ESS Lithium System
Le Défi
Proposer une solution solaire hybride avec du stockage dont la capacité peut évoluer.
Les solutions BYD B BOX Pro, basées sur des cellules au phosphate de fer lithié, répondent à cette attente et fournissent une armoire modulaire capable d'accueillir jusqu'à 10 kWh de capacité, voire plus si mise en parallèle de plusieurs unités. En choisissant les meilleurs composants du marché, nous offrons au client final un système performant, cohérent techniquement (gestion de la charge batterie et optimisation de l'autoconsommation) et fiable (garantie 10 ans STUDER & BYD).
Pourquoi STUDER
Robustesse, garantie de 10 ans, facilité de mise en service, grande performance des produits! La solution VS-70 + XTM est unique sur le marché et permet d'y adjoindre un champ solaire d'un seul string, tout en restant en couplage DC, et en bénéficiant d'une tension supérieure (de 100 à 600VCC). Le rendement global du système avec une ba! erie lithium est op"mal (~ 90%).
La Solution
Système Studer Xtender avec un onduleur XTMen DC coupling sur un VS-70 et une BYD B BOX de 5 kWh.
Les résultats du projet
Réduction de sa facture d'électricité, augmentation de son autoconsommation, lissage des évolutions futures des coûts d'électricité.
System components
3960Wc PV Power en couplage DC sur un XTM-4kVA avec un
VS-70.
10xTrina Solar M 330W half-cut
1x BYD B BOX PRO 5.0 kWh
1x XTM 4000-48V
1x Variostring-70
XCom-232i
RCC-02 + XCom-CAN
Responsible company
Perma-Batteries
Le Défi
Proposer une solution solaire hybride avec du stockage dont la capacité peut évoluer.
Les solutions BYD B BOX Pro, basées sur des cellules au phosphate de fer lithié, répondent à cette attente et fournissent une armoire modulaire capable d'accueillir jusqu'à 10 kWh de capacité, voire plus si mise en parallèle de plusieurs unités. En choisissant les meilleurs composants du marché, nous offrons au client final un système performant, cohérent techniquement (gestion de la charge batterie et optimisation de l'autoconsommation) et fiable (garantie 10 ans STUDER & BYD).
Pourquoi STUDER
Robustesse, garantie de 10 ans, facilité de mise en service, grande performance des produits! La solution VS-70 + XTM est unique sur le marché et permet d'y adjoindre un champ solaire d'un seul string, tout en restant en couplage DC, et en bénéficiant d'une tension supérieure (de 100 à 600VCC). Le rendement global du système avec une ba! erie lithium est op"mal (~ 90%).
La Solution
Système Studer Xtender avec un onduleur XTMen DC coupling sur un VS-70 et une BYD B BOX de 5 kWh.
Les résultats du projet
Réduction de sa facture d'électricité, augmentation de son autoconsommation, lissage des évolutions futures des coûts d'électricité.
France: Lithium-powered Off-grid site
The challenge
Situated 10 km from the utility grid in a rural area next to Bourges, France, these two yurts needed a year-round reliable and cost-effective off-grid energy system. The owner was looking for a flexible system where it would be easy to scale up the battery capacity if needed.
Also, in order to avoid partial shading from the surrounding trees and vegetation, the solar modules would have to be installed relatively far away from the battery and electronics.
The solution
Pylontech US2000B lithium batteries were selected for their numerous advantages: delivery of up to 5kW of power per module, having a long cycle life at 90% DOD, being safe to operate (LFP chemistry), and can be upgraded later if extra capacity is needed. Studer Innotec's high-voltage VS-70 MPPT solar charge controller facilitates string wiring and has a very high efficiency, overcoming the voltage drop that conventional MPPT controllers have. The XTM-4000-48V perfectly manages the batteries' charging cycles using a multiprotocol communication module Xcom-CAN. Supervision and monitoring is ensured by an Xcom-LAN.
Why Studer
Since our inception, we have chosen to work with Studer equipment, as they are the only inverters that guarantee a perfect management of the storage systems we use, whether it's Li-Ion systems or unconventional chemistry such as Nickel-Iron that requires a specific voltage range. Their unrivalled robustness enables us to provide our customers with a reliable and long-lasting system. What's more, the Xcom-LAN gives us a perfect real-time monitoring and remote control of the system for after-sales support or troubleshooting if needed.
Project outcome
The Studer/Pylontech combination provides year-round autonomy to the end-user and drastically reduces his dependency on a generator. The high quality of the components brings peace of mind to the customer, ensuring that his energetic needs are backed by a dependable and durable system that can be extended if required.
System components
10 x Q-CELLS monocrystalline Q-Peak BFR 4.1 305W
1 x STUDER inverter/charger Xtender XTM-4000-48V
1 x STUDER MPPT Solar Charge Controller VarioString VS-70
1 x STUDER Xcom-LAN communication device
1 x STUDER Xcom-CAN multi-protocol communication module
3 x LiFePO4 PYLONTECH US2000B
Responsible company
Perma-Batteries
The challenge
Situated 10 km from the utility grid in a rural area next to Bourges, France, these two yurts needed a year-round reliable and cost-effective off-grid energy system. The owner was looking for a flexible system where it would be easy to scale up the battery capacity if needed.
Also, in order to avoid partial shading from the surrounding trees and vegetation, the solar modules would have to be installed relatively far away from the battery and electronics.
The solution
Pylontech US2000B lithium batteries were selected for their numerous advantages: delivery of up to 5kW of power per module, having a long cycle life at 90% DOD, being safe to operate (LFP chemistry), and can be upgraded later if extra capacity is needed. Studer Innotec's high-voltage VS-70 MPPT solar charge controller facilitates string wiring and has a very high efficiency, overcoming the voltage drop that conventional MPPT controllers have. The XTM-4000-48V perfectly manages the batteries' charging cycles using a multiprotocol communication module Xcom-CAN. Supervision and monitoring is ensured by an Xcom-LAN.
Why Studer
Since our inception, we have chosen to work with Studer equipment, as they are the only inverters that guarantee a perfect management of the storage systems we use, whether it's Li-Ion systems or unconventional chemistry such as Nickel-Iron that requires a specific voltage range. Their unrivalled robustness enables us to provide our customers with a reliable and long-lasting system. What's more, the Xcom-LAN gives us a perfect real-time monitoring and remote control of the system for after-sales support or troubleshooting if needed.
Project outcome
The Studer/Pylontech combination provides year-round autonomy to the end-user and drastically reduces his dependency on a generator. The high quality of the components brings peace of mind to the customer, ensuring that his energetic needs are backed by a dependable and durable system that can be extended if required.
France: Skid SUNCONNECT 4000 avec batteries au titanate de lithium Zenaji Aeon
Le Défi
Fournir un système hybride fiable de back-up pour sécuriser les appareils critiques (circulateur pour une Chaudière à granulé), et permettre d’augmenter le taux d’auto-consommation du client. Coupures EDF fréquentes entrainant des pannes sur certains composants sensibles du client (Chaudière à granule). Maximiser la pérénité du système en choissisant les composants les plus performants et durables du marché.
Pourquoi STUDER
Les onduleurs Studer répondent aux caractéristiques spécifiques des batteries au titanate de lithium Zenaji Aeon. La durée de vie des appareils Studer est élevée (20 ans) et nous pouvons proposer à notre client une garantie de 10 ans sur l’électronique de conversion et de puissance. La chimie LTO nécessite des plages de tension spécifiques et des réglages adaptés, que nous pouvons obtenir grâce à la grande souplesse de réglage du BSP et du système Xtender dans son ensemble.
La Solution
Afin de proposer un système Solaire hybride fiable avec des composants européens, nous avons tout logiquement fait le choix de composants Studer Innotec. Leur grande qualité de fabrication et leur fiabilité légendaire nous permet de proposer à nos clients finaux des systems hybrides de grande qualité. Le client consomme désormais majoritairement en journée au fil du soleil grâce aux deux chargeurs VarioString VS-70, et le complement est apporté par l’énergie stockée dans les batteries, en configuration battery priority. Nous intégrons tous les composants Studer en solution pré-câblée dans une armoire SUN.CONNECT, afin de proposer à nos clients et à notre reseau d’installateurs des systems clefs en mains, rapide à installer, et pré-configurés.
Les résultats du projet
Les appareils critiques sont sécurisés, le système de chauffage du client continue de fonctionner même en cas de coupure EDF, la longévité des cartes électroniques embarquées dans les chaudières à bois sera optimisé (plus de micro-coupures). Par ailleurs, les hausses d’électricité à venir sont lissés grâce au taux d’auto-consommation élevé obtenu via le stockage. Les systems Studer sont évolutifs et nous pourrons rajouter des batteries Zenaji, ainsi que d’autres chargeurs VS-70.
System components
1x XTM-4000-48V
1x VS-70
1x RCC-02
1xBSP 500
12x QCELLS 350W G8+
2x batteries LTO Zenaji Aeon de 1.9 kWh
Responsible company
Perma-Batteries
Le Défi
Fournir un système hybride fiable de back-up pour sécuriser les appareils critiques (circulateur pour une Chaudière à granulé), et permettre d’augmenter le taux d’auto-consommation du client. Coupures EDF fréquentes entrainant des pannes sur certains composants sensibles du client (Chaudière à granule). Maximiser la pérénité du système en choissisant les composants les plus performants et durables du marché.
Pourquoi STUDER
Les onduleurs Studer répondent aux caractéristiques spécifiques des batteries au titanate de lithium Zenaji Aeon. La durée de vie des appareils Studer est élevée (20 ans) et nous pouvons proposer à notre client une garantie de 10 ans sur l’électronique de conversion et de puissance. La chimie LTO nécessite des plages de tension spécifiques et des réglages adaptés, que nous pouvons obtenir grâce à la grande souplesse de réglage du BSP et du système Xtender dans son ensemble.
La Solution
Afin de proposer un système Solaire hybride fiable avec des composants européens, nous avons tout logiquement fait le choix de composants Studer Innotec. Leur grande qualité de fabrication et leur fiabilité légendaire nous permet de proposer à nos clients finaux des systems hybrides de grande qualité. Le client consomme désormais majoritairement en journée au fil du soleil grâce aux deux chargeurs VarioString VS-70, et le complement est apporté par l’énergie stockée dans les batteries, en configuration battery priority. Nous intégrons tous les composants Studer en solution pré-câblée dans une armoire SUN.CONNECT, afin de proposer à nos clients et à notre reseau d’installateurs des systems clefs en mains, rapide à installer, et pré-configurés.
Les résultats du projet
Les appareils critiques sont sécurisés, le système de chauffage du client continue de fonctionner même en cas de coupure EDF, la longévité des cartes électroniques embarquées dans les chaudières à bois sera optimisé (plus de micro-coupures). Par ailleurs, les hausses d’électricité à venir sont lissés grâce au taux d’auto-consommation élevé obtenu via le stockage. Les systems Studer sont évolutifs et nous pourrons rajouter des batteries Zenaji, ainsi que d’autres chargeurs VS-70.
France: Système off-grid TESVOLT & Studer
Le Défi
Proposer une solution performante, durable et evolutive pour l’alimentation d’un site isolé dans l’Hérault.
Pourquoi STUDER
Robustesse, garantie de 10 ans, facilité de mise en service, grande performance des produits! La solution VS-70 + XTH est unique sur le marché et permet d'y adjoindre un champ solaire d'un seul string, tout en restant en couplage DC, et en bénéficiant d'une tension supérieure (de 100 à 600VCC). L’association TESVOLT+Studer est la plus performante pour des projets off-grid nécessitant puissance, fiabilité, performance et évolutivité.
La Solution
Nous avons fait le choix d’un système zero compromis, avec les meilleurs composants du marché : un onduleur-chargeur Studer XTH-8000, couplé via deux Variostring-70 à 7400W de panneaux back-contact LG NeON R, avec une batterie TESVOLT à BMS actif de 14.4 kWh. Nous avons également un générateur de secours (un SDMO 10kVA) piloté par le Studer en fonction du SOC batterie. Les garanties produits proposés (10 ans batterie + électronique et 25 ans pour les modules solaires) sécurisent l’investissement du client. Les batteries lithium TESVOLT (cellules Samsung) sont uniques de part leur équilibrage actif, qui permet l’ajout ultérieur de modules au delà d’un an après la mise en service initiale. Leur durée de vie est élevée (> 8000 cycles à 1C, 100% DOD).
Les résultats du projet
Couverture à 95% des consommations à l’année via le système, réduction des usages du groupe électrogène, fiabilité maximale, et monitoring facilité pour le client via l’application Studer sur smartphone.
System components
1x TESVOLT TS40 14.4 kWh
2x VS-70
1x XTH-8000
1x XCOM-LAN
1x COM-CAN
1x RCC-03
Responsible company
Perma-Batteries
Le Défi
Proposer une solution performante, durable et evolutive pour l’alimentation d’un site isolé dans l’Hérault.
Pourquoi STUDER
Robustesse, garantie de 10 ans, facilité de mise en service, grande performance des produits! La solution VS-70 + XTH est unique sur le marché et permet d'y adjoindre un champ solaire d'un seul string, tout en restant en couplage DC, et en bénéficiant d'une tension supérieure (de 100 à 600VCC). L’association TESVOLT+Studer est la plus performante pour des projets off-grid nécessitant puissance, fiabilité, performance et évolutivité.
La Solution
Nous avons fait le choix d’un système zero compromis, avec les meilleurs composants du marché : un onduleur-chargeur Studer XTH-8000, couplé via deux Variostring-70 à 7400W de panneaux back-contact LG NeON R, avec une batterie TESVOLT à BMS actif de 14.4 kWh. Nous avons également un générateur de secours (un SDMO 10kVA) piloté par le Studer en fonction du SOC batterie. Les garanties produits proposés (10 ans batterie + électronique et 25 ans pour les modules solaires) sécurisent l’investissement du client. Les batteries lithium TESVOLT (cellules Samsung) sont uniques de part leur équilibrage actif, qui permet l’ajout ultérieur de modules au delà d’un an après la mise en service initiale. Leur durée de vie est élevée (> 8000 cycles à 1C, 100% DOD).
Les résultats du projet
Couverture à 95% des consommations à l’année via le système, réduction des usages du groupe électrogène, fiabilité maximale, et monitoring facilité pour le client via l’application Studer sur smartphone.
Gaza, Palestine: Islamic University, Back-up System
The challenge
Palestine has a severe energy problem. The energy production of their one functioning power plant is not sufficient to meet the country's energy needs and due to their political situation, it is difficult to import sufficient energy from neighbouring countries. The electricity is typically available for a number of hours per day and then cut for at least as many.
The Islamic University Gaza (IUG) was founded in 1978 and has currently ten faculties delivering BA., B.SC, MA and M.Sc degrees. Until now, the university was using the utility grid for energy supply and diesel generators as backup during blackouts. As the number of blackouts became more frequent and with longer duration, the cost for the diesel generators increased and the university started to look for a new energy solution for its laboratories building.
The solution
As Gaza has 320 days of sunshine per year, the IUG chose solar energy for their new backup system for the laboratory building. The system consists of two parts. Each with a 70kWp PV array, 9 XTH 8000-48 units, 15 VT-80 and a 3330Ah@C10 battery bank.
The total PV capacity of 140kWp is enough for the entire buildings lighting, which represent 40% of the buildings total energy needs.
Why Studer
Under the existing circumstances, the new system had to be flawless and it was challenging to find reliable and efficient system components. Especially as they had to be ungradable as well. With Studer's products, the system design and implementation was smooth and a great experience.
Furthermore Studer's inverter/chargers enable a 3-phase supply and comes with a 5-year warranty.
Project outcome
The new backup system ensures the availability of power during working hours or during any occasion. The IUG is convinced by the backup systems performance and its general strategy is now to create more sustainable and environmentally friendly campuses in Gaza. They are planning retrofitting measures to existing buildings and renewable energy for their future energy generation.
System components
Responsible company
PalSolar
The challenge
Palestine has a severe energy problem. The energy production of their one functioning power plant is not sufficient to meet the country's energy needs and due to their political situation, it is difficult to import sufficient energy from neighbouring countries. The electricity is typically available for a number of hours per day and then cut for at least as many.
The Islamic University Gaza (IUG) was founded in 1978 and has currently ten faculties delivering BA., B.SC, MA and M.Sc degrees. Until now, the university was using the utility grid for energy supply and diesel generators as backup during blackouts. As the number of blackouts became more frequent and with longer duration, the cost for the diesel generators increased and the university started to look for a new energy solution for its laboratories building.
The solution
As Gaza has 320 days of sunshine per year, the IUG chose solar energy for their new backup system for the laboratory building. The system consists of two parts. Each with a 70kWp PV array, 9 XTH 8000-48 units, 15 VT-80 and a 3330Ah@C10 battery bank.
The total PV capacity of 140kWp is enough for the entire buildings lighting, which represent 40% of the buildings total energy needs.
Why Studer
Under the existing circumstances, the new system had to be flawless and it was challenging to find reliable and efficient system components. Especially as they had to be ungradable as well. With Studer's products, the system design and implementation was smooth and a great experience.
Furthermore Studer's inverter/chargers enable a 3-phase supply and comes with a 5-year warranty.
Project outcome
The new backup system ensures the availability of power during working hours or during any occasion. The IUG is convinced by the backup systems performance and its general strategy is now to create more sustainable and environmentally friendly campuses in Gaza. They are planning retrofitting measures to existing buildings and renewable energy for their future energy generation.
Germany: Office building with energy storage
The Challenge
When Autarctech started to build their new office with production and laboratory, they wanted to get as energy independent as possible, living up to their company slogan: enjoy independence.
Among the prerequisites were to have a system with enough energy to be able to work at least 8 hours per day, even if there is a power outage, as well as being able of handling additional energy requirements, i.e. charging an e-car or an increased production of their active balanced storage systems. It should also be possible to upgrade the system easily and they wanted to test different energy management systems with the setup.
The Solution
The photovoltaic energy easily covers the complete electrical energy consumption during a sunny day and charges the batteries very fast. The building is efficiently heated with an air heat pump. Low temperature underfloor heating is installed in each room and there is a controlled ventilation system with heat recovery. All warm water is generated electrically through a central heating boiler.
As all energy necessary to run the building, the offices and our meeting room as well as the production and laboratory is electrical, we have chosen to install a 3-phase power grid with one STUDER XTH 8000-48 on each phase. The STUDER inverter/chargers are controlling the Fronius inverter to enable charge and disable discharge through programming.
During daylight the Fronius inverter first delivers energy for the power grid and on top charges the battery up to 95% SOC. When the battery is at 95% the Fronius is put on hold level and just feeds enough energy into the system to run the building. The battery is used to cover peaks that the PV-inverter can’t deliver.
As soon as there is not enough energy coming from the photovoltaic, the battery is discharged and delivers the necessary power. When the battery has reached a level below 85% SOC, the photovoltaic inverter is activated again to charge the battery if energy is available. During nighttime the battery is still discharged. During summertime, there is no need receiving additional energy from the outside. This winter they will see what independence they can achieve with the system.
Why Studer
STUDER has always been very supportive of technical questions or issues. In addition, STUDER inverters have a high performance and are very reliable. The possibility of easily realizing an emergency power supply with uninterruptable power supply capability was a strong argument.
Project outcome
The system is running very stable without any connection to an external grid for several months. The company has been able to test their battery storage as well as the complete set up of their facility.
The system also work as a demonstration installation showing customers what possibilities there are in regards of using renewable energy for a smaller company.
System components
26 kWp PV panels
1x LiRack 22,4 kWh active balanced LiFeMnPO4 storage
3x STUDER Xtender inverter/charger XTH 8000-48
1x STUDER mounting system X-connect
1x STUDER multi-protocol communication module Xcom-CAN
1x STUDER communication set Xcom-LAN
1x STUDER remote control RCC-02
1x Fronius 20.0-3-M PV-inverter
Responsible company
Autarctech
The Challenge
When Autarctech started to build their new office with production and laboratory, they wanted to get as energy independent as possible, living up to their company slogan: enjoy independence.
Among the prerequisites were to have a system with enough energy to be able to work at least 8 hours per day, even if there is a power outage, as well as being able of handling additional energy requirements, i.e. charging an e-car or an increased production of their active balanced storage systems. It should also be possible to upgrade the system easily and they wanted to test different energy management systems with the setup.
The Solution
The photovoltaic energy easily covers the complete electrical energy consumption during a sunny day and charges the batteries very fast. The building is efficiently heated with an air heat pump. Low temperature underfloor heating is installed in each room and there is a controlled ventilation system with heat recovery. All warm water is generated electrically through a central heating boiler.
As all energy necessary to run the building, the offices and our meeting room as well as the production and laboratory is electrical, we have chosen to install a 3-phase power grid with one STUDER XTH 8000-48 on each phase. The STUDER inverter/chargers are controlling the Fronius inverter to enable charge and disable discharge through programming.
During daylight the Fronius inverter first delivers energy for the power grid and on top charges the battery up to 95% SOC. When the battery is at 95% the Fronius is put on hold level and just feeds enough energy into the system to run the building. The battery is used to cover peaks that the PV-inverter can’t deliver.
As soon as there is not enough energy coming from the photovoltaic, the battery is discharged and delivers the necessary power. When the battery has reached a level below 85% SOC, the photovoltaic inverter is activated again to charge the battery if energy is available. During nighttime the battery is still discharged. During summertime, there is no need receiving additional energy from the outside. This winter they will see what independence they can achieve with the system.
Why Studer
STUDER has always been very supportive of technical questions or issues. In addition, STUDER inverters have a high performance and are very reliable. The possibility of easily realizing an emergency power supply with uninterruptable power supply capability was a strong argument.
Project outcome
The system is running very stable without any connection to an external grid for several months. The company has been able to test their battery storage as well as the complete set up of their facility.
The system also work as a demonstration installation showing customers what possibilities there are in regards of using renewable energy for a smaller company.
Ghana: 5 solar Mini-Grids
The challenge
The Ghana Energy Development and Access Project (GEDAP) by the Ministry of Power implemented 5 mini-grids on a turn-key basis to provide access to electricity service 24/7 and enhance income generating activities to a total population of around 3,500 in remote island communities on Volta Lake. This project was the first of its kind promoting RE based mini-grids to play a key role in Ghana's transition to a low-carbon economy while electrifying population in rural areas.
The solution
The five mini-grids implemented by Trama TecnoAmbiental (TTA) required a different design and configuration based on the demand surveys and project context. By choosing the Studer solution it was possible to use the same equipment in different configurations (three-phase or single-phase, batteries of different size and configuration, a mix of PV and wind power generation, different size of back-up diesel generators) monitored with the same tool and procedures.
The centralised system provides electricity through a low-voltage distribution grid consisting of a three-phase backbone feeder with single-phase laterals connecting single-phase loads at each customer's premises. A dedicated line feeds high-efficiency LED street lamps throughout the villages.
Why Studer
Studer equipment is especially designed for off-grid applications. The flexibility of Studer products allowed to use a modular solution matching the different system configurations based on the demand and field studies. In addition, the systems are easily scalable and can be operated and monitored using centralized tools and equipment.
Project outcome
The five mini-grids serve as a demonstration project and showcase to representatives from other West African countries. This flexible design can be adapted to any configuration required by a rural electrification project with the following advantages:
- The modularity allows the mini-grids to be scaled up (or down). Requests for service upgrading started immediately after the start-up phase, corn-mills operation, cooling equipment, etc. A 20% extension is already under negotiation.
- Installation and operational costs are minimized using the same equipment with different configurations
- More effective training for local O&M
- Centralized, efficient management of spare parts
System components
Responsible company
Trama TecnoAmbiental (TTA)
The challenge
The Ghana Energy Development and Access Project (GEDAP) by the Ministry of Power implemented 5 mini-grids on a turn-key basis to provide access to electricity service 24/7 and enhance income generating activities to a total population of around 3,500 in remote island communities on Volta Lake. This project was the first of its kind promoting RE based mini-grids to play a key role in Ghana's transition to a low-carbon economy while electrifying population in rural areas.
The solution
The five mini-grids implemented by Trama TecnoAmbiental (TTA) required a different design and configuration based on the demand surveys and project context. By choosing the Studer solution it was possible to use the same equipment in different configurations (three-phase or single-phase, batteries of different size and configuration, a mix of PV and wind power generation, different size of back-up diesel generators) monitored with the same tool and procedures.
The centralised system provides electricity through a low-voltage distribution grid consisting of a three-phase backbone feeder with single-phase laterals connecting single-phase loads at each customer's premises. A dedicated line feeds high-efficiency LED street lamps throughout the villages.
Why Studer
Studer equipment is especially designed for off-grid applications. The flexibility of Studer products allowed to use a modular solution matching the different system configurations based on the demand and field studies. In addition, the systems are easily scalable and can be operated and monitored using centralized tools and equipment.
Project outcome
The five mini-grids serve as a demonstration project and showcase to representatives from other West African countries. This flexible design can be adapted to any configuration required by a rural electrification project with the following advantages:
- The modularity allows the mini-grids to be scaled up (or down). Requests for service upgrading started immediately after the start-up phase, corn-mills operation, cooling equipment, etc. A 20% extension is already under negotiation.
- Installation and operational costs are minimized using the same equipment with different configurations
- More effective training for local O&M
- Centralized, efficient management of spare parts
Guatemala: Parque nacional Tikal
El Proyecto
La administración del Parque Nacional Tikal tiene como objetivo reducir su consumo de combustible para el funcionamiento de las oficinas administrativas y áreas comunes para los visitantes; además por encontrarse dentro de una reserva arqueológica y natural se tiene como objetivo la utilización de energías renovables para su funcionamiento.
El objetivo es llegar a cubrir el 100% de su demanda energética en el lapso de 2 años.
La Solución
Para poder cubrir con la demanda de energía y por lo disperso de las instalaciones se tiene programado hacerlo en cuatro fases, con igual número de instalaciones.
Debido a que la vegetación es densa alrededor, se procedió a sobredimensionar los paneles fotovoltaicos para poder garantizar la energía diaria a consumir y evitar el uso del generador.
Por Qué STUDER
STUDER es una marca reconocida en sistemas aislados y con una muy buena eficiencia. Además se eligió por la robustez de los inversores/cargadores, ya que en ocasiones utilizan maquinaria eléctrica para carpintería cuya corriente pico de arranque es elevada.
La tasa de fallo es muy baja con lo cual nos da certeza que el sistema va a estar funcionando correctamente ya que el parque funciona los 365 días del año.
Resultado del Proyecto
El sistema no ha presentado ningún tipo de inconveniente al momento de conectar todo tipo de cargas inductivas de excesiva potencia.
Los usuarios han manifestado que el sistema ha sobrepasado sus expectativas ya que la información que le muestra el RCC-02 en producción y estado de carga de las baterías les ha servido para administrar el uso de la energía.
System components
1 x Inversor/Cargador STUDER Xtender, XTM 4000-48-01
16 x Módulos fotovoltaicos Yingli YGE-260, 260Wp
16 x Baterías Trojan T-105 225Ah en C20
2 x Regulador MPPT STUDER VarioTrack VT-65
1 x STUDER RCC-02
Responsible company
DEPRO SOLAR
El Proyecto
La administración del Parque Nacional Tikal tiene como objetivo reducir su consumo de combustible para el funcionamiento de las oficinas administrativas y áreas comunes para los visitantes; además por encontrarse dentro de una reserva arqueológica y natural se tiene como objetivo la utilización de energías renovables para su funcionamiento.
El objetivo es llegar a cubrir el 100% de su demanda energética en el lapso de 2 años.
La Solución
Para poder cubrir con la demanda de energía y por lo disperso de las instalaciones se tiene programado hacerlo en cuatro fases, con igual número de instalaciones.
Debido a que la vegetación es densa alrededor, se procedió a sobredimensionar los paneles fotovoltaicos para poder garantizar la energía diaria a consumir y evitar el uso del generador.
Por Qué STUDER
STUDER es una marca reconocida en sistemas aislados y con una muy buena eficiencia. Además se eligió por la robustez de los inversores/cargadores, ya que en ocasiones utilizan maquinaria eléctrica para carpintería cuya corriente pico de arranque es elevada.
La tasa de fallo es muy baja con lo cual nos da certeza que el sistema va a estar funcionando correctamente ya que el parque funciona los 365 días del año.
Resultado del Proyecto
El sistema no ha presentado ningún tipo de inconveniente al momento de conectar todo tipo de cargas inductivas de excesiva potencia.
Los usuarios han manifestado que el sistema ha sobrepasado sus expectativas ya que la información que le muestra el RCC-02 en producción y estado de carga de las baterías les ha servido para administrar el uso de la energía.
Honduras: Comunidad Rural Inteligente Mistruck
El Proyecto
Como un aporte de la Comisión de Acción Social Menonita (Casm) y la cooperación de Ayuda en Acción y Energías sin Fronteras, se realizó el proyecto denominado Smart Community en el Sector de la Mosquita Hondureña en la Comunidad de Mistruck. La finalidad del proyecto es brindar energía al centro eductivo incluida un aula dotada de equipos tecnológicos, y el Centro Ecoturítico en la Laguna de Tansin.
Es por ello que se tomó la decisión de trabajar con STUDER como sistema de respaldo. Fue considerado trabajar con la marca STUDER por sus especificaciones, por su robustez y la simplicidad para poder suministrar la energía necesaria para las instalaciones en caso de fallo de la presencia de la red eléctrica local.
El proyecto consiste en poder energizar el Centro Ecoturístico y el Centro Educativo, aparte de dotar de un sistema de bombeo solar para poder brindar agua potable a la Comunidad de Mistruck.
La Solución
El objectivo era brindar energía a todos los equipos eléctricos instalados como ser 15 computadoras, iluminación, freezer solar 24v, retroproyector, impresora, equipo de sonido y TV. Dado que eran equipos modernos y que cuentan con electrónica muy delicada se decidió la instalación de los equipos STUDER. Además se pedía una protección contra la salitre y STUDER reunía todos los requisitos que se necesitaban.
Por Qué STUDER
Porque son equipos confiables, robustos, y ofrecen la solución de protección contra la salitre, (se tropicalizaron). Además tenían que adaptarse al objetivo del proyecto de hacer una comunidad inteligente, y Studer con sus más de 500 parámetros hace que sean capaces de ofrecer soluciones inteligentes.
Resultado del Proyecto
La solución ofrecida con todos los equipos de STUDER permite tener un mayor rendimiento en las instalaciones. Ofrece una solución de respaldo excelente, y ante problemas de la red eléctrica permite seguir con la rutina diaria al suministrar energía eléctrica mediante los equipos STUDER.
System components
1 x Inversor Cargador de XTM 3500-24-01 STUDER
1 x Inversor Cargador de XTM 2400-24-01 STUDER
2 x Controladores VT-80 STUDER
2 x Sensores de Temperatura BTS-01 STUDER
2 x Sensores de Estado de las Baterías BSP 500 STUDER
2 x Xcom-GSM STUDER
2 x RCC-02 STUDER
19 x Modulos Solares Jinko Solar 310W
Responsible company
Tecnosol Honduras
El Proyecto
Como un aporte de la Comisión de Acción Social Menonita (Casm) y la cooperación de Ayuda en Acción y Energías sin Fronteras, se realizó el proyecto denominado Smart Community en el Sector de la Mosquita Hondureña en la Comunidad de Mistruck. La finalidad del proyecto es brindar energía al centro eductivo incluida un aula dotada de equipos tecnológicos, y el Centro Ecoturítico en la Laguna de Tansin.
Es por ello que se tomó la decisión de trabajar con STUDER como sistema de respaldo. Fue considerado trabajar con la marca STUDER por sus especificaciones, por su robustez y la simplicidad para poder suministrar la energía necesaria para las instalaciones en caso de fallo de la presencia de la red eléctrica local.
El proyecto consiste en poder energizar el Centro Ecoturístico y el Centro Educativo, aparte de dotar de un sistema de bombeo solar para poder brindar agua potable a la Comunidad de Mistruck.
La Solución
El objectivo era brindar energía a todos los equipos eléctricos instalados como ser 15 computadoras, iluminación, freezer solar 24v, retroproyector, impresora, equipo de sonido y TV. Dado que eran equipos modernos y que cuentan con electrónica muy delicada se decidió la instalación de los equipos STUDER. Además se pedía una protección contra la salitre y STUDER reunía todos los requisitos que se necesitaban.
Por Qué STUDER
Porque son equipos confiables, robustos, y ofrecen la solución de protección contra la salitre, (se tropicalizaron). Además tenían que adaptarse al objetivo del proyecto de hacer una comunidad inteligente, y Studer con sus más de 500 parámetros hace que sean capaces de ofrecer soluciones inteligentes.
Resultado del Proyecto
La solución ofrecida con todos los equipos de STUDER permite tener un mayor rendimiento en las instalaciones. Ofrece una solución de respaldo excelente, y ante problemas de la red eléctrica permite seguir con la rutina diaria al suministrar energía eléctrica mediante los equipos STUDER.
Honduras: Movimiento de Bananos Dole
El Proyecto
El proyecto es parte de la tecnificación de las fincas de producción de Bananos, para poder hacer más eficientes los procesos de recolección de las frutas dentro de las fincas.
Dole asignó la tarea a la Universidad Tecnológica Centroamérica (UNITEC) que es una institución privada de educación superior y fue creada el 17 de diciembre de 1986 con el propósito de convertirse en una alternativa para la formación universitaria, tanto por su innovadora oferta académica como por su propuesta y modelo educativos.
La tarea asignada a los estudiantes de Ingeniería consiste en rediseñar un sistema de arrastre que superara en tiempo y en fuerza uno ya existente, donde actualmente esta labor la realizan animales de arrastre o motores diésel. Se realizó el diseño donde se brinda energía a través de un inversor/cargador STUDER XTM a un variador para que este controle la potencia de arranque del motor, logrando obtener los resultados deseados, sustituyendo sistemas diésel o animales de arrastre.
La Solución
Para cumplir con el objetivo de eliminar el sistema diésel y los animales de arrastre, se han instalado las baterías de RELiON, de tecnología LiFePO4 con la cual se obtuvo más horas de trabajo. Y gracias a la función de carga del XTM, éste hace una carga muy rápida de las baterías permitiendo mas tiempo de trabajo, traduciéndose en más productividad.
Por Qué STUDER
Porque son equipos robustos, capaces de trabajar en distintas aplicaciones. El poder integrar el STUDER XTM a este proyecto, permitió que en el sistema se pudiese tener una alimentación de energía estable. Además, la flexibilidad de su programación permite optimizar el uso de la carga y descarga de las baterías.
Resultado del Proyecto
La solución ofrecida, logró realizar lo encomendado por Dolé a los estudiantes de UNITEC. Se realizaron pruebas de arrastre de bananos desde las fincas productoras hasta el área de empaque. Los encargados de la planta se mostraron satisfechos con la operatividad del sistema.
System components
1 x Inversor/Cargador STUDER XTM 4000-48-01
1 x Módulo de Control Remoto STUDER RCC-02
4 x Baterías RELiON RB100
1 x Motor AC 5HP Trifásico
1 x Variador de Frecuencia
Responsible company
Unitec and TECNOSOL
El Proyecto
El proyecto es parte de la tecnificación de las fincas de producción de Bananos, para poder hacer más eficientes los procesos de recolección de las frutas dentro de las fincas.
Dole asignó la tarea a la Universidad Tecnológica Centroamérica (UNITEC) que es una institución privada de educación superior y fue creada el 17 de diciembre de 1986 con el propósito de convertirse en una alternativa para la formación universitaria, tanto por su innovadora oferta académica como por su propuesta y modelo educativos.
La tarea asignada a los estudiantes de Ingeniería consiste en rediseñar un sistema de arrastre que superara en tiempo y en fuerza uno ya existente, donde actualmente esta labor la realizan animales de arrastre o motores diésel. Se realizó el diseño donde se brinda energía a través de un inversor/cargador STUDER XTM a un variador para que este controle la potencia de arranque del motor, logrando obtener los resultados deseados, sustituyendo sistemas diésel o animales de arrastre.
La Solución
Para cumplir con el objetivo de eliminar el sistema diésel y los animales de arrastre, se han instalado las baterías de RELiON, de tecnología LiFePO4 con la cual se obtuvo más horas de trabajo. Y gracias a la función de carga del XTM, éste hace una carga muy rápida de las baterías permitiendo mas tiempo de trabajo, traduciéndose en más productividad.
Por Qué STUDER
Porque son equipos robustos, capaces de trabajar en distintas aplicaciones. El poder integrar el STUDER XTM a este proyecto, permitió que en el sistema se pudiese tener una alimentación de energía estable. Además, la flexibilidad de su programación permite optimizar el uso de la carga y descarga de las baterías.
Resultado del Proyecto
La solución ofrecida, logró realizar lo encomendado por Dolé a los estudiantes de UNITEC. Se realizaron pruebas de arrastre de bananos desde las fincas productoras hasta el área de empaque. Los encargados de la planta se mostraron satisfechos con la operatividad del sistema.
Honduras: Sistema de Prioridad Solar
El Proyecto
El proyecto surge de la necesidad del cliente de poder tener un sistema que permita ahorrar y a la vez suplir energía cuando la red eléctrica nacional no está presente, y sobre todo contrarrestar la inestabilidad de la red, en un sistema split phase.
Este proyecto consiste en poder brindar un ahorro entre el 60%-70% del consumo de la energía de la compañía eléctrica nacional suministradora. El ahorro de energía proviene de energía generada por los paneles fotovoltaicos y acumulación en baterías de litio.
Además permite corregir la inestabilidad de la red eléctrica nacional y en caso de que la calidad de la red eléctrica de la compañía suministradora nacional sea deficiente o inexistente, el sistema nos garantiza un back up permitiendo el funcionamiento de todos los aparatos eléctricos de la casa.
La solucíon
Para cumplir con el objetivo de disminuir el consumo de energía eléctrica convencional, se han instalado paneles solares con baterías de Litio. Con la cual podemos sustituir un porcentaje del consumo de la energía comercial.
Esto solo es posible gracias a acumular la energía producida por los por paneles fotovoltaicos y solo en caso de no haber energía disponible en las baterías se recurre a la energía de la red comercial. Con esto se reduce mucho el consumo de energía de la compañía suministradora.
Por Qué STUDER
Porque la solución que ofrece la función prioridad solar, única en STUDER, hace posible una programación que gestiona de forma perfecta la energía produciendo un ahorro en el consumo de energía de la red eléctrica, dándole prioridad el consumo desde la energía creada por los paneles fotovoltaicos.
Además sirve como sistema de respaldo en caso de cortes de la energía eléctrica nacional y pudiendo disponer de energía en todo momento.
Resultado del Proyecto
Con la solución ofrecida se ha logrado poder brindar la energía a los aparatos eléctricos y electrónicos utilizados en la vivienda. También se ha brindado respaldo durante los fallos de la red eléctrica nacional y se ha minimizado un 60% el consumo de la energía eléctrica procedente de la compañía eléctrica nacional.
System components
24 x Módulos Solares Jinko Solar 315W
1 x Baterías RELiON RB200-48
2 x Inversor/Cargador STUDER Xtender XTH 6000-48-01
1 x Regulador solar MPPT STUDER VarioString VS-120
1 x Sensores de Temperatura BTS-01
1 x Procesador de estado de batería STUDER BSP 500
1 x Elemento de monitoreo remoto STUDER Xcom-LAN
1 x Gestor de la instalación STUDER RCC-02
Responsible company
Tecnosol
El Proyecto
El proyecto surge de la necesidad del cliente de poder tener un sistema que permita ahorrar y a la vez suplir energía cuando la red eléctrica nacional no está presente, y sobre todo contrarrestar la inestabilidad de la red, en un sistema split phase.
Este proyecto consiste en poder brindar un ahorro entre el 60%-70% del consumo de la energía de la compañía eléctrica nacional suministradora. El ahorro de energía proviene de energía generada por los paneles fotovoltaicos y acumulación en baterías de litio.
Además permite corregir la inestabilidad de la red eléctrica nacional y en caso de que la calidad de la red eléctrica de la compañía suministradora nacional sea deficiente o inexistente, el sistema nos garantiza un back up permitiendo el funcionamiento de todos los aparatos eléctricos de la casa.
La solucíon
Para cumplir con el objetivo de disminuir el consumo de energía eléctrica convencional, se han instalado paneles solares con baterías de Litio. Con la cual podemos sustituir un porcentaje del consumo de la energía comercial.
Esto solo es posible gracias a acumular la energía producida por los por paneles fotovoltaicos y solo en caso de no haber energía disponible en las baterías se recurre a la energía de la red comercial. Con esto se reduce mucho el consumo de energía de la compañía suministradora.
Por Qué STUDER
Porque la solución que ofrece la función prioridad solar, única en STUDER, hace posible una programación que gestiona de forma perfecta la energía produciendo un ahorro en el consumo de energía de la red eléctrica, dándole prioridad el consumo desde la energía creada por los paneles fotovoltaicos.
Además sirve como sistema de respaldo en caso de cortes de la energía eléctrica nacional y pudiendo disponer de energía en todo momento.
Resultado del Proyecto
Con la solución ofrecida se ha logrado poder brindar la energía a los aparatos eléctricos y electrónicos utilizados en la vivienda. También se ha brindado respaldo durante los fallos de la red eléctrica nacional y se ha minimizado un 60% el consumo de la energía eléctrica procedente de la compañía eléctrica nacional.
Honduras: Sistema de Prioridad Solar
Proyecto
El proyecto surge por la necesidad del cliente de poder tener un sistema que permita ahorrar y a la vez suplir energía cuando la red eléctrica nacional no está presente. Y sobre todo, contrarrestar la inestabilidad en la calidad de la red eléctrica nacional.
El proyecto consiste en poder generar un ahorro del 90% del consumo de la energía eléctrica nacional, brindando energía de manera instantánea a la vivienda durante la ventana solar gracias a los paneles solares, y a través de acumulación en las horas nocturnas gracias a la batería de litio.
La Solución
Para cumplir con el objetivo de disminuir el consumo de energía eléctrica nacional, se han instalado paneles solares con batería de litio. Con lo cual, se puede reducir un porcentaje muy alto del consumo de la energía tomada de la red eléctrica nacional. Esto solo es posible, gracias a acumular la energía producida por los por paneles fotovoltaicos, y solo en caso de no haber energía disponible en las baterías, es únicamente cuando se recurre al consumo de la energía de la red eléctrica nacional.
Por Qué STUDER
Porque la solución que ofrece la función Prioridad Solar, única del fabricante STUDER, hace posible una programación que gestiona de forma perfecta la energía produciendo un ahorro en el consumo de energía de la red eléctrica nacional, dando prioridad al consumo desde la energía creada por los paneles fotovoltaicos. Además, sirve como un sistema de respaldo en caso de cortes de la energía eléctrica nacional, y permite disponer de energía en cualquier momento gracias a este sistema.
Resultado del Proyecto
Con la solución ofertada se ha logrado poder brindar la energía a los aparatos eléctricos y electrónicos utilizadas en la vivienda mediante energía solar, también bridando respaldo durante los fallos y cortes de la red eléctrica nacional. Se ha reducido en un 90% el consumo de la energía que se consumía de la red eléctrica nacional.
System components
2x Inversor/Cargador STUDER XTM 4000-48-01
1x Controlador STUDER MPPT VS-70
1x Sensores de temperatura BTS-01
1x Procesador de estado de baterías BSP 500
1x Monitor remoto XCom-LAN
1x Monitor y datalogger STUDER RCC-02
1x Batería de litio RELION RB100-48
10x Módulos solares Jinko Solar 315Wp
Responsible company
Tecnosol
Proyecto
El proyecto surge por la necesidad del cliente de poder tener un sistema que permita ahorrar y a la vez suplir energía cuando la red eléctrica nacional no está presente. Y sobre todo, contrarrestar la inestabilidad en la calidad de la red eléctrica nacional.
El proyecto consiste en poder generar un ahorro del 90% del consumo de la energía eléctrica nacional, brindando energía de manera instantánea a la vivienda durante la ventana solar gracias a los paneles solares, y a través de acumulación en las horas nocturnas gracias a la batería de litio.
La Solución
Para cumplir con el objetivo de disminuir el consumo de energía eléctrica nacional, se han instalado paneles solares con batería de litio. Con lo cual, se puede reducir un porcentaje muy alto del consumo de la energía tomada de la red eléctrica nacional. Esto solo es posible, gracias a acumular la energía producida por los por paneles fotovoltaicos, y solo en caso de no haber energía disponible en las baterías, es únicamente cuando se recurre al consumo de la energía de la red eléctrica nacional.
Por Qué STUDER
Porque la solución que ofrece la función Prioridad Solar, única del fabricante STUDER, hace posible una programación que gestiona de forma perfecta la energía produciendo un ahorro en el consumo de energía de la red eléctrica nacional, dando prioridad al consumo desde la energía creada por los paneles fotovoltaicos. Además, sirve como un sistema de respaldo en caso de cortes de la energía eléctrica nacional, y permite disponer de energía en cualquier momento gracias a este sistema.
Resultado del Proyecto
Con la solución ofertada se ha logrado poder brindar la energía a los aparatos eléctricos y electrónicos utilizadas en la vivienda mediante energía solar, también bridando respaldo durante los fallos y cortes de la red eléctrica nacional. Se ha reducido en un 90% el consumo de la energía que se consumía de la red eléctrica nacional.
Honduras: Smart rural community Mirasol
El Proyecto
Como un aporte de la Comisión de Acción Social Menonita (Casm) y la cooperación de Ayuda en Acción y Energías sin Fronteras, se realizó el proyecto denominado Smart Community en el Sector de la Mosquita Hondureña en la comunidad de Mirasol. La finalidad del proyecto es brindar energía al centro educativo, incluida un aula dotada de equipos tecnológicos, y al Centro de Salud de la comunidad.
La Solución
El objetivo era brindar energía a todos los equipos eléctricos instalados como, 10 computadoras, iluminación, retroproyector, impresora, equipo de sonido, computadoras portátiles, bomba de agua, equipo médico, nebulizadores, incineradores pequeños, ultrasonidos portátiles, medidores de presión y ventiladores en el área de espera y atención medica. Se decidió utilizar Studer porque los equipos a energizar son modernos y cuentan con una electrónica muy delicada. También se pedía que resistieran el salitre y Studer reunía todos los requisitos que se necesitaban.
Por Qué STUDER
Se eligió Studer porque son equipos confiables y robustos, brindan la solución de protección contra el salitre (se tropicalizaron) y porque tenían que adaptarse al objetivo del proyecto de hacer una comunidad inteligente y Studer, con sus más de 500 parámetros, hace que sean equipos inteligentes. Además por ser el único en ofrecer 10 años de garantía integra.
Resultado del Proyecto
La solución ofrecida, el poder integrar todos los equipos de Studer, permite tener un mayor rendimiento en las instalaciones.
System components
1 x Inversor Cargador de XTM 3500W-24-01 STUDER
1 x Controladores MPPT VT-80 STUDER
1 x BSP 1200 STUDER
1 x RCC-02 STUDER
15x Módulos Solares Peimar 300W
12x Baterías BAE 14PVV- 2660Ah
Responsible company
Tecnosol Honduras
El Proyecto
Como un aporte de la Comisión de Acción Social Menonita (Casm) y la cooperación de Ayuda en Acción y Energías sin Fronteras, se realizó el proyecto denominado Smart Community en el Sector de la Mosquita Hondureña en la comunidad de Mirasol. La finalidad del proyecto es brindar energía al centro educativo, incluida un aula dotada de equipos tecnológicos, y al Centro de Salud de la comunidad.
La Solución
El objetivo era brindar energía a todos los equipos eléctricos instalados como, 10 computadoras, iluminación, retroproyector, impresora, equipo de sonido, computadoras portátiles, bomba de agua, equipo médico, nebulizadores, incineradores pequeños, ultrasonidos portátiles, medidores de presión y ventiladores en el área de espera y atención medica. Se decidió utilizar Studer porque los equipos a energizar son modernos y cuentan con una electrónica muy delicada. También se pedía que resistieran el salitre y Studer reunía todos los requisitos que se necesitaban.
Por Qué STUDER
Se eligió Studer porque son equipos confiables y robustos, brindan la solución de protección contra el salitre (se tropicalizaron) y porque tenían que adaptarse al objetivo del proyecto de hacer una comunidad inteligente y Studer, con sus más de 500 parámetros, hace que sean equipos inteligentes. Además por ser el único en ofrecer 10 años de garantía integra.
Resultado del Proyecto
La solución ofrecida, el poder integrar todos los equipos de Studer, permite tener un mayor rendimiento en las instalaciones.
India: Apartment complex in Bangalore, Off-Grid System
The challenge
An unreliable electric grid in combination with the owner's deep interest in solar power were the two main reasons to install an off-grid system in the luxury apartment complex "Ashish Pride" in central Bangalore, India. This is Bangalore's first apartment complex to run on solar energy.
The solution
The loads for this apartment complex includes the common area lighting (including the garden), a Schindler-elevator for 10 persons, four water pumps (2 Borewell submersible pumps and 2 pumps for an overhead tank) and five apartments.
During power outages, the system also provide backup for the lighting of the 25 apartments.
Why Studer
The owner chose Studer products for this installation, as he needed inverter/chargers capable of handling high surge loads like an elevator and motors.
This independent system is also pre-configured and is totally trouble free. There is no manpower required for its continuous operation.
Project outcome
The system was commissioned in 2015 and the off-grid system has been able to produce enough energy, in average 90- 110 kWh/day, to power the specified loads.
The area previously used by the diesel generator for backup has been converted into parking spaces. The owner has also been able to increase the price of the apartments with the selling argument that he can guarantee power 24/7 with solar energy.
System components
Responsible company
JJJ Solar
The challenge
An unreliable electric grid in combination with the owner's deep interest in solar power were the two main reasons to install an off-grid system in the luxury apartment complex "Ashish Pride" in central Bangalore, India. This is Bangalore's first apartment complex to run on solar energy.
The solution
The loads for this apartment complex includes the common area lighting (including the garden), a Schindler-elevator for 10 persons, four water pumps (2 Borewell submersible pumps and 2 pumps for an overhead tank) and five apartments.
During power outages, the system also provide backup for the lighting of the 25 apartments.
Why Studer
The owner chose Studer products for this installation, as he needed inverter/chargers capable of handling high surge loads like an elevator and motors.
This independent system is also pre-configured and is totally trouble free. There is no manpower required for its continuous operation.
Project outcome
The system was commissioned in 2015 and the off-grid system has been able to produce enough energy, in average 90- 110 kWh/day, to power the specified loads.
The area previously used by the diesel generator for backup has been converted into parking spaces. The owner has also been able to increase the price of the apartments with the selling argument that he can guarantee power 24/7 with solar energy.
India: Car Showroom, Sirsi, AC coupling
The challenge
India is the third largest electricity producer & consumer in the world, after USA & China. Even so, over hundreds of millions of people are not connected to the electrical grid. The Indian national grids are experiencing difficulties with frequent power outages and perhaps as much as ¼ of the generated energy lost during transmission or stolen.
The state Karnataka, situated in the south of India, is actively trying to change this situation by encouraging individuals, societies, institutions and companies to install grid-connected rooftop solar units; in first hand to make people self-sufficient in electrical power and in second hand to inject any surplus into the local grid paid by net-metering. With 300 sunny days a year, Karnataka has 10 gigawatts of solar energy potential. If all goes according to plan, rooftops alone will contribute with 400 megawatts by 2018.
The solution
This car show room and service centre initially had an on-grid system, which was completely unsuccessful due to regular power cuts during the daytime. During power outages, they had to rely on a diesel generator for backup. The energy was mainly used to power pneumatic jacks, compressors and other basic utilities.
By taking 5 kWp of the existing PV panels and adding 3 inverter/chargers, one MPPT solar charge controller and 150 Ah batteries, they now have converted their pure on-grid system into an AC-coupled self-consumption system with grid-feeding.
With the new PV system they are not only self-sufficient but they can also inject electricity into the grid making money. This solution gives them access to uninterrupted power and good surge handling when using big loads such as a pneumatic jack.
Why Studer
Studer products were chosen for this system as they are reliable and have a good surge handling capacity. They are also capable of sending the excess electrical power back to the grid and credits are given from main power supply unit for excess power generated.
Project outcome
With the new system, there is less need to run a diesel generator. The owner of the car show room has been able to inject approximately 30% of the generated energy back into the grid, especially energy generated during lunch hours and holidays. Furthermore, he is no longer exposed to the frequent power outages as he has his own independent energy system.The area previously used by the diesel generator for backup has been converted into parking spaces. The owner has also been able to increase the price of the apartments with the selling argument that he can guarantee power 24/7 with solar energy.
System components
Responsible company
Popular solar
The challenge
India is the third largest electricity producer & consumer in the world, after USA & China. Even so, over hundreds of millions of people are not connected to the electrical grid. The Indian national grids are experiencing difficulties with frequent power outages and perhaps as much as ¼ of the generated energy lost during transmission or stolen.
The state Karnataka, situated in the south of India, is actively trying to change this situation by encouraging individuals, societies, institutions and companies to install grid-connected rooftop solar units; in first hand to make people self-sufficient in electrical power and in second hand to inject any surplus into the local grid paid by net-metering. With 300 sunny days a year, Karnataka has 10 gigawatts of solar energy potential. If all goes according to plan, rooftops alone will contribute with 400 megawatts by 2018.
The solution
This car show room and service centre initially had an on-grid system, which was completely unsuccessful due to regular power cuts during the daytime. During power outages, they had to rely on a diesel generator for backup. The energy was mainly used to power pneumatic jacks, compressors and other basic utilities.
By taking 5 kWp of the existing PV panels and adding 3 inverter/chargers, one MPPT solar charge controller and 150 Ah batteries, they now have converted their pure on-grid system into an AC-coupled self-consumption system with grid-feeding.
With the new PV system they are not only self-sufficient but they can also inject electricity into the grid making money. This solution gives them access to uninterrupted power and good surge handling when using big loads such as a pneumatic jack.
Why Studer
Studer products were chosen for this system as they are reliable and have a good surge handling capacity. They are also capable of sending the excess electrical power back to the grid and credits are given from main power supply unit for excess power generated.
Project outcome
With the new system, there is less need to run a diesel generator. The owner of the car show room has been able to inject approximately 30% of the generated energy back into the grid, especially energy generated during lunch hours and holidays. Furthermore, he is no longer exposed to the frequent power outages as he has his own independent energy system.The area previously used by the diesel generator for backup has been converted into parking spaces. The owner has also been able to increase the price of the apartments with the selling argument that he can guarantee power 24/7 with solar energy.
India: Namanne industries, Self-Consumption System
The challenge
To manage a small industrial business is challenging and even more so when the erratic power supply from the electrical grid makes it impossible to stick to production plans or to meet set delivery dates. Collaborators have to be paid their salaries, even though they are incapacitated to perform their work.
In July 2015 Nammane Industries, a manufacturer of disposable bowls, plates and cups made from Areca leaves situated in Bangalore, decided to change this situation by investing in a self-consumption system to become energy independent.
The solution
As many small businesses Nammane Industries is situated in the same building as its owner's private home. The self-consumption system was therefore dimensioned to cover loads of both industrial and domestic character. The industrial loads included a hydraulic lift in single phase and other machines for making the plates.
A 5kW rooftop PV plant was installed on the building's roof. For practical reasons the 20 panels were mounted on a metal structure providing access to the roof for other activities such as children playing or drying clothes. The complete loads are powered with solar power. This way the machines keep working even during power cuts.
If there is excess power, it is injected into the grid against a feed-in tariff, making money for the owner. The system avoids any manual intervention and supervise all aspects; from generation to charging of batteries, supply to industrial and domestic consumption and feeding into the grid.
Why Studer
In this geographical area, the voltage fluctuations are high and most industrial equipment won't work. By using devices from Studer Innotec the surge capacity needed by the machines are met and the inverter/chargers produce a pure sine wave AC power output which make all machines perform at their best.
Project outcome
So far the system has always produced more energy than needed giving the owner the possibility to sell power to the grid by using the inverter/chargers that automatically control the required in-house consumption and accordingly supply the surplus to the grid. Providing a welcome extra revenue.
The company has been able to make on-time deliveries to their customers, as they no longer experience any power cuts.
System components
Responsible company
Popular solar
The challenge
To manage a small industrial business is challenging and even more so when the erratic power supply from the electrical grid makes it impossible to stick to production plans or to meet set delivery dates. Collaborators have to be paid their salaries, even though they are incapacitated to perform their work.
In July 2015 Nammane Industries, a manufacturer of disposable bowls, plates and cups made from Areca leaves situated in Bangalore, decided to change this situation by investing in a self-consumption system to become energy independent.
The solution
As many small businesses Nammane Industries is situated in the same building as its owner's private home. The self-consumption system was therefore dimensioned to cover loads of both industrial and domestic character. The industrial loads included a hydraulic lift in single phase and other machines for making the plates.
A 5kW rooftop PV plant was installed on the building's roof. For practical reasons the 20 panels were mounted on a metal structure providing access to the roof for other activities such as children playing or drying clothes. The complete loads are powered with solar power. This way the machines keep working even during power cuts.
If there is excess power, it is injected into the grid against a feed-in tariff, making money for the owner. The system avoids any manual intervention and supervise all aspects; from generation to charging of batteries, supply to industrial and domestic consumption and feeding into the grid.
Why Studer
In this geographical area, the voltage fluctuations are high and most industrial equipment won't work. By using devices from Studer Innotec the surge capacity needed by the machines are met and the inverter/chargers produce a pure sine wave AC power output which make all machines perform at their best.
Project outcome
So far the system has always produced more energy than needed giving the owner the possibility to sell power to the grid by using the inverter/chargers that automatically control the required in-house consumption and accordingly supply the surplus to the grid. Providing a welcome extra revenue.
The company has been able to make on-time deliveries to their customers, as they no longer experience any power cuts.
India: Residential Solar Hybrid Project
The challenge
Kerala is having wet and maritime tropical climate, influenced by the seasonal heavy rains brought up by the monsoon. Well known for its Lush greenery, during monsoon power outage due to tree falling is common in rural areas. In 2018, monsoon caused flood in Kerala and power failure in most of the rural parts for more than 3 days.
It was during COVID lockdown in 2020, Mr. Aji Kumar an NRI contacted us to install a solar for home. His home is located in a beautiful village called Kalady Angamaly. Since he was back home and working – he wanted a project which guarantees continues power even in case of power failures for 3-4 days. Also when he is going back to UAE power generated must not go un-utilized. Another challenge was the roof itself, we have to install solar panels on Traditional Antique Kerala Clay tiles without disturbing or breaking it.
Why STUDER
High reliability, surge capacity and 10 years long warranty made us to choose STUDER for the project. Multi programmable functions, detailed plant performance monitoring was also utilized in the project.
The solution
Starting from the designing, our team of engineers did energy auditing at site. We figured the power usage at different time & surge. This residence was using 4 Air conditioners, powerful water pumping motors for irrigation, washing machine, refrigerators & Work Server. Since customer requirement of solution for power failure & solar power not getting wasted when no one at home cannot be met by OFF Grid and ON Grid, we recommended Hybrid Solar Solution.
We did project using high efficiency REC solar module 5kWp & Studer Inverter – 2nos to support load up to 6kW and surge load up to 12kVA. 200Ah battery 8 nos was used considering 50% Depth of discharge & autonomy for 1 day. Special structural designing was made for panel mounting on roof without disturbing the tiles.
Project outcome
Hybrid project is providing uninterrupted supply & excess power is exported to GRID. Customer is now working without any fear of power failures due to monsoon & happy that he can monitoring solar generation, usage and export . Even when there is fluctuation in grid voltage, Xtender is handling.
System components
Solar Modules : 5kW REC Mono PERC - 395Wp
Inverters: STUDER XTM 4000-48V - 2 Nos
Charge Controller : VT–80 - 1 Nos
Remote Communication: XCom – LAN - 1 Nos
DBL : ABB-80L - 3 Nos
Batteries : EXIDE C10 – 200Ah - 8 Nos
Racking – Engineered GI Structure
Responsible company
ILLUMINE ENERGY SOLUTIONS
The challenge
Kerala is having wet and maritime tropical climate, influenced by the seasonal heavy rains brought up by the monsoon. Well known for its Lush greenery, during monsoon power outage due to tree falling is common in rural areas. In 2018, monsoon caused flood in Kerala and power failure in most of the rural parts for more than 3 days.
It was during COVID lockdown in 2020, Mr. Aji Kumar an NRI contacted us to install a solar for home. His home is located in a beautiful village called Kalady Angamaly. Since he was back home and working – he wanted a project which guarantees continues power even in case of power failures for 3-4 days. Also when he is going back to UAE power generated must not go un-utilized. Another challenge was the roof itself, we have to install solar panels on Traditional Antique Kerala Clay tiles without disturbing or breaking it.
Why STUDER
High reliability, surge capacity and 10 years long warranty made us to choose STUDER for the project. Multi programmable functions, detailed plant performance monitoring was also utilized in the project.
The solution
Starting from the designing, our team of engineers did energy auditing at site. We figured the power usage at different time & surge. This residence was using 4 Air conditioners, powerful water pumping motors for irrigation, washing machine, refrigerators & Work Server. Since customer requirement of solution for power failure & solar power not getting wasted when no one at home cannot be met by OFF Grid and ON Grid, we recommended Hybrid Solar Solution.
We did project using high efficiency REC solar module 5kWp & Studer Inverter – 2nos to support load up to 6kW and surge load up to 12kVA. 200Ah battery 8 nos was used considering 50% Depth of discharge & autonomy for 1 day. Special structural designing was made for panel mounting on roof without disturbing the tiles.
Project outcome
Hybrid project is providing uninterrupted supply & excess power is exported to GRID. Customer is now working without any fear of power failures due to monsoon & happy that he can monitoring solar generation, usage and export . Even when there is fluctuation in grid voltage, Xtender is handling.
India: Rural electrification of Pasanga
The challenge
Far away from the grid in the Gumla district, Jharkand, India, lies the village Pasanga. As the transmission line for the national grid is far away, an off-grid solar system was the answer for powering the village's rice hullers (agricultural machines that remove the outer coat of the rice) as well as irrigation pumps and household lighting.
The solution
Commissioned in 2016, this off-grid system of 24.3kW supplies 30 of the village houses with electricity as well as the irrigation pumps and agricultural machines.
The power is distributed through transmission cables without any loss. All connected houses has an individual smart meter that registers their energy consumption.
Each energy unit has a fixed price and the consumers pay in advance, on a monthly basis their estimated energy consumption.
Other village houses may also join the local network once they pay the minimum charge fee.
Why Studer
For this installation, it was vital to find inverter/chargers that could provide uninterrupted power with high surge handling capacity and high efficiency. As our XTH 8000-48 in the Xtender series with a surge capacity of 21kVA.
Project outcome
The village enjoys access to energy through a stand-alone system that provides them with power whenever they need it.
The smooth operating system is free from pollution and provides the village independent energy.
System components
Responsible company
Play solar
The challenge
Far away from the grid in the Gumla district, Jharkand, India, lies the village Pasanga. As the transmission line for the national grid is far away, an off-grid solar system was the answer for powering the village's rice hullers (agricultural machines that remove the outer coat of the rice) as well as irrigation pumps and household lighting.
The solution
Commissioned in 2016, this off-grid system of 24.3kW supplies 30 of the village houses with electricity as well as the irrigation pumps and agricultural machines.
The power is distributed through transmission cables without any loss. All connected houses has an individual smart meter that registers their energy consumption.
Each energy unit has a fixed price and the consumers pay in advance, on a monthly basis their estimated energy consumption.
Other village houses may also join the local network once they pay the minimum charge fee.
Why Studer
For this installation, it was vital to find inverter/chargers that could provide uninterrupted power with high surge handling capacity and high efficiency. As our XTH 8000-48 in the Xtender series with a surge capacity of 21kVA.
Project outcome
The village enjoys access to energy through a stand-alone system that provides them with power whenever they need it.
The smooth operating system is free from pollution and provides the village independent energy.
India: The Smart School, AC coupling
The challenge
Indian cities regularly experience temporary power cuts during daytime, sometimes up to 6 or even 8 hours per day. These power failures influence the continuity and quality of the education at school. Therefore, Sri Vidya Kendra, The Smart school, situated at the outskirts of Bangalore, decided to set up a back-up system with renewable energy in order to eliminate power cuts during school hours, to reduce their use of noisy, costly and polluting diesel generators and to reduce their grid-dependence.
The solution
Founded in 2009, this modern school is situated in a picturesque, green, pollution free environment. They wanted to educate their students about renewable energy and had already installed a grid-tied solar system. However, due to particularly heavy power outages in their locality, the school could hardly use its grid-tied system. By adding 3 Xtender inverter/chargers in three-phase and 8 batteries to their existing system and allocating 14kW of the existing PV panels we provided them with a renewable energy backup system with the possibility to either store the produced energy in the batteries or to inject excess energy into the grid.
The stand-alone backup system supplies electricity to common area lighting, all class rooms (including projectors, lights and fans), the science labs, the computer lad (40 computers), 4 Xerox machines and the administration block during power cuts.
Why Studer
Studer could successfully provide the school with an AC-coupled hybrid system, combining the grid-tied system with a stand-alone backup system.
Project outcome
With its new system, the school and even the entire campus (1400 students from Play school to 12th standard) do not need to worry about power outages; they have round the clock power. There is no longer a need to run the diesel generator for extra power, which leads to big savings on diesel.
The power generated after school hours, on Sundays or during school holidays is injected into the grid with a feed-in tariff making additional incomes for the school.
System components
Responsible company
Solar Corona Energy Pvt Ltd
The challenge
Indian cities regularly experience temporary power cuts during daytime, sometimes up to 6 or even 8 hours per day. These power failures influence the continuity and quality of the education at school. Therefore, Sri Vidya Kendra, The Smart school, situated at the outskirts of Bangalore, decided to set up a back-up system with renewable energy in order to eliminate power cuts during school hours, to reduce their use of noisy, costly and polluting diesel generators and to reduce their grid-dependence.
The solution
Founded in 2009, this modern school is situated in a picturesque, green, pollution free environment. They wanted to educate their students about renewable energy and had already installed a grid-tied solar system. However, due to particularly heavy power outages in their locality, the school could hardly use its grid-tied system. By adding 3 Xtender inverter/chargers in three-phase and 8 batteries to their existing system and allocating 14kW of the existing PV panels we provided them with a renewable energy backup system with the possibility to either store the produced energy in the batteries or to inject excess energy into the grid.
The stand-alone backup system supplies electricity to common area lighting, all class rooms (including projectors, lights and fans), the science labs, the computer lad (40 computers), 4 Xerox machines and the administration block during power cuts.
Why Studer
Studer could successfully provide the school with an AC-coupled hybrid system, combining the grid-tied system with a stand-alone backup system.
Project outcome
With its new system, the school and even the entire campus (1400 students from Play school to 12th standard) do not need to worry about power outages; they have round the clock power. There is no longer a need to run the diesel generator for extra power, which leads to big savings on diesel.
The power generated after school hours, on Sundays or during school holidays is injected into the grid with a feed-in tariff making additional incomes for the school.
Ireland: 72kWA Off-Grid System with Lithium batteries
The challenge
From an economic point of view all off-grid systems with battery storage should find a way to efficiently handle their battery management. This poultry farm with renewable energy in form of wind power is no exception. The challenge was to find a way to automate the energy system so that the wind turbine does not provide more power that can be used or charged to the lithium battery bank.
The solution
oday two large chicken sheds are powered at all times by a 72kVA system with off-grid priority combining Studer's power-electronics with Warik Energy's control and monitoring system EMMA Pro (EPRO).
Power generation on the AC-Out side is automatically regulated through the EPRO that limits the export towards the batteries to 500W per phase and directs the rest of the wind turbine produced power directly towards the sheds and diverts the excess energy into a 7000 liter buffer tank.
A clever programming between the EPRO and the Studer Xtender inverter/ charger's auxiliary relays regulates the power to the BYD batteries making sure that they never become fully charged nor empty. A level is set for the batteries highest and lowest allowed state of charge (SOC).
It is possible to view the system's performance and energy consumption remotely by using Studer's Xcom-LAN access portal. This portal also allow to download the daily, weekly and monthly logs and import them to an excel template file. The EPRO online monitoring displays the turbine generation, demand on site, export to the batteries, import from the batteries, power diverted to heating the tank, and three temperature readings from the tank allowing shut down of the turbine if the tank gets too hot in the event of a pump failing.
An interlock mechanism prevents the wind turbine and the diesel generator to run at the same time. Once the diesel generator starts a stop signal is given to the wind turbine. This is accomplished by putting a simple relay between the AC-In and the diesel generator which signals the turbine when the diesel generator is turned on.
The system has an automatic fault notification and remote access. If a fault occurs, the Xcom-LAN provides automatic notification to three different people through the Studer Access Portal which then can make the necessary changes.
Why Studer
Wind turbines have high start-up inrush currents and the Studer products have the ability to cope with surges close to 3 times its rated capacity. By using Studer's X-connect mounting system it was possible to install much power on a small surface, up to 24kVA per m2.
Project outcome
This system, developed on a tight budget, is functioning well providing the owner almost perfect autonomy from the grid and drastically reducing grid electricity cost and dependency.
Excess power generation is used to provide heat for drying the chicken litter, reducing the need for gas heating and its associated costs.
System components
Responsible company
Warik Energy
The challenge
From an economic point of view all off-grid systems with battery storage should find a way to efficiently handle their battery management. This poultry farm with renewable energy in form of wind power is no exception. The challenge was to find a way to automate the energy system so that the wind turbine does not provide more power that can be used or charged to the lithium battery bank.
The solution
oday two large chicken sheds are powered at all times by a 72kVA system with off-grid priority combining Studer's power-electronics with Warik Energy's control and monitoring system EMMA Pro (EPRO).
Power generation on the AC-Out side is automatically regulated through the EPRO that limits the export towards the batteries to 500W per phase and directs the rest of the wind turbine produced power directly towards the sheds and diverts the excess energy into a 7000 liter buffer tank.
A clever programming between the EPRO and the Studer Xtender inverter/ charger's auxiliary relays regulates the power to the BYD batteries making sure that they never become fully charged nor empty. A level is set for the batteries highest and lowest allowed state of charge (SOC).
It is possible to view the system's performance and energy consumption remotely by using Studer's Xcom-LAN access portal. This portal also allow to download the daily, weekly and monthly logs and import them to an excel template file. The EPRO online monitoring displays the turbine generation, demand on site, export to the batteries, import from the batteries, power diverted to heating the tank, and three temperature readings from the tank allowing shut down of the turbine if the tank gets too hot in the event of a pump failing.
An interlock mechanism prevents the wind turbine and the diesel generator to run at the same time. Once the diesel generator starts a stop signal is given to the wind turbine. This is accomplished by putting a simple relay between the AC-In and the diesel generator which signals the turbine when the diesel generator is turned on.
The system has an automatic fault notification and remote access. If a fault occurs, the Xcom-LAN provides automatic notification to three different people through the Studer Access Portal which then can make the necessary changes.
Why Studer
Wind turbines have high start-up inrush currents and the Studer products have the ability to cope with surges close to 3 times its rated capacity. By using Studer's X-connect mounting system it was possible to install much power on a small surface, up to 24kVA per m2.
Project outcome
This system, developed on a tight budget, is functioning well providing the owner almost perfect autonomy from the grid and drastically reducing grid electricity cost and dependency.
Excess power generation is used to provide heat for drying the chicken litter, reducing the need for gas heating and its associated costs.
Italy: Capanna Gnifetti
The challenge
The Capanna Gnifetti mountain hut, is situated at 3647m above sea level in the Italian Alps close to the Monte Rosa massif. It offers 176 beds, community room, emergency room, shared bathrooms, showers and electric lighting. With a PV system of 2kW their backup diesel generator of 40 kVA was working most of the time. The mountain hut is easiest reached by helicopter which is both expensive and time-consuming. It is therefore of utmost importance that the installer brings all the necessary material, even a missing nut would delay the installation.
The solution
The actual energy needs of the mountain hut was thoroughly calculated and a 15kW off-grid system was installed. It is a three-phase system with one inverter per phase, and two MPPT regulators with strings of 15 modules each. The system can be monitored remotely thanks to the Xcom-LAN.
The installers delivered a complete kit, including batteries, modules, inverters and regulators, all already cabled and configured in their lab.
Why Studer
Project outcome
System components
250Wp WARIS SOLAR Polycrystalline
24 x MIDAC SPA - OPzV 800Ah C10
3 x STUDER XTH 6000-48 inverter / chargers
2 x STUDER VS-120 VarioString MPPT
Custom FGS Energie Alternative “FGS STORAGE” mounting plates. System is built inside a container.
STUDER RCC-02 control system
STUDER Xcom-LAN communication Set
STUDER BSP-1200 Battery Status Processor
Responsible company
FGS Energie Alternative
The challenge
The Capanna Gnifetti mountain hut, is situated at 3647m above sea level in the Italian Alps close to the Monte Rosa massif. It offers 176 beds, community room, emergency room, shared bathrooms, showers and electric lighting. With a PV system of 2kW their backup diesel generator of 40 kVA was working most of the time. The mountain hut is easiest reached by helicopter which is both expensive and time-consuming. It is therefore of utmost importance that the installer brings all the necessary material, even a missing nut would delay the installation.
The solution
The actual energy needs of the mountain hut was thoroughly calculated and a 15kW off-grid system was installed. It is a three-phase system with one inverter per phase, and two MPPT regulators with strings of 15 modules each. The system can be monitored remotely thanks to the Xcom-LAN.
The installers delivered a complete kit, including batteries, modules, inverters and regulators, all already cabled and configured in their lab.
Why Studer
Project outcome
Italy: Hybrid System
The challenge
The Anfora Island is a picturesque fishing village at the heart of the Grado lagoon situated on the north-eastern coast of Italy. Totally off-grid, the owners of the hotel and trattoria "Ai Ciodi" on this island had relied on a diesel generator for the electricity needed in their business and for the island's fresh water pump. By using energy from renewable sources (photovoltaic), they hope that the passing tourists will have a more enjoyable stay (tranquillity) and to reduce the ecological footprint on the surrounding nature.
The solution
In order to dimension the system properly a thorough calculation of the users' daily energy consumption through technical inspections and interviews was made taking into consideration the different energy needs during the open three seasons; Spring, Summer and Fall. The system is used for lights, cooking, refrigerators, air conditioning, satellite TV etc.
The resulting hybrid system consist of 36 x 185Wp PV panels, built and certified in accordance with EN61215 standards. For storage, 24 lead-acid batteries, OPZS1200 48Vdc/1200Ah-C10, were chosen to guarantee high reliability and low self-consumption. The solar charge controller, Power Tarom 4140, automatically manages the flow of energy to and from the battery and ensure maximum control and charge thereof. Then is also installed two inverter/chargers XTH 6000-48 in parallel, each feeding a line of electrical loads. A framework with Multiple insertion switch allows you to switch the two lines into a single inverter if supply fails.
As support to the PV system, there is one diesel generator 25kW in three-phase. The generator also run the fresh water pump for water supply of the whole island.
Why Studer
Studer products were chosen due to their outstanding quality, technical performance and features. For instance, in this installation the Xtender inverter/charger has been programmed to automatically control the genset. If there is not enough renewable energy for the electrical loads, the Xtender switches on the diesel generator. When there is no need for extra energy the genset is automatically switched off.
Project outcome
The combined action of the two systems: photovoltaic and diesel generator, guarantee the reliability and continuity of energy, avoiding troublesome and dangerous electrical blackouts. The idea of using energy from renewable sources (photovoltaic) makes the stay even more enjoyable to passing tourists, helping to spread the photovoltaic technology throughout the Grado Lagoon, a site of high natural value.
After the installation of the photovoltaic system, the diesel generator is only used 3 hours a day instead of the 8 hours prior to the PV system, which is a considerable reduction. According to the installing company's calculations, this PV hybrid system will pay for itself in about 5-6 years. The system's life is about 30 years and if the system's batteries are used properly (they have an estimated life of 8-9 years) the battery replacements will be repaid by annual cost savings produced by the system.
Other estimated savings that the system will produce during 30 years: Saved operating hours of the diesel generator system: 27 000h, saved litres of fuel: 130 410 litres, saved CO2: 490.78, saved Tonn SOx (Sulphur Oxide): 4.63, saved Tonn NOx (Nitrogen Oxide): 10.91, saved Tonn CO: 1.77, saved Tonn Toe (tonne of oil equivalents): 37.49.
System components
Responsible company
ENERECO srl
The challenge
The Anfora Island is a picturesque fishing village at the heart of the Grado lagoon situated on the north-eastern coast of Italy. Totally off-grid, the owners of the hotel and trattoria "Ai Ciodi" on this island had relied on a diesel generator for the electricity needed in their business and for the island's fresh water pump. By using energy from renewable sources (photovoltaic), they hope that the passing tourists will have a more enjoyable stay (tranquillity) and to reduce the ecological footprint on the surrounding nature.
The solution
In order to dimension the system properly a thorough calculation of the users' daily energy consumption through technical inspections and interviews was made taking into consideration the different energy needs during the open three seasons; Spring, Summer and Fall. The system is used for lights, cooking, refrigerators, air conditioning, satellite TV etc.
The resulting hybrid system consist of 36 x 185Wp PV panels, built and certified in accordance with EN61215 standards. For storage, 24 lead-acid batteries, OPZS1200 48Vdc/1200Ah-C10, were chosen to guarantee high reliability and low self-consumption. The solar charge controller, Power Tarom 4140, automatically manages the flow of energy to and from the battery and ensure maximum control and charge thereof. Then is also installed two inverter/chargers XTH 6000-48 in parallel, each feeding a line of electrical loads. A framework with Multiple insertion switch allows you to switch the two lines into a single inverter if supply fails.
As support to the PV system, there is one diesel generator 25kW in three-phase. The generator also run the fresh water pump for water supply of the whole island.
Why Studer
Studer products were chosen due to their outstanding quality, technical performance and features. For instance, in this installation the Xtender inverter/charger has been programmed to automatically control the genset. If there is not enough renewable energy for the electrical loads, the Xtender switches on the diesel generator. When there is no need for extra energy the genset is automatically switched off.
Project outcome
The combined action of the two systems: photovoltaic and diesel generator, guarantee the reliability and continuity of energy, avoiding troublesome and dangerous electrical blackouts. The idea of using energy from renewable sources (photovoltaic) makes the stay even more enjoyable to passing tourists, helping to spread the photovoltaic technology throughout the Grado Lagoon, a site of high natural value.
After the installation of the photovoltaic system, the diesel generator is only used 3 hours a day instead of the 8 hours prior to the PV system, which is a considerable reduction. According to the installing company's calculations, this PV hybrid system will pay for itself in about 5-6 years. The system's life is about 30 years and if the system's batteries are used properly (they have an estimated life of 8-9 years) the battery replacements will be repaid by annual cost savings produced by the system.
Other estimated savings that the system will produce during 30 years: Saved operating hours of the diesel generator system: 27 000h, saved litres of fuel: 130 410 litres, saved CO2: 490.78, saved Tonn SOx (Sulphur Oxide): 4.63, saved Tonn NOx (Nitrogen Oxide): 10.91, saved Tonn CO: 1.77, saved Tonn Toe (tonne of oil equivalents): 37.49.
Italy: Off-Grid Feed Distribution System
The Challenge
The challenge in this particular application was to guarantee a 24h / 24 power supply to a mobile system for distributing the feed in a trout farm. The system, which can be moved using motorized trolleys, had to be fully functional in all weather conditions. The system also needed to be as reliable as possible to avoid holes in production.
The Solution
The solution for this particular customer request was provided through the use of Studer devices mounted inside an IP65 panel.
The system have been pre-programmed, mounted and wired in our laboratory in order to guarantee an easy and quick installation on the site. The studer system in this case feeds the trolley motors and a PLC. The PLC allows the trolley to return to position 0 during the night for a possible nightly charging of the battery pack, for this reason inverter-chargers have been used.
Why Studer
We have chosen Studer for the great reliability of its products and above all for the strength of the machines supplied, the conditions in which the system must work are in fact very adverse because of the low temperatures and of the continuous handling of the panel in which the devices are contained. Another reason why we chose to use Studer's Inverters is linked to the fact that they have a remarkable starting capacity compared to other brands, and this is very useful in this application.
Project Outcome
This unique solution made possible the distribution of the the feed to the trout of the farm without moving heavy batteries on the trolleys every day and without using other forms of external power supply that would have made the trolleys handling more difficult.
Furthermore, the use of photovoltaic panels has made it possible to economize on the purchase of electricity from the national network and therefore to have a not too high pay-back time.
System components
3x Inverter Studer Charger XTM 4000 48V
1x Studer RCC-02 Remote Control and Programming Centre
1x Studer VarioTrack VT-65
24x Elements OpzS 420Ah
Responsible company
FGS Energie Alternative Srl
The Challenge
The challenge in this particular application was to guarantee a 24h / 24 power supply to a mobile system for distributing the feed in a trout farm. The system, which can be moved using motorized trolleys, had to be fully functional in all weather conditions. The system also needed to be as reliable as possible to avoid holes in production.
The Solution
The solution for this particular customer request was provided through the use of Studer devices mounted inside an IP65 panel.
The system have been pre-programmed, mounted and wired in our laboratory in order to guarantee an easy and quick installation on the site. The studer system in this case feeds the trolley motors and a PLC. The PLC allows the trolley to return to position 0 during the night for a possible nightly charging of the battery pack, for this reason inverter-chargers have been used.
Why Studer
We have chosen Studer for the great reliability of its products and above all for the strength of the machines supplied, the conditions in which the system must work are in fact very adverse because of the low temperatures and of the continuous handling of the panel in which the devices are contained. Another reason why we chose to use Studer's Inverters is linked to the fact that they have a remarkable starting capacity compared to other brands, and this is very useful in this application.
Project Outcome
This unique solution made possible the distribution of the the feed to the trout of the farm without moving heavy batteries on the trolleys every day and without using other forms of external power supply that would have made the trolleys handling more difficult.
Furthermore, the use of photovoltaic panels has made it possible to economize on the purchase of electricity from the national network and therefore to have a not too high pay-back time.
Italy: The power of silence
The Challenge
Embracing the green Choice. Reduce the run time of traditional diesel generator and start benefiting from complete silent, highly efficient and emission-free power.
The Solution
Enercubo Series Hybrid TecnoGen power generators with lithium battery and photovoltaic panels (as option) are available in an ultra-silent Fusteq canopy (or ISO standard 20’ container depending on the power).
They are equipped with Tier IV F or STAGE V engines, and Archimede lithium batteries with full customization options.
ENERCUBO are suitable to be powered by renewable energy sources. Solar chargers could be easily integrated. They are a real silent solution in battery mode.
They are the perfect solution for working in places with high human density, such as construction sites in the cities.
High performance is guaranteed. The high number of recharge cycles and the absence of maintenance have made this product the best solution for energy storage.
Best control is ensured with Archimede BMS (Battery Management System) Hermes M3 with has been designed to let the batteries communicate with the other components (solar chargers, inverters) for key-information sharing.
Why STUDER
STUDER offers reliability for the customer’s needs; with its flexibility, durability and 10-year warranty. The fact that it bears the "Swiss Made" label is a guarantee of top quality recognised all over the world.
Project Outcome
• fuel saving
• lower co2 emission
• clean energy on hand for every application
• less maintenance service with consequent opex
(operational expense) reduction
• zero noise for a truly silent solution (in battery mode)
• longer engine life for less engine running hours
• engine service cost reduction
• low load problems solved
• no interruption with peak of power management
• power always available off-grid
• plug&play connectivity
• connection to other renewable energy source
(solar panels, wind turbines, hydroelectric turbine)
System components
Hybrid power generator in canopy equipped with Stage V engine (or Tier IV final)
Archimede Energia Lithium battery (PJO-400-150-TDA model)
Studer Inverters (xtender and accessories)
Photovoltaic panels (option)
Responsible company
TECNOGEN spa and Archimede Energia
The Challenge
Embracing the green Choice. Reduce the run time of traditional diesel generator and start benefiting from complete silent, highly efficient and emission-free power.
The Solution
Enercubo Series Hybrid TecnoGen power generators with lithium battery and photovoltaic panels (as option) are available in an ultra-silent Fusteq canopy (or ISO standard 20’ container depending on the power).
They are equipped with Tier IV F or STAGE V engines, and Archimede lithium batteries with full customization options.
ENERCUBO are suitable to be powered by renewable energy sources. Solar chargers could be easily integrated. They are a real silent solution in battery mode.
They are the perfect solution for working in places with high human density, such as construction sites in the cities.
High performance is guaranteed. The high number of recharge cycles and the absence of maintenance have made this product the best solution for energy storage.
Best control is ensured with Archimede BMS (Battery Management System) Hermes M3 with has been designed to let the batteries communicate with the other components (solar chargers, inverters) for key-information sharing.
Why STUDER
STUDER offers reliability for the customer’s needs; with its flexibility, durability and 10-year warranty. The fact that it bears the "Swiss Made" label is a guarantee of top quality recognised all over the world.
Project Outcome
• fuel saving
• lower co2 emission
• clean energy on hand for every application
• less maintenance service with consequent opex
(operational expense) reduction
• zero noise for a truly silent solution (in battery mode)
• longer engine life for less engine running hours
• engine service cost reduction
• low load problems solved
• no interruption with peak of power management
• power always available off-grid
• plug&play connectivity
• connection to other renewable energy source
(solar panels, wind turbines, hydroelectric turbine)
Jordan border: Off-grid system
The challenge
Far away from the grid in the Jordanian military barracks, Al-Ruwashid, Al-Hadalat to Ruqban, Jordan border. The transmission line for the national grid is far away, an offgrid solar system was the answer for powering Jordanian military barracks.
Why STUDER
The VarioString high-voltage MPPT solar charge controller that provides balance of system advantages not available from any other suppliers. The Xtender inverter/charger with a surge capacity that can handle three times its nominal power which is a great benefit in systems that have to cope with the start-up of largewater pumps. No other device on the market has this kind of capacity.
The solution
As Jordan has 320 days of sunshine per year, the IOM choose solar energy for their new backup system for Jordanian military barracks. The system consists of two parts. The first part consists of eight towers, each with a 35.15 kWp PV array, 3 XTH 6000-48, 5 VS-120, 1 VS-70 and a 3182Ah@C72 battery bank. The second part consists of one tower with a 75.26 kWp PV array, 3 XTH 6000-48, 11 VS-120 and a 3182Ah @C72 battery bank.
Project outcome
Jordanian military barracks enjoy access to energy through a stand-alone system that provides them with power whenever they need it.
The new backup system ensures the availability of power during working hours or during any time.
System components
27x Studer XTH 6000-48
BAE 17 PVV 3230
BAE 24 PVV 4560
51x Studer VarioString VS-120
8x Studer VarioString VS-70
Ground Mount solar
Responsible company
Schweikh Establishment for Contracting
The challenge
Far away from the grid in the Jordanian military barracks, Al-Ruwashid, Al-Hadalat to Ruqban, Jordan border. The transmission line for the national grid is far away, an offgrid solar system was the answer for powering Jordanian military barracks.
Why STUDER
The VarioString high-voltage MPPT solar charge controller that provides balance of system advantages not available from any other suppliers. The Xtender inverter/charger with a surge capacity that can handle three times its nominal power which is a great benefit in systems that have to cope with the start-up of largewater pumps. No other device on the market has this kind of capacity.
The solution
As Jordan has 320 days of sunshine per year, the IOM choose solar energy for their new backup system for Jordanian military barracks. The system consists of two parts. The first part consists of eight towers, each with a 35.15 kWp PV array, 3 XTH 6000-48, 5 VS-120, 1 VS-70 and a 3182Ah@C72 battery bank. The second part consists of one tower with a 75.26 kWp PV array, 3 XTH 6000-48, 11 VS-120 and a 3182Ah @C72 battery bank.
Project outcome
Jordanian military barracks enjoy access to energy through a stand-alone system that provides them with power whenever they need it.
The new backup system ensures the availability of power during working hours or during any time.
Kenya: Rural Hospital in the Masai Region
The challenge
Help Masai is a registered Kenyan community-based organization, with the mission “Helping improve maternity and child care, income generation training, and food growing in the Masai region of Kenya”. This project consists of the development of a maternity / child hospital in Ngoswani since the nearest hospital that provides 24/7 emergency Cesarean section operations is 160 Kms (100 miles) away on roads that are not well maintained in this very remote region.
The solution
The Lions Maternal Child Health Centre in the Masai region is in a remote part of Kenya with no access to electricity. Now the health centre can provide 24/7 medical services thanks to the energy system installed.
The solar power charges the battery bank during the day. The battery system with Studer inverters ensures continuous electricity supply to the health centre and all of the equipment installed there. The second Studer inverter provides a second output at 120Vac for US manufactured medical devices available in the hospital.
Why Studer
The Studer solution, as always, is robust and suitable for the rural and harsh conditions of this part of Kenya. The flexibility of having two different outputs enables the use of different medical devices donated by European and American organizations. The remote monitoring facilitates the follow up of the installation by the technicians from both Nairobi and the US and reduce the need for travel to site.
Project outcome
The hospital will provide a reliable service available 24h/7 improving the maternity/child medical services and care in the Masai region. This includes the advanced medical equipment not usually available in this region, powered by the Studer system. This will also encourage doctors from the city to be deployed in this rural area, bringing their skills and ensuring an improved service contributing to an increased life expectancy for births in this region.
System components
7kWp Amerisolar AS-6P30-255W
24 x Sunlight RES 2V OPzV 1360
1 x STUDER XTH 6000-48 (standard AC-output at 230Vac)
1 x STUDER XTH 6000-48-01 (AC-output at 120Vac for specific medical devices)
1 x STUDER VS-120 VarioString MPPT
RCC-02, BSP-500 and Xcom-LAN for remote monitoring from USA
Responsible company
Center for Alternative Technologies (CAT) Kenya
The challenge
Help Masai is a registered Kenyan community-based organization, with the mission “Helping improve maternity and child care, income generation training, and food growing in the Masai region of Kenya”. This project consists of the development of a maternity / child hospital in Ngoswani since the nearest hospital that provides 24/7 emergency Cesarean section operations is 160 Kms (100 miles) away on roads that are not well maintained in this very remote region.
The solution
The Lions Maternal Child Health Centre in the Masai region is in a remote part of Kenya with no access to electricity. Now the health centre can provide 24/7 medical services thanks to the energy system installed.
The solar power charges the battery bank during the day. The battery system with Studer inverters ensures continuous electricity supply to the health centre and all of the equipment installed there. The second Studer inverter provides a second output at 120Vac for US manufactured medical devices available in the hospital.
Why Studer
The Studer solution, as always, is robust and suitable for the rural and harsh conditions of this part of Kenya. The flexibility of having two different outputs enables the use of different medical devices donated by European and American organizations. The remote monitoring facilitates the follow up of the installation by the technicians from both Nairobi and the US and reduce the need for travel to site.
Project outcome
The hospital will provide a reliable service available 24h/7 improving the maternity/child medical services and care in the Masai region. This includes the advanced medical equipment not usually available in this region, powered by the Studer system. This will also encourage doctors from the city to be deployed in this rural area, bringing their skills and ensuring an improved service contributing to an increased life expectancy for births in this region.
Kenya: UPS back-up system at Kenya's First Green Certified Building Dunhill Towers
The challenge
Late in 2018 the European Union Delegation to Kenya relocated offices from the Upper Hill region of the Kenyan capital, Nairobi – to the 21 floor Dunhill building in Westlands. The delegation set very high standards regarding general security, and this also extended to requirements in terms of energy security. Due to the important nature of the information stored and systems running on their servers and computers, it is critical that the equipment is not exposed to power cuts due to grid-supplied power failures.
The Solution
In order to ensure continuous power supply to the new offices, the decision was taken to install a back-up system that included the Studer components and energy storage. This system design ensures that the offices never experience periods without power. When the grid fails, the offices and all of the equipment, devices and lights they use to perform their work, remain connected to the Studer system and uses the energy stored in the batteries. The 17 XTH 6000-48 inverter/chargers are installed in separate systems distributed across the office space with their own battery banks of different sizes. It was therefore possible to adjust the parameter settings for individual systems per very specific requirements if needed in the future.
Why Studer
The Studer equipment have been programmed to sense any grid failure and will, in the case of an outage, open the transfer relay and supply the offices from the battery storage. The transfer relay in Studer inverter/chargers opens in less than 15 milli-seconds and therefore the power supply will be un-interrupted, and the equipment will not be affected. The reliability of the Studer equipment along with the 10-year warranty was also very important to the delegation when they assessed the options in terms of system components. Studer technical staff assisted local installation partners with the commissioning of the site and provide ongoing support as required.
Project outcome
Being a 5-star rated green building, it was also very beneficial to the sustainable design that the system installed uses energy stored in fully re-cyclable AGM batteries and inverted to supply the AC loads of the offices. The building has also become the first in East Africa to be assessed under the green star TM-Africa tool, focusing on advanced green features and awarded the 5-star rating by the World Green Building Council.
System components
17x STUDER inverter/chargers Xtender XTH 6000-48
4x RCC-02 STUDER Remote Control Centres
4x BTS-01 STUDER battery temperature sensors
104x Trojan SAGM 06 375 AGM Batteries
Responsible company
Center for Alternative Technologies (CAT)
The challenge
Late in 2018 the European Union Delegation to Kenya relocated offices from the Upper Hill region of the Kenyan capital, Nairobi – to the 21 floor Dunhill building in Westlands. The delegation set very high standards regarding general security, and this also extended to requirements in terms of energy security. Due to the important nature of the information stored and systems running on their servers and computers, it is critical that the equipment is not exposed to power cuts due to grid-supplied power failures.
The Solution
In order to ensure continuous power supply to the new offices, the decision was taken to install a back-up system that included the Studer components and energy storage. This system design ensures that the offices never experience periods without power. When the grid fails, the offices and all of the equipment, devices and lights they use to perform their work, remain connected to the Studer system and uses the energy stored in the batteries. The 17 XTH 6000-48 inverter/chargers are installed in separate systems distributed across the office space with their own battery banks of different sizes. It was therefore possible to adjust the parameter settings for individual systems per very specific requirements if needed in the future.
Why Studer
The Studer equipment have been programmed to sense any grid failure and will, in the case of an outage, open the transfer relay and supply the offices from the battery storage. The transfer relay in Studer inverter/chargers opens in less than 15 milli-seconds and therefore the power supply will be un-interrupted, and the equipment will not be affected. The reliability of the Studer equipment along with the 10-year warranty was also very important to the delegation when they assessed the options in terms of system components. Studer technical staff assisted local installation partners with the commissioning of the site and provide ongoing support as required.
Project outcome
Being a 5-star rated green building, it was also very beneficial to the sustainable design that the system installed uses energy stored in fully re-cyclable AGM batteries and inverted to supply the AC loads of the offices. The building has also become the first in East Africa to be assessed under the green star TM-Africa tool, focusing on advanced green features and awarded the 5-star rating by the World Green Building Council.
Kingdom of Saudi Arabia: Off grid System at K.A.CARE
The challenge
K.A.CARE weather monitoring station experience frequent and long duration blackouts due to the failure of diesel generators. To reduce the maintenance / repair cost of diesel generator and to have a stable power supply, K.A.CARE started to look for a new energy solution for their weather monitoring station and to take the advantage of KSA’s climate by installing a 39.6kWp solar system on their weather monitoring station at Al Uyayanah, near Riyadh, KSA. Our exclusive partner M/s Innovative Systems were involved in installing, testing and commissioning of the subject energy solution.
Why STUDER
Because of location reliability of the system is critically important. Temperature and dust levels in this part of KSA gets high and Studer devices robustness and performance in the harsh climates appealed to the customer. The setup of the system is also easy in terms of charge cycles of batteries because the VarioString units are synchronized with the Xtender. With Studer’s products, the system design and implementation is smooth and great experience. Further studer’s inverter/charger enables 3 phase supply and comes with 5 years warranty. The generator auto start is also managed very easily by battery SOC, voltage and /or time of the day.
The solution
The total PV capacity 39.6kWp is enough for complete connected load of the system with one day of battery autonomy. It ensures continuous power supply to the station with a backup system that includes Studer components and energy storage. With this system it is possible to control environment where the batteries and power electronics installed. Maintenance also much more manageable and also easier to clean and maintain the solar panels.
Project outcome
This backup storage system ensures continuous power supply to the station. With this robust system design, the lifespan of system components are prolonged. The oversized PV array ensures the full recharge of storage batteries and Studer power electronics managing all aspects of system functionality and remote communication capabilities. The system can be managed from anywhere in the world via Studer online portal.
System components
120x PV modules capacity (330Wp)
48x Storage Batteries (2317Ah @ C10) lead acid maintenance free
3x Studer xtm 4000-48-01 Inverter/Charge Xtender
10x Studer vt 65 VarioTrack MPPT solar charge controller
1x Studer bsp 1200 Battery status processor
1x Studer rcc 02 Remote control
1x Studer xcom-lan internet based communication set
Responsible company
Innovative Systems (Isys)
The challenge
K.A.CARE weather monitoring station experience frequent and long duration blackouts due to the failure of diesel generators. To reduce the maintenance / repair cost of diesel generator and to have a stable power supply, K.A.CARE started to look for a new energy solution for their weather monitoring station and to take the advantage of KSA’s climate by installing a 39.6kWp solar system on their weather monitoring station at Al Uyayanah, near Riyadh, KSA. Our exclusive partner M/s Innovative Systems were involved in installing, testing and commissioning of the subject energy solution.
Why STUDER
Because of location reliability of the system is critically important. Temperature and dust levels in this part of KSA gets high and Studer devices robustness and performance in the harsh climates appealed to the customer. The setup of the system is also easy in terms of charge cycles of batteries because the VarioString units are synchronized with the Xtender. With Studer’s products, the system design and implementation is smooth and great experience. Further studer’s inverter/charger enables 3 phase supply and comes with 5 years warranty. The generator auto start is also managed very easily by battery SOC, voltage and /or time of the day.
The solution
The total PV capacity 39.6kWp is enough for complete connected load of the system with one day of battery autonomy. It ensures continuous power supply to the station with a backup system that includes Studer components and energy storage. With this system it is possible to control environment where the batteries and power electronics installed. Maintenance also much more manageable and also easier to clean and maintain the solar panels.
Project outcome
This backup storage system ensures continuous power supply to the station. With this robust system design, the lifespan of system components are prolonged. The oversized PV array ensures the full recharge of storage batteries and Studer power electronics managing all aspects of system functionality and remote communication capabilities. The system can be managed from anywhere in the world via Studer online portal.
Latin America: Euro Solar Off-Grid project in 8 countries, Rural Electrification
The challenge
To improve the living conditions in the rural communities of Latin America's eight most disadvantaged countries through the use of renewable energy. To help the inhabitants to fight against poverty, isolation and marginalisation resulting from their socioeconomic conditions.
The solution
The EURO-SOLAR Programme helped the communities through the installation of kits that provides electricity, communication facilities in form of computers, an internet connection and a projector and health care devices such as a refrigerator for medicine and a water purifier.
Most of the beneficiary communities (70%) opted for a solar-energy system. The consistent wind in Bolivia and in Peru, led these countries to choose mixed solar-wind systems. 12 Gel batteries store the energy for access to electricity around the clock.
A control panel monitors and manages the electricity storage and directs the power to the facilities.
This project used a participatory approach where the communities has to cover the expenses for the operation and maintenance of the equipment included in the EURO-SOLAR kit. For that reason the system has been designed to be user-friendly and its equipment carefully selected for its robustness, reliability and ease of repair.
Why Studer
As these systems are installed in remote areas, EURO-SOLAR wanted products of high reliability that were produced in Europe.
Project outcome
At the end of the EURO-SOLAR Programme 600 power-generation kits had been installed providing electricity, based exclusively on renewable energy sources, to over 300 000 people in 600 rural communities in Latin America previously without access to electricity.
The total budget was 36.4 million Euros, co-financed by the European Union (80%) and the national governments of the beneficiary countries (20%).
System components
5m2 of PV panels
A wind turbine (30% of communities)
12 x gel batteries
1 x solar charge regulator
1 x STUDER Inverter AJ 1300-24
1 x STUDER Inverter AJ 350-24
A cinder-block shed to protect the batteries
A control panel and power supply
A safety fence for the enclosure
Responsible company
Eurosolar
The challenge
To improve the living conditions in the rural communities of Latin America's eight most disadvantaged countries through the use of renewable energy. To help the inhabitants to fight against poverty, isolation and marginalisation resulting from their socioeconomic conditions.
The solution
The EURO-SOLAR Programme helped the communities through the installation of kits that provides electricity, communication facilities in form of computers, an internet connection and a projector and health care devices such as a refrigerator for medicine and a water purifier.
Most of the beneficiary communities (70%) opted for a solar-energy system. The consistent wind in Bolivia and in Peru, led these countries to choose mixed solar-wind systems. 12 Gel batteries store the energy for access to electricity around the clock.
A control panel monitors and manages the electricity storage and directs the power to the facilities.
This project used a participatory approach where the communities has to cover the expenses for the operation and maintenance of the equipment included in the EURO-SOLAR kit. For that reason the system has been designed to be user-friendly and its equipment carefully selected for its robustness, reliability and ease of repair.
Why Studer
As these systems are installed in remote areas, EURO-SOLAR wanted products of high reliability that were produced in Europe.
Project outcome
At the end of the EURO-SOLAR Programme 600 power-generation kits had been installed providing electricity, based exclusively on renewable energy sources, to over 300 000 people in 600 rural communities in Latin America previously without access to electricity.
The total budget was 36.4 million Euros, co-financed by the European Union (80%) and the national governments of the beneficiary countries (20%).
Latin America: Pepamobile, Bruno Furer, Mobile Application
The challenge
Mr and Mrs Furer are an adventurous couple that loves to travel and to discover different countries around the world aboard their van "The Pepamobil". Traditionally, a combination of the vehicle's 24 volt, 220 volt and gas is used to provide power in vehicles. Mr Furer started out with a system combining solar panels with a gas generator and 120l gas tank. However, the gas tank had some problems with the height and temperature when they travelled in South America. Mr Furer started to think of a new improved system. This new system would have to work continuously 24/7, whatever the environment. The truck would visit places up to 5.000 meters above sea level with temperatures from -25°C up to +40°C and humidity up to 95%.
The solution
The mobile hybrid system is completely running on 220V with a small battery bank. It powers a refrigerator, a freezer, an induction hob, an oven, a water pump, lights and other loads. The procurement of household appliances becomes easier and a lot cheaper when all appliances are 220V. The network is more stable than the one from the socket (!).
The system includes solar panels, MPPT solar charge controllers, an inverter/charger and batteries. Additional energy comes from a windturbine.
Why Studer
After having looked at various products on the market such as an Australian system and Mastervolt, they opted for Studer. Decisive for Mr Furer was the HP-Compact inverter/charger's adjustable charge detection system (1-20W) that allows the smallest energy consumption and ensures a long life of the battery. Another important factor was that the product is entirely manufactured in Switzerland.
Project outcome
The Pepamobil has, so far, been confronted with the climate of the following countries without any problem: Morocco, South Africa, Namibia, Botswana, Mozambique, Zimbabwe, USA, Canada, Mexico, El Salvador, Honduras, Nicaragua, Guatemala, Belize, Yucatan, Costa Rica, Panama, Columbia, Venezuela, Ecuador, Peru, Paraguay Bolivia, Argentina, Chile, Brasil, Franz Guyana, Surinam, Guyana, and Europa.
Mr and Mrs Furer are pleased to have gained independence from gas, 110V and a 220V grid connection. Almost every country has its own gas connections and rules on how to refuel gas cylinders. With gas the power fluctuated between 95-220 volts making it hard for their electronics to follow. The battery based system provide them with a very stable and secure power supply. Also, they no longer have to worry about gas replacement or if there will be enough energy during their travels, making them more comfortable and less stressful.
After ten years their chosen system is still working very well; they never have had to eat cold food…
System components
Responsible company
Bruno Furer
The challenge
Mr and Mrs Furer are an adventurous couple that loves to travel and to discover different countries around the world aboard their van "The Pepamobil". Traditionally, a combination of the vehicle's 24 volt, 220 volt and gas is used to provide power in vehicles. Mr Furer started out with a system combining solar panels with a gas generator and 120l gas tank. However, the gas tank had some problems with the height and temperature when they travelled in South America. Mr Furer started to think of a new improved system. This new system would have to work continuously 24/7, whatever the environment. The truck would visit places up to 5.000 meters above sea level with temperatures from -25°C up to +40°C and humidity up to 95%.
The solution
The mobile hybrid system is completely running on 220V with a small battery bank. It powers a refrigerator, a freezer, an induction hob, an oven, a water pump, lights and other loads. The procurement of household appliances becomes easier and a lot cheaper when all appliances are 220V. The network is more stable than the one from the socket (!).
The system includes solar panels, MPPT solar charge controllers, an inverter/charger and batteries. Additional energy comes from a windturbine.
Why Studer
After having looked at various products on the market such as an Australian system and Mastervolt, they opted for Studer. Decisive for Mr Furer was the HP-Compact inverter/charger's adjustable charge detection system (1-20W) that allows the smallest energy consumption and ensures a long life of the battery. Another important factor was that the product is entirely manufactured in Switzerland.
Project outcome
The Pepamobil has, so far, been confronted with the climate of the following countries without any problem: Morocco, South Africa, Namibia, Botswana, Mozambique, Zimbabwe, USA, Canada, Mexico, El Salvador, Honduras, Nicaragua, Guatemala, Belize, Yucatan, Costa Rica, Panama, Columbia, Venezuela, Ecuador, Peru, Paraguay Bolivia, Argentina, Chile, Brasil, Franz Guyana, Surinam, Guyana, and Europa.
Mr and Mrs Furer are pleased to have gained independence from gas, 110V and a 220V grid connection. Almost every country has its own gas connections and rules on how to refuel gas cylinders. With gas the power fluctuated between 95-220 volts making it hard for their electronics to follow. The battery based system provide them with a very stable and secure power supply. Also, they no longer have to worry about gas replacement or if there will be enough energy during their travels, making them more comfortable and less stressful.
After ten years their chosen system is still working very well; they never have had to eat cold food…
Mexico: Backup system, Battery Master
El Proyecto
Debido a la necesidad corporativa de la empresa Battery Master para poder dar servicio y atender a los clientes de forma continuada, esto obliga a la empresa a estar conectada a la red eléctrica de manera permanente, para un funcionamiento correcto de todos sus equipos y sistemas de comunicación en línea.
Las oficinas centrales de Battery Master no deben tener inestabilidad de voltaje de la red eléctrica, ya que en ellas se encuentra el servidor general, el cual es punto central de las tiendas y oficinas a nivel nacional, siendo este un punto crítico.
Por ello se tomó la decisión de trabajar con STUDER utilizando sus equipos en combinación con baterías de la marca TROJAN, para cuando exista inestabilidad en la red eléctrica nacional o ausencia de ésta, puedan todos los sistemas ser alimentados desde los equipos STUDER trabajando como sistemas de alimentación ininterrumpida.
Además las especificaciones y características técnicas de los inversores/cargadores STUDER más las baterías TROJAN, permiten una autonomía de trabajo calculada en ausencia de red local.
La Solución
Para cumplir con el objetivo de eliminar los cortes de tensión que suceden en la zona, se implementó un respaldo con baterías TROJAN IND33-2V 2405Ah en C100, con lo cual se ha reducido las horas de inactividad gracias al banco de baterías. Estas baterías son cargadas a través del inversor/cargador STUDER desde la red eléctrica local para que estén siempre listas por si ocurre un apagón. En dicho caso, las instalaciones no se ven afectadas y son capaces de trabajar durante la autonomía completa definida.
Por Qué STUDER
STUDER es una marca reconocida en sistemas de soluciones para instalaciones remotas de telecomunicaciones y sistemas de respaldo, por la robustez de sus equipos. Una de las razones más importantes es que los equipos ofrecen un nivel de incidencias mínimo además de una garantía de 10 años siendo el equipo más económico al final de la vida.
Resultado del Proyecto
La solución ofrecida, basado en la acumulación directa a baterías, evita los cortes de tensión eléctrica, lo cual incrementa la productividad laboral, ya que se mantiene un horario continuo de trabajo y se evitan momentos de inactividad en oficinas y tiendas a nivel nacional.
System components
1 x Inversor / Cargador STUDER XTH 5000-24-01
12 x Elementos de baterías estacionarias TROJAN IND33 2V de 1849Ah en C 20
1 x Elemento de monitoreo STUDER Xcom-LAN
Responsible company
Battery Master
El Proyecto
Debido a la necesidad corporativa de la empresa Battery Master para poder dar servicio y atender a los clientes de forma continuada, esto obliga a la empresa a estar conectada a la red eléctrica de manera permanente, para un funcionamiento correcto de todos sus equipos y sistemas de comunicación en línea.
Las oficinas centrales de Battery Master no deben tener inestabilidad de voltaje de la red eléctrica, ya que en ellas se encuentra el servidor general, el cual es punto central de las tiendas y oficinas a nivel nacional, siendo este un punto crítico.
Por ello se tomó la decisión de trabajar con STUDER utilizando sus equipos en combinación con baterías de la marca TROJAN, para cuando exista inestabilidad en la red eléctrica nacional o ausencia de ésta, puedan todos los sistemas ser alimentados desde los equipos STUDER trabajando como sistemas de alimentación ininterrumpida.
Además las especificaciones y características técnicas de los inversores/cargadores STUDER más las baterías TROJAN, permiten una autonomía de trabajo calculada en ausencia de red local.
La Solución
Para cumplir con el objetivo de eliminar los cortes de tensión que suceden en la zona, se implementó un respaldo con baterías TROJAN IND33-2V 2405Ah en C100, con lo cual se ha reducido las horas de inactividad gracias al banco de baterías. Estas baterías son cargadas a través del inversor/cargador STUDER desde la red eléctrica local para que estén siempre listas por si ocurre un apagón. En dicho caso, las instalaciones no se ven afectadas y son capaces de trabajar durante la autonomía completa definida.
Por Qué STUDER
STUDER es una marca reconocida en sistemas de soluciones para instalaciones remotas de telecomunicaciones y sistemas de respaldo, por la robustez de sus equipos. Una de las razones más importantes es que los equipos ofrecen un nivel de incidencias mínimo además de una garantía de 10 años siendo el equipo más económico al final de la vida.
Resultado del Proyecto
La solución ofrecida, basado en la acumulación directa a baterías, evita los cortes de tensión eléctrica, lo cual incrementa la productividad laboral, ya que se mantiene un horario continuo de trabajo y se evitan momentos de inactividad en oficinas y tiendas a nivel nacional.
Mexico: Sistema Aislado
El Proyecto
La necesidad energética que existe en el lugar ubicado en la zona del estado de Quintana Roo, y la falta de suministro energético por parte de CFE, compañía suministradora de electricidad del México, hace que el cliente utilice una solución con energías renovables. Además, evita así un consumo constante con combustibles diésel que sería de un coste exagerado.
Es por ello que la propuesta, utilizando equipos STUDER, es la solución elegida por el cliente para trabajar en zonas remotas, acumulando la energía producida por los paneles en bancos de baterías y poder así, disminuir el consumo de diésel prácticamente a cero.
La Solución
Para evitar consumo de diésel, se han instalado baterías de plomo-ácido de ciclo profundo tecnología GEL del tipo OPzV, con lo cual se han reducido las horas de funcionamiento de los generadores diésel prácticamente a cero gracias a la energía obtenida con los paneles fotovoltaicos. Mediante las baterías ha sido posibles acumular la energía producida por los paneles fotovoltaicos durante el día y abastecer los consumos nocturnos. Solo en caso de no haber producción fotovoltaica se recurre al consumo de energía producida con el grupo electrógeno.
Por Qué STUDER
STUDER es una marca reconocida en sistemas de soluciones para instalaciones aisladas remotas por la robustez de sus equipos. Una de las razones más importantes es que los equipos ofrecen un nivel de incidencias mínimo.
Además, es el único fabricante de reguladores MPPT de 120 amperios, que simplifican la instalación eléctrica ya que pueden trabajar a 900Vdc.
La flexibilidad que permite STUDER optimiza una reducción de costes comparados con otros fabricantes a la hora de ejecutar la instalación.
El marcado Swiss Made tuvo un impacto muy positivo en el cliente.
Resultado del Proyecto
La necesidad energética por parte del cliente y la ausencia de la red pública hace indispensable la instalación de este sistema de generación solar y almacenamiento, que le garantiza un buen suministro energético confiable y robusto, cumpliendo de esta manera con la solicitud de consumos requerida por el cliente.
La solución ofrecida, basada en la acumulación directa a baterías, evita el uso constante de generadores eléctricos de diésel, ahorrando en el consumo diésel y consiguiendo unos tiempos de retorno de inversión mucho más cortos, añadiendo que los equipos cuentan con 10 años de garantía.
Battery Master apoyó en la puesta en marcha de la solución para tranquilidad del cliente final, con la supervisión del Ing. Ernesto Carrillo.
System components
9 x Inversor / Cargador de XTH 6000-48-01 STUDER
9 x Regulador solar MPPT VS-120
1 x control remoto RCC-02
1 x monitoreo remoto XCOM-LAN STUDER
198 x Paneles Solares de 340W a 48v
72 x Elementos de baterías estacionarias OPzV BAE 20 PVV 3800 DE 3220 AH C20.
1 x Grupo electrógeno de 125 kW automático
Responsible company
Battery Master
El Proyecto
La necesidad energética que existe en el lugar ubicado en la zona del estado de Quintana Roo, y la falta de suministro energético por parte de CFE, compañía suministradora de electricidad del México, hace que el cliente utilice una solución con energías renovables. Además, evita así un consumo constante con combustibles diésel que sería de un coste exagerado.
Es por ello que la propuesta, utilizando equipos STUDER, es la solución elegida por el cliente para trabajar en zonas remotas, acumulando la energía producida por los paneles en bancos de baterías y poder así, disminuir el consumo de diésel prácticamente a cero.
La Solución
Para evitar consumo de diésel, se han instalado baterías de plomo-ácido de ciclo profundo tecnología GEL del tipo OPzV, con lo cual se han reducido las horas de funcionamiento de los generadores diésel prácticamente a cero gracias a la energía obtenida con los paneles fotovoltaicos. Mediante las baterías ha sido posibles acumular la energía producida por los paneles fotovoltaicos durante el día y abastecer los consumos nocturnos. Solo en caso de no haber producción fotovoltaica se recurre al consumo de energía producida con el grupo electrógeno.
Por Qué STUDER
STUDER es una marca reconocida en sistemas de soluciones para instalaciones aisladas remotas por la robustez de sus equipos. Una de las razones más importantes es que los equipos ofrecen un nivel de incidencias mínimo.
Además, es el único fabricante de reguladores MPPT de 120 amperios, que simplifican la instalación eléctrica ya que pueden trabajar a 900Vdc.
La flexibilidad que permite STUDER optimiza una reducción de costes comparados con otros fabricantes a la hora de ejecutar la instalación.
El marcado Swiss Made tuvo un impacto muy positivo en el cliente.
Resultado del Proyecto
La necesidad energética por parte del cliente y la ausencia de la red pública hace indispensable la instalación de este sistema de generación solar y almacenamiento, que le garantiza un buen suministro energético confiable y robusto, cumpliendo de esta manera con la solicitud de consumos requerida por el cliente.
La solución ofrecida, basada en la acumulación directa a baterías, evita el uso constante de generadores eléctricos de diésel, ahorrando en el consumo diésel y consiguiendo unos tiempos de retorno de inversión mucho más cortos, añadiendo que los equipos cuentan con 10 años de garantía.
Battery Master apoyó en la puesta en marcha de la solución para tranquilidad del cliente final, con la supervisión del Ing. Ernesto Carrillo.
Mexico: Sistema de Video Vigilancia
El Proyecto
La necesidad de mantener un área debidamente monitoreada por cuestiones de seguridad perimetral fue lo que motivó a un fraccionamiento localizado en Monterrey N.L. ubicado en la parte alta de uno de los cerros de la ciudad a utilizar los sistemas descritos en este caso de estudio.
Este fraccionamiento por cuestión de su ubicación requería tener una visión total monitoreada de su espacio. Por su ubicación no es rentable tener personal haciendo recorridos, debido a que, por cuestión de distancias y topografía, es difícil y costoso. Por ello se utilizaron 14 sistemas remotos para poder tener monitoreado todo el perímetro del fraccionamiento.
La solucíon
Para cumplir con el objetivo de mantener el espacio monitoreado permanentemente se instalaron equipos de generación de energía fotovoltaica. Gracias a los controladores solares MORNINGSTAR se almacena energía en las baterías TROJAN, pues es la fuente más fiable para brindar la seguridad de almacenamiento y tener disponibilidad de energía. Por medio de los inversores AJ de STUDER se alimentan consumos en corriente alterna desde las baterías como una cámara de video vigilancia y un modem inalámbrico wifi 3G para mantener la comunicación con los equipos.
Por Qué STUDER
STUDER es una marca reconocida en sistemas de soluciones para instalaciones remotas de telecomunicaciones por la robustez de sus equipos. Una de las razones más importantes es que los equipos ofrecen un nivel de incidencias mínimo. Pero lo más importante es por su función B.L.O., única y exclusiva de los inversores AJ de STUDER. Esta función aumenta de manera dinámica el umbral de desconexión del equipo (LVD) por bajo voltaje, hasta que la batería consiga una carga al 100%.
Esta estrategia, permite recuperar cargas completas de la capacidad de la batería, disminuye la media de profundidad de descarga, evita que se trabaje en descargas profundas de forma continuada y evita que la batería falle de forma prematura. Por todo esto se aumenta el tiempo de vida útil. De esta forma, la batería entrega más energía a lo largo de su vida útil y abarata los costes de ésta al final de su vida.
Resultado del Proyecto
La solución ofrecida, basada en la acumulación directa a baterías para poder brindar al cliente el resultado requerido, es la mejor de las opciones y esto basándolo en equipos confiables en acumulación, control y generación dan como resultado un sistema altamente confiable para el personal que labora en el lugar como a los residentes del mismo.
System components
1 x Inversor AJ-275-12-01 STUDER
1 x controlador SS-10-12v MORNINGSTAR
1 x Paneles Solares de 275W AMERISOLAR
1 x Batería 31-AGM 100AH @ 20 HR TROJAN
1 x Caseta prefabricada para albergar equipos
Responsible company
Battery Master
El Proyecto
La necesidad de mantener un área debidamente monitoreada por cuestiones de seguridad perimetral fue lo que motivó a un fraccionamiento localizado en Monterrey N.L. ubicado en la parte alta de uno de los cerros de la ciudad a utilizar los sistemas descritos en este caso de estudio.
Este fraccionamiento por cuestión de su ubicación requería tener una visión total monitoreada de su espacio. Por su ubicación no es rentable tener personal haciendo recorridos, debido a que, por cuestión de distancias y topografía, es difícil y costoso. Por ello se utilizaron 14 sistemas remotos para poder tener monitoreado todo el perímetro del fraccionamiento.
La solucíon
Para cumplir con el objetivo de mantener el espacio monitoreado permanentemente se instalaron equipos de generación de energía fotovoltaica. Gracias a los controladores solares MORNINGSTAR se almacena energía en las baterías TROJAN, pues es la fuente más fiable para brindar la seguridad de almacenamiento y tener disponibilidad de energía. Por medio de los inversores AJ de STUDER se alimentan consumos en corriente alterna desde las baterías como una cámara de video vigilancia y un modem inalámbrico wifi 3G para mantener la comunicación con los equipos.
Por Qué STUDER
STUDER es una marca reconocida en sistemas de soluciones para instalaciones remotas de telecomunicaciones por la robustez de sus equipos. Una de las razones más importantes es que los equipos ofrecen un nivel de incidencias mínimo. Pero lo más importante es por su función B.L.O., única y exclusiva de los inversores AJ de STUDER. Esta función aumenta de manera dinámica el umbral de desconexión del equipo (LVD) por bajo voltaje, hasta que la batería consiga una carga al 100%.
Esta estrategia, permite recuperar cargas completas de la capacidad de la batería, disminuye la media de profundidad de descarga, evita que se trabaje en descargas profundas de forma continuada y evita que la batería falle de forma prematura. Por todo esto se aumenta el tiempo de vida útil. De esta forma, la batería entrega más energía a lo largo de su vida útil y abarata los costes de ésta al final de su vida.
Resultado del Proyecto
La solución ofrecida, basada en la acumulación directa a baterías para poder brindar al cliente el resultado requerido, es la mejor de las opciones y esto basándolo en equipos confiables en acumulación, control y generación dan como resultado un sistema altamente confiable para el personal que labora en el lugar como a los residentes del mismo.
Morocco: Grid Independent Gas Station
The challenge
A very unstable electricity grid causes blackouts from time to time. Issued to that the pumps of the gas station stop working and the main business is interrupted. The challenge was to have a real backup system that keeps the gas station in operation in any given case. Together with our partner JONSOL, exclusive partner of the brand SUN SILO in Morocco, we were able to master the task.
Why STUDER
As the system is installed in a hot and dusty environment, reliability of the equipment was critically important. Studer´s robustness and performance in harsh climates appealed to the user and by registering the system installation, he can also access the Studer 10-year warranty.
The solution
Combining the Jonsol PV-Rooftop-System (2x20kWp AC /19.2kWp DC/64xJSM-60 300Wp) with SUNSILO. A smart storage system that has a super-short reaction time of less than 15 milli-seconds in case of irregularities or power shortages from the grid.
Project outcome
Together we offer efficient solutions wherever the connection to a power grid is associated with high costs or diesel power generators are expensive transitional solutions. With SUNSILO and Jonsol photovoltaic moduls, you benefit from the solar power plant regardless of infrastructural restrictions and bring the power exactly where it is needed.
Above all, one of the decisive factors for our product portfolio is: highest standards. The German quality concept is therefore selection criterion and at the same time guarantee for the longevity of our products.
System components
64 x PV-Modules: Jonsol JSM60-300Wp
1 x Storage System: 25kWh SUN SILO
3 x Inverter: Studer XTH 8000-48
3 x Charge Controller: Studer VS-120
1 x Remote Control: Studer RCC-03
1 x Communication Set: Studer Xcom-LAN
Responsible company
Jonsol GmbH / ProRe GmbH & Co KG
The challenge
A very unstable electricity grid causes blackouts from time to time. Issued to that the pumps of the gas station stop working and the main business is interrupted. The challenge was to have a real backup system that keeps the gas station in operation in any given case. Together with our partner JONSOL, exclusive partner of the brand SUN SILO in Morocco, we were able to master the task.
Why STUDER
As the system is installed in a hot and dusty environment, reliability of the equipment was critically important. Studer´s robustness and performance in harsh climates appealed to the user and by registering the system installation, he can also access the Studer 10-year warranty.
The solution
Combining the Jonsol PV-Rooftop-System (2x20kWp AC /19.2kWp DC/64xJSM-60 300Wp) with SUNSILO. A smart storage system that has a super-short reaction time of less than 15 milli-seconds in case of irregularities or power shortages from the grid.
Project outcome
Together we offer efficient solutions wherever the connection to a power grid is associated with high costs or diesel power generators are expensive transitional solutions. With SUNSILO and Jonsol photovoltaic moduls, you benefit from the solar power plant regardless of infrastructural restrictions and bring the power exactly where it is needed.
Above all, one of the decisive factors for our product portfolio is: highest standards. The German quality concept is therefore selection criterion and at the same time guarantee for the longevity of our products.
Morocco: Water pumping system
The challenge
In 2016, students from CIFP Don Bosco in Spain were participating in the “Panda-Raid” car ralley, from Madrid, Spain to Essaouira, Morocco. Along the road they came in contact with a nursery school in the Errachidia valley and they observed the difficulties that the people had extracting water from the subsoil through the wells. A relationship was established and back in Madrid, the students were challenged to design a water pump system powered by solar energy to help extract the water easier.
The Solution
A photovoltaic installation was set up in order to supply an extraction pump with enough energy to pump water from the well and in addition providing electricity for other potential loads such as lamps and computers. The two Don Bosco students took advantage of their participation in the Panda-Raid 2017, to set up the photovoltaic installation. The STUDER AJ2100-12 inverter and 30A PRS regulator was generously donated by the ELEKTRA group along with advice for the set-up.
Why STUDER
STUDER products were chosen as they operate even at extremely warm temperatures without losing efficiency.
STUDER is a recognised brand whose products are durable, resilient and able to withstand important peak starting loads, necessary for the smooth running of the KSB water pump in this installation.
Project outcome
The PV system developed by the CIFP Don Bosco students has provided the nursery school with running water and a source of electricity, creating a most comfortable school environment for both its students and teachers.
The Don Bosco students and teacher who oversaw the installation and start-up on site in Errichidia thought it “magical to see the happy faces of the people approaching the fountain to collect water. The school is still under construction and they hope to have it finished by September. It will be a school built with the hearts and hands of many volunteers”.
System components
8 x 50W solar panels
2 x 6V batteries
1 x STUDER AJ inverter AJ2100-12
1 x PRS 30 Ah solar controller
1 x KSB ITUR water-extraction pump
Responsible company
ELEKTRA Group
The challenge
In 2016, students from CIFP Don Bosco in Spain were participating in the “Panda-Raid” car ralley, from Madrid, Spain to Essaouira, Morocco. Along the road they came in contact with a nursery school in the Errachidia valley and they observed the difficulties that the people had extracting water from the subsoil through the wells. A relationship was established and back in Madrid, the students were challenged to design a water pump system powered by solar energy to help extract the water easier.
The Solution
A photovoltaic installation was set up in order to supply an extraction pump with enough energy to pump water from the well and in addition providing electricity for other potential loads such as lamps and computers. The two Don Bosco students took advantage of their participation in the Panda-Raid 2017, to set up the photovoltaic installation. The STUDER AJ2100-12 inverter and 30A PRS regulator was generously donated by the ELEKTRA group along with advice for the set-up.
Why STUDER
STUDER products were chosen as they operate even at extremely warm temperatures without losing efficiency.
STUDER is a recognised brand whose products are durable, resilient and able to withstand important peak starting loads, necessary for the smooth running of the KSB water pump in this installation.
Project outcome
The PV system developed by the CIFP Don Bosco students has provided the nursery school with running water and a source of electricity, creating a most comfortable school environment for both its students and teachers.
The Don Bosco students and teacher who oversaw the installation and start-up on site in Errichidia thought it “magical to see the happy faces of the people approaching the fountain to collect water. The school is still under construction and they hope to have it finished by September. It will be a school built with the hearts and hands of many volunteers”.
Myanmar: Hybrid Solar System
The Challenge
Hybrid solar solution designed for electric water heating system at Dhamma Winiya Monastery. By day-time, it will use power from solar energy whilst batteries will be charged from solar energy.
By night-time, it will get power from batteries. If the batteries power is running low, grid power will support the load. The solar priority has been implemented and allow use all of the available renewable energy.
The Solution
Commissioned in 2020, this hybrid system of 7.2kW supplies electric water heating system of the monastery.
Although there is the national grid, the client wants to promote renewable energy andwants to reduce the utility cost.
Why STUDER
The load is for electric water heating system which may be used day and night. There is existing grid which is not very stable and the client wants to have independent power supply for electric water system because it can be used during grid power cuts. Therefore, we make separate power line for those water heaters from main distribution and feed the hybrid solar power into it. We choose Studer solution as it can be used as hybrid solution (Solar, Battery and Grid).
Project Outcome
The client who makes donation of solar system to monastery is happy about the results which solar power system for stable power supply.
System components
18 x Jinko Solar 400W Solar panels
1 x Battery Narada 7.2 kWh Systems
1 x Inverter: Studer XTH 6000-48
2 x Charge Controller: Studer VT-65
1 x Remote Control: Studer RCC-01
1 x Studer BTS-01
1 x Studer Xcom-232i
Responsible company
Planet Nine Engineering and Power Solutions Co., Ltd.
The Challenge
Hybrid solar solution designed for electric water heating system at Dhamma Winiya Monastery. By day-time, it will use power from solar energy whilst batteries will be charged from solar energy.
By night-time, it will get power from batteries. If the batteries power is running low, grid power will support the load. The solar priority has been implemented and allow use all of the available renewable energy.
The Solution
Commissioned in 2020, this hybrid system of 7.2kW supplies electric water heating system of the monastery.
Although there is the national grid, the client wants to promote renewable energy andwants to reduce the utility cost.
Why STUDER
The load is for electric water heating system which may be used day and night. There is existing grid which is not very stable and the client wants to have independent power supply for electric water system because it can be used during grid power cuts. Therefore, we make separate power line for those water heaters from main distribution and feed the hybrid solar power into it. We choose Studer solution as it can be used as hybrid solution (Solar, Battery and Grid).
Project Outcome
The client who makes donation of solar system to monastery is happy about the results which solar power system for stable power supply.
Myanmar: Minigrid for agriculture
The Challenge
The Nyaung Kyo village in Bago Region in Myanmar is far from the national grid, that will not be extended in the next 10 years.
An off-grid solar system was the answer for powering the village's rice hullers (agricultural machines that remove the outer coat of the rice) as well as the irrigation pumps and the households
The Solution
Commissioned in 2020, this off-grid system of 59.4kW supplies Nyaung Kyo village 157 HH and public facilities with 24 hr supply electricity, including the irrigation pumps and agricultural machines.
Each energy unit has a fixed price and the consumers pay in advance their estimated energy consumption on a monthly basis.
Other village houses may also join the local network once they pay the minimum connection fee.
Why STUDER
For this project, high quality uninterrupted power with high surge handling capacity and best efficiency was vital, both technically and commercially. In this case the XTH 8000-48 in the Xtender series meets the highest requirements especially with a surge capacity of 21kVA, three times its nominal power.
Project Outcome
The village enjoys access to energy through a Mini Grid system that provides them with power whenever they need it.
The smooth operating system is free from pollution and provides the village independent energy.
Significantly reduce of firewood consumption and environmental pollution
System components
Yingli Solar 59.4kW Solar Panels
Battery: BSB OPzV ,288 kWh
Studer Innotec, 6 Xtender, XTH 8000-48
Studer Innotec,12 VarioTrack VT-80
Studer Innotec, 1 remote control RCC-02, 1 BSP and 1 xcom-GSM
Responsible company
Mega Global Green Automa!on
The Challenge
The Nyaung Kyo village in Bago Region in Myanmar is far from the national grid, that will not be extended in the next 10 years.
An off-grid solar system was the answer for powering the village's rice hullers (agricultural machines that remove the outer coat of the rice) as well as the irrigation pumps and the households
The Solution
Commissioned in 2020, this off-grid system of 59.4kW supplies Nyaung Kyo village 157 HH and public facilities with 24 hr supply electricity, including the irrigation pumps and agricultural machines.
Each energy unit has a fixed price and the consumers pay in advance their estimated energy consumption on a monthly basis.
Other village houses may also join the local network once they pay the minimum connection fee.
Why STUDER
For this project, high quality uninterrupted power with high surge handling capacity and best efficiency was vital, both technically and commercially. In this case the XTH 8000-48 in the Xtender series meets the highest requirements especially with a surge capacity of 21kVA, three times its nominal power.
Project Outcome
The village enjoys access to energy through a Mini Grid system that provides them with power whenever they need it.
The smooth operating system is free from pollution and provides the village independent energy.
Significantly reduce of firewood consumption and environmental pollution
Nepal: Modular Hydro-Electric Mini-Grid
The Challenge
Most micro-hydro-electric power plants (MHP, ~10 – ~100 kW) in remote Northwestern Himalayan Nepal are constructed to meet the future needs of communities they serve. Unfortunately these communities, having never had electricity before, have not yet developed the economic vitality needed to productively utilize this much energy in the first few years, resulting in very low utilization factors of 5-10%. More importantly, the communities are not able to provide the funds needed to maintain such over-sized equipment, so the systems usually fail within a few years. A pilot pico-hydroelectric system has been constructed in the village of Moharigaun to demonstrate the feasibility of such a system that can be modularly expanded over the years to serve an evolving community’s economic capabilities and power demand.
The Solution
Two turbines feed each VS-70 charge controller at 300 VDC. 300 VDC was chosen to minimize the weight of transmission cables to the village since there is no mechanized machinery available to handle heavy spools of cable in the village. Deep cycle batteries are not needed given the continuous power generation, so readily available truck batteries were used. The three Xtender inverters produce 3-phase power that’s distributed to junction boxes placed throughout the village, demonstrating that the eventual use of 3-phase motors is feasible. The junction boxes contain Itron single-phase prepay meters, one per household, to ensure a revenue stream needed to maintain the system. The computer is used to regulate the temperature of useful loads such as hot water tanks for showers and the slurry in biogas digesters, by programmatically monitoring their bath temperatures and applying excess power when available and needed. Any excess power after that is diverted to resistive elements to heat the community center. The net result is that 100% of the available power is utilized in a variety of ‘useful loads’ distributed throughout the village, 24 hrs a day, 365 days a year.
The eventual goal of this pilot project is to broadly replicate the approach, so we would be happy to work with you to transfer the necessary technology.
Why Studer
Studer’s reliability was essential in such a remote location, the VS-70 supports 600 VDC and specified to operate up to 3000m which is the elevation of Moharigaun. The Xtender system was easy to set up and simply works!
Project outcome
Moharigaun has had continuous electricity service ever since it was commissioned in November 2018, utilizing 100% of the available power
System components
4x N200 Exide truck batteries in series (each 12 VDC, 200Ah)
3x Studer VS-70 charge controllers
3x Studer XTM 4000-48 inverters
1x XCOM-232i
1x BSP-500
1x RCC-02
1x Schweitzer Engineering Labs 3360 computer
1x Itron ACE9000 SSP DIN-R pre-pay electricity meters
Responsible company
RIDS-Nepal
The Challenge
Most micro-hydro-electric power plants (MHP, ~10 – ~100 kW) in remote Northwestern Himalayan Nepal are constructed to meet the future needs of communities they serve. Unfortunately these communities, having never had electricity before, have not yet developed the economic vitality needed to productively utilize this much energy in the first few years, resulting in very low utilization factors of 5-10%. More importantly, the communities are not able to provide the funds needed to maintain such over-sized equipment, so the systems usually fail within a few years. A pilot pico-hydroelectric system has been constructed in the village of Moharigaun to demonstrate the feasibility of such a system that can be modularly expanded over the years to serve an evolving community’s economic capabilities and power demand.
The Solution
Two turbines feed each VS-70 charge controller at 300 VDC. 300 VDC was chosen to minimize the weight of transmission cables to the village since there is no mechanized machinery available to handle heavy spools of cable in the village. Deep cycle batteries are not needed given the continuous power generation, so readily available truck batteries were used. The three Xtender inverters produce 3-phase power that’s distributed to junction boxes placed throughout the village, demonstrating that the eventual use of 3-phase motors is feasible. The junction boxes contain Itron single-phase prepay meters, one per household, to ensure a revenue stream needed to maintain the system. The computer is used to regulate the temperature of useful loads such as hot water tanks for showers and the slurry in biogas digesters, by programmatically monitoring their bath temperatures and applying excess power when available and needed. Any excess power after that is diverted to resistive elements to heat the community center. The net result is that 100% of the available power is utilized in a variety of ‘useful loads’ distributed throughout the village, 24 hrs a day, 365 days a year.
The eventual goal of this pilot project is to broadly replicate the approach, so we would be happy to work with you to transfer the necessary technology.
Why Studer
Studer’s reliability was essential in such a remote location, the VS-70 supports 600 VDC and specified to operate up to 3000m which is the elevation of Moharigaun. The Xtender system was easy to set up and simply works!
Project outcome
Moharigaun has had continuous electricity service ever since it was commissioned in November 2018, utilizing 100% of the available power
Nicaragua: Casa Residencial con Prioridad Solar
El Proyecto
La producción de energía a partir del sol supone un ahorro económico importante, ya que es una fuente inagotable de energía que no está sujeta a las fluctuaciones del mercado. Aunque requiere un desembolso inicial importante, este se ve compensado por una rápida amortización de la inversión.
Cuidado ambiental: Los sistemas de generación de energía solar son amigables con el medio ambiente, ya que ayudan a evitar la emisión de gases contaminantes como el CO2.
Al contar con su propio sistema de energía, el hogar no se verá afectado por altos costos de energía ni por cortes, mantenimientos o fallas en el suministro energético tradicional. Así se puede garantizar el funcionamiento de forma continuado de los equipos domésticos.
La Solucíon
Para cumplir con el objetivo de disminuir sel consumo de energía eléctrica convencional, se han instalado paneles solares con baterías selladas de ciclo profundo, con lo cual se ha reducido las horas de consumo de parte de la red comercial. Esto ha sido posible gracias a acumular la energía producida por los por paneles fotovoltaicos y solo en caso de no haber energía disponible en las baterías se recurre a la energía de la red comercial.
Por Qué STUDER
Porque la solución que ofrece la función prioridad solar, única en STUDER, hace posible una programación que gestiona de forma perfecta la energía minimizando el consumo de energía de la red eléctrica, priorizando el consumo desde la energía creada por los paneles fotovoltaicos. Además en caso de cortes del suministro eléctrico se garantiza mediante las baterías los equipos puede ser alimentados de forma continuada funcionando el sistema como un UPS.
Resultado del Proyecto
La solución ofrecida, en prioridad solar, basado en autoconsumo y la acumulación directa a baterías, evita el uso de la red comercial, ahorrando un 90% del consumo de energía dentro de la vivienda consiguiendo unas ratios de amortización que están alrededor de 4 años, frente a equipos que tienen una durabilidad de hasta 25 años.
System components
2 x Inversor STUDER XTH 6000-48-01 6000VA/120VAC/48VDC
1 x Control de Programación STUDER RCC-02
13 x Módulos solares 330W-36.4V SG330P
1 x Estructura para módulos
1 x Estructura para baterías
1 x Regulador VarioString STUDER 70A MPPT VS-70
16 x Baterías 12V-200AH
Responsible company
Tecnosol
El Proyecto
La producción de energía a partir del sol supone un ahorro económico importante, ya que es una fuente inagotable de energía que no está sujeta a las fluctuaciones del mercado. Aunque requiere un desembolso inicial importante, este se ve compensado por una rápida amortización de la inversión.
Cuidado ambiental: Los sistemas de generación de energía solar son amigables con el medio ambiente, ya que ayudan a evitar la emisión de gases contaminantes como el CO2.
Al contar con su propio sistema de energía, el hogar no se verá afectado por altos costos de energía ni por cortes, mantenimientos o fallas en el suministro energético tradicional. Así se puede garantizar el funcionamiento de forma continuado de los equipos domésticos.
La Solucíon
Para cumplir con el objetivo de disminuir sel consumo de energía eléctrica convencional, se han instalado paneles solares con baterías selladas de ciclo profundo, con lo cual se ha reducido las horas de consumo de parte de la red comercial. Esto ha sido posible gracias a acumular la energía producida por los por paneles fotovoltaicos y solo en caso de no haber energía disponible en las baterías se recurre a la energía de la red comercial.
Por Qué STUDER
Porque la solución que ofrece la función prioridad solar, única en STUDER, hace posible una programación que gestiona de forma perfecta la energía minimizando el consumo de energía de la red eléctrica, priorizando el consumo desde la energía creada por los paneles fotovoltaicos. Además en caso de cortes del suministro eléctrico se garantiza mediante las baterías los equipos puede ser alimentados de forma continuada funcionando el sistema como un UPS.
Resultado del Proyecto
La solución ofrecida, en prioridad solar, basado en autoconsumo y la acumulación directa a baterías, evita el uso de la red comercial, ahorrando un 90% del consumo de energía dentro de la vivienda consiguiendo unas ratios de amortización que están alrededor de 4 años, frente a equipos que tienen una durabilidad de hasta 25 años.
Nicaragua: Granada Islet Bora Bora
The challenge
There are 365 islets in the lake Nicaragua, most of them without grid connection. When one of the islets of Grenada, the small Bora Bora island, passed on as a heritage from father to son, the new proprietary wanted to honour his father by completely renovating and modernising the house.
One important step was adding a renewable energy system in order to turn the facilities into a tourist location. As there is no grid for backup, it is necessary to dimension the system properly taking into consideration any peak demand.
The solution
A photovoltaic installation was set up in order to supply an extraction pump with enough energy to pump water from the well and in addition providing electricity for other potential loads such as lamps and computers.
Why Studer
The Bora Bora islet is remotely situated in a very humid climate. The customer chose STUDER as it is a globally recognised brand known for the quality and reliability of its products which reassured him for this installation.
STUDER equipment also has an extremely wide range of parameters that can be coupled with any type of system, demonstrating excellent results.
Project outcome
The solar installation has drastically reduced the use of the diesel generator, making the need for diesel transportation to the island via boat less frequent which is positively influencing the operational cost.
With the photovoltaic array being very visible, it has stirred interest among the other islets' inhabitants, becoming a reference for solar installations in the area.
System components
7 x Trina solar polycrystalline modules, 265Wp
12x Ritar 12V 100Ah battery bank
1 x STUDER VarioTrack MPPT solar charge controller VT-65
1 x STUDER Xtender inverter/charger XTM-4000-48-01
1 x RCC-02 remote control
Responsible company
Ecami SA
The challenge
There are 365 islets in the lake Nicaragua, most of them without grid connection. When one of the islets of Grenada, the small Bora Bora island, passed on as a heritage from father to son, the new proprietary wanted to honour his father by completely renovating and modernising the house.
One important step was adding a renewable energy system in order to turn the facilities into a tourist location. As there is no grid for backup, it is necessary to dimension the system properly taking into consideration any peak demand.
The solution
A photovoltaic installation was set up in order to supply an extraction pump with enough energy to pump water from the well and in addition providing electricity for other potential loads such as lamps and computers.
Why Studer
The Bora Bora islet is remotely situated in a very humid climate. The customer chose STUDER as it is a globally recognised brand known for the quality and reliability of its products which reassured him for this installation.
STUDER equipment also has an extremely wide range of parameters that can be coupled with any type of system, demonstrating excellent results.
Project outcome
The solar installation has drastically reduced the use of the diesel generator, making the need for diesel transportation to the island via boat less frequent which is positively influencing the operational cost.
With the photovoltaic array being very visible, it has stirred interest among the other islets' inhabitants, becoming a reference for solar installations in the area.
Panama: Luxury Resort by La Casa de Las Baterías
The Challenge
La Loma Jungle Lodge and Chocolate Farm is located in the heart of the Isla Bastimentos rainforest, nestled in a 55-acre estate that stretches from the shores of the Bahia Honda mangroves, through tropical forests and groves of fruit trees, to the highest point of Isla Bastimentos, in Bocas del Toro, Panama. The property borders the spectacular National Marine Park, and the idyllic white sand beaches of the Panamanian Caribbean are just a short boat ride away. Passionate about sharing this natural beauty and luxury while protecting its precious environment and the lives of its inhabitants, this one-of-a-kind hospitality complex set itself the goal of generating 100% of the electricity it requires to operate with a solar photovoltaic system, aiming for the highest quality standards and using available cutting-edge technology. In this respect, the system designed and installed by La Casa de las Baterías includes a solar photovoltaic system, lithium-ion batteries and STUDER equipment that ensure the efficient supply of all the electrical energy necessary for this majestic place to provide its guests with eco-friendly luxury accommodation.
The Solucion
A 23.2kWp solar photovoltaic (PV) system was installed to supply the entire tourist complex with electricity. The system is designed to charge the 81.6kWh lithium-ion battery bank, using Studer charge controllers which enable an input of up to 600V, the ideal voltage to optimize the energy generated and reduce the wiring gauge required in the strings. Three Xtender 6kVA inverters/chargers were used, in a 208/120Vac three-phase configuration. The system includes a backup generator set which kicks in to maintain the continuity of the electricity supply should the PV energy generation fail. The system works automatically, controlling lithium battery discharge values and optimizing the loads that can happen randomly, at times when solar generation allows it. All system monitoring is done remotely.
Why STUDER
STUDER offers the reliability that customers demand for remote installations of off-grid systems, which, together with its flexibility, durability and 10-year warranty, are the main reasons for choosing STUDER equipment. The fact that it bears the "Swiss Made" label is a guarantee of top quality recognised all over the world.
Project outcome
Once completed, the project allowed the luxury tourist complex to generate 100% of its power supply from solar PV energy, providing its guests with a unique experience amidst the beau!ful natural se% ng, while minimizing the lodge's environmental impact in this truly magical region.
System components
4 x STUDER VarioString VS-120 solar charge controllers
3 x STUDER Xtender XTH 6000-48-01 Inverter/Chargers
1 x STUDER Remote Control Centre RCC-02
1 x STUDER Xcom-CAN
1 x STUDER Xcom-LAN
58 x 400Wp monocrystalline Jinko Solar Panels
8 x BYD 48Vdc, 10.2kWh lithium-ion battery banks
Responsible company
La Casa de las Baterías Energía
The Challenge
La Loma Jungle Lodge and Chocolate Farm is located in the heart of the Isla Bastimentos rainforest, nestled in a 55-acre estate that stretches from the shores of the Bahia Honda mangroves, through tropical forests and groves of fruit trees, to the highest point of Isla Bastimentos, in Bocas del Toro, Panama. The property borders the spectacular National Marine Park, and the idyllic white sand beaches of the Panamanian Caribbean are just a short boat ride away. Passionate about sharing this natural beauty and luxury while protecting its precious environment and the lives of its inhabitants, this one-of-a-kind hospitality complex set itself the goal of generating 100% of the electricity it requires to operate with a solar photovoltaic system, aiming for the highest quality standards and using available cutting-edge technology. In this respect, the system designed and installed by La Casa de las Baterías includes a solar photovoltaic system, lithium-ion batteries and STUDER equipment that ensure the efficient supply of all the electrical energy necessary for this majestic place to provide its guests with eco-friendly luxury accommodation.
The Solucion
A 23.2kWp solar photovoltaic (PV) system was installed to supply the entire tourist complex with electricity. The system is designed to charge the 81.6kWh lithium-ion battery bank, using Studer charge controllers which enable an input of up to 600V, the ideal voltage to optimize the energy generated and reduce the wiring gauge required in the strings. Three Xtender 6kVA inverters/chargers were used, in a 208/120Vac three-phase configuration. The system includes a backup generator set which kicks in to maintain the continuity of the electricity supply should the PV energy generation fail. The system works automatically, controlling lithium battery discharge values and optimizing the loads that can happen randomly, at times when solar generation allows it. All system monitoring is done remotely.
Why STUDER
STUDER offers the reliability that customers demand for remote installations of off-grid systems, which, together with its flexibility, durability and 10-year warranty, are the main reasons for choosing STUDER equipment. The fact that it bears the "Swiss Made" label is a guarantee of top quality recognised all over the world.
Project outcome
Once completed, the project allowed the luxury tourist complex to generate 100% of its power supply from solar PV energy, providing its guests with a unique experience amidst the beau!ful natural se% ng, while minimizing the lodge's environmental impact in this truly magical region.
Peru: Empowering Mushuk Lamas
The challenge
High in the jungle and inaccessible by motor vehicle, the native community of Mushuk Lamas has yet to be connected to the grid by the Peruvian government. Living half their lives in the dark means it is difficult to study and learn after sunset, makes cooking and cleaning more challenging, and limits economic development for this hard-working community.
The solution
With community investment and sweat equity along with volunteer designers and installers, Twende Solar organized donations of supplies, funds and volunteers to install a 7.2kw off-grid, ground-mount PV system + battery backup that will produce an estimated 9,800 KWH per year. Powering an Internet tower and bringing electricity to the community center will increase the productive hours of the day and access to information and learning with power to spare once they are ready to transmit to their homes.
Why Studer
Needing rugged and reliable system components to keep the Mushuk Lamas community empowered for years to come in their tropical, jungle environment, STUDER was the perfect choice for power electronics. With a 10 year warranty and widespread use in Peru, Twende felt confident that the donated system would be in good hands in the rare event special maintenance were needed.
Project outcome
Living responsibly off the richness of the land in the protected Cordillera Escalera, the self-sufficient Mushuk Lamas community is able to grow or make most of the things they need to live. With this solar system and battery backup, they now also produce their own electricity and will have access to the basic functions of lighting, refrigeration, and the internet. Generating solar power means the community will be able to improve coffee production and achieve a higher price for their beans through membership in a cooperative.
System components
24 x Jinko JKM305P-72 solar modules
5 x SimpliPhi Phi3.5 batteries
2 x STUDER XTM 4000-48 inverter/chargers
2 x STUDER VT-65 MPPT solar charge controllers
Unirac ULA racking
1 x STUDER Remote Control RCC-03
1 x STUDER Communication Set Xcom-GSM
Responsible company
Twende Solar
The challenge
High in the jungle and inaccessible by motor vehicle, the native community of Mushuk Lamas has yet to be connected to the grid by the Peruvian government. Living half their lives in the dark means it is difficult to study and learn after sunset, makes cooking and cleaning more challenging, and limits economic development for this hard-working community.
The solution
With community investment and sweat equity along with volunteer designers and installers, Twende Solar organized donations of supplies, funds and volunteers to install a 7.2kw off-grid, ground-mount PV system + battery backup that will produce an estimated 9,800 KWH per year. Powering an Internet tower and bringing electricity to the community center will increase the productive hours of the day and access to information and learning with power to spare once they are ready to transmit to their homes.
Why Studer
Needing rugged and reliable system components to keep the Mushuk Lamas community empowered for years to come in their tropical, jungle environment, STUDER was the perfect choice for power electronics. With a 10 year warranty and widespread use in Peru, Twende felt confident that the donated system would be in good hands in the rare event special maintenance were needed.
Project outcome
Living responsibly off the richness of the land in the protected Cordillera Escalera, the self-sufficient Mushuk Lamas community is able to grow or make most of the things they need to live. With this solar system and battery backup, they now also produce their own electricity and will have access to the basic functions of lighting, refrigeration, and the internet. Generating solar power means the community will be able to improve coffee production and achieve a higher price for their beans through membership in a cooperative.
Peru: Petrolera
El Proyecto
La Solución
Para cumplir con el objetivo de disminuir su consumo de diésel, se han instalado baterías de plomo-ácido de ciclo profundo tecnología OPzV, con lo cual se ha reducido las horas de funcionamiento de los generadores diésel. Esto ha sido posible gracias a acumular la energía producida por los aerogeneradores ENAIR, y por paneles fotovoltaicos YINGLI regulados por el VT-65 de STUDER . Solo en caso de no haber producción eólica o fotovoltaica se recurre al consumo de energía producida con diésel.
Por Qué STUDER
Cuando se necesita elegir equipos pensando en alta confiabilidad y condiciones de alta temperatura, las opciones se ven muy reducidas. STUDER es una marca que es reconocida por trabajar en temperaturas extremas y que permite garantizar el correcto funcionamiento bajo las condiciones descritas por el cliente. Destacar los 10 años de garantía que ofrece STUDER.
Resultado del Proyecto
El sistema se encuentra trabajando actualmente y suministrando la energía necesaria para el accionamiento de las bombas. Los voltajes de batería registrados y analizados por el datalogger RCC-03 permite estimar una vida aproximada de baterías superior a los 5 años, cumpliendo de esta manera con la condición de durabilidad requerida por el cliente final.
System components
4 x Panel Solar Yingli de 150 Wp. policristalino
1 x Estructura de soporte para 4 paneles
1 x Gabinete metálico OUTDOOR de 60x60x120 cm, conteniendo:
1 x Controlador MPPT STUDER, VT-65
1 x Consola de programación STUDER RCC-03
1 x Sensor de temperatura de baterías STUDER BTS-01
1 x Relé Auxiliar ARM-02, para control de cargas
2 x Baterías RITAR, modelo OPzV 12-200, 12V 236 Ah (C100)
Responsible company
Q-Energy Perú
El Proyecto
La Solución
Para cumplir con el objetivo de disminuir su consumo de diésel, se han instalado baterías de plomo-ácido de ciclo profundo tecnología OPzV, con lo cual se ha reducido las horas de funcionamiento de los generadores diésel. Esto ha sido posible gracias a acumular la energía producida por los aerogeneradores ENAIR, y por paneles fotovoltaicos YINGLI regulados por el VT-65 de STUDER . Solo en caso de no haber producción eólica o fotovoltaica se recurre al consumo de energía producida con diésel.
Por Qué STUDER
Cuando se necesita elegir equipos pensando en alta confiabilidad y condiciones de alta temperatura, las opciones se ven muy reducidas. STUDER es una marca que es reconocida por trabajar en temperaturas extremas y que permite garantizar el correcto funcionamiento bajo las condiciones descritas por el cliente. Destacar los 10 años de garantía que ofrece STUDER.
Resultado del Proyecto
El sistema se encuentra trabajando actualmente y suministrando la energía necesaria para el accionamiento de las bombas. Los voltajes de batería registrados y analizados por el datalogger RCC-03 permite estimar una vida aproximada de baterías superior a los 5 años, cumpliendo de esta manera con la condición de durabilidad requerida por el cliente final.
Peru: Project TAMBOS – Peruvian government
The challenge
In Peru there are many remotely situated villages. To get in closer contact with the population there, the Peruvian government decided to set up 27 local “Tambos”. A Tambos is a decentralised government unit equipped with lighting and electricity to provide basic services for the inhabitants in surrounding villages.
The Tambos are located in eight regions across Peru, mainly in La Sierra and the Amazon. The programme was financed by the Peruvian Ministry of Housing, Construction and Sanitation.
The solution
The 27 Tambos are presently covering 100% of their energy demand with the photovoltaic systems. For emergencies they use a generator for backup. Each Tambo daily provides services to the inhabitants in these remote villages, reducing the need travel to the main cities to do paperwork and get in contact with the government.
Each system is mounted in an electrical cabinet with its related accessories and electrical protections in accordance with Peruvian regulations. The status of the equipment in the Tambo's photovoltaic system is remotely controlled over the Internet thanks to STUDER's data transmission accessories.
Why STUDER
The regions where these Tambos are installed are either located at high altitudes in the mountains or in conditions of extreme temperature and humidity in the Amazon. STUDER products were chosen for their performance in severe conditions. By guaranteeing the functioning of its equipment under the project's working conditions and extending the product warranty, STUDER provided security to meet the life expectancy set for the project.
Project outcome
In the time of the Incas, a "Tambo" (Tanpu in the Quechuan language) was an area located next to an important road which was used as a shelter and as a centre for storing food and provisions. Thanks to this project, modern "Tambos" also have lighting and electricity to provide basic services to the inhabitants of the surrounding villages.
System components
16 x GREALTEC solar polycrystalline modules GAT150P,
12 Vdc 150 Wp
12 x RITAR OPzV12-180,12 Vdc in a battery bank with 600 Ah and 48 Vdc
1 x STUDER Xtender inverter / charger XTM 4000-48
1 x STUDER VarioTrack MPPT charge controller, VS-70
1 x STUDER RCC-03 remote control
1 x STUDER BTS-01 battery sensor
1 x STUDER Xcom-LAN communication set
1 x STUDER BSP 500 battery status processor
Responsible company
Q-Energy Peru
The challenge
In Peru there are many remotely situated villages. To get in closer contact with the population there, the Peruvian government decided to set up 27 local “Tambos”. A Tambos is a decentralised government unit equipped with lighting and electricity to provide basic services for the inhabitants in surrounding villages.
The Tambos are located in eight regions across Peru, mainly in La Sierra and the Amazon. The programme was financed by the Peruvian Ministry of Housing, Construction and Sanitation.
The solution
The 27 Tambos are presently covering 100% of their energy demand with the photovoltaic systems. For emergencies they use a generator for backup. Each Tambo daily provides services to the inhabitants in these remote villages, reducing the need travel to the main cities to do paperwork and get in contact with the government.
Each system is mounted in an electrical cabinet with its related accessories and electrical protections in accordance with Peruvian regulations. The status of the equipment in the Tambo's photovoltaic system is remotely controlled over the Internet thanks to STUDER's data transmission accessories.
Why STUDER
The regions where these Tambos are installed are either located at high altitudes in the mountains or in conditions of extreme temperature and humidity in the Amazon. STUDER products were chosen for their performance in severe conditions. By guaranteeing the functioning of its equipment under the project's working conditions and extending the product warranty, STUDER provided security to meet the life expectancy set for the project.
Project outcome
In the time of the Incas, a "Tambo" (Tanpu in the Quechuan language) was an area located next to an important road which was used as a shelter and as a centre for storing food and provisions. Thanks to this project, modern "Tambos" also have lighting and electricity to provide basic services to the inhabitants of the surrounding villages.
Perú: Repotenciación de una Instalación Aislada para la Aldea Infantil Westfalia
El Proyecto
La aldea infantil Westfalia Kinderdorf, es una institución benéfica sin fines de lucro que, desde hace más de 26 años, tiene como objetivo ayudar a niños, adolescentes y jóvenes huérfanos, víctimas de violencia familiar, en abandono, con habilidades especiales o en situación de extrema pobreza.
La aldea, se encuentra ubicada en el distrito de Cieneguilla, que en la actualidad atiende a 133 personas, entre niños, adolescentes y jóvenes, brindándoles un hogar con una familia, educación, alimentación, asistencia médica y psicológica, así como formación orientada a futuros profesionales y técnicos calificados.
La aldea, es un usuario de energía solar desde sus inicios, y cuenta con una instalación de energía de mas de 20 años, pero en los últimos meses estuvieron teniendo cortes de energía, lo cual los llevo a utilizar velas por la noche, significando esto un riesgo grande para los niños. Por esa razón, solicitaron a Q-Energy, hacer la evaluación del funcionamiento del sistema y proponerles la reposición de los equipos de control y potencia, así como del banco de baterías.
La Solución
Lo que necesitaba la aldea era tener un sistema de control y potencia, confiable y que permitiera hacer el monitoreo remoto, para verificar su correcto funcionamiento en producción solar y consumos.
El cliente conocía la marca STUDER y los proyectos realizados por Q-Energy, por lo cual, decidieron ejecutar la instalación con equipos electrónicos STUDER (Made in Switzerland) y baterías OPzV Sonnenschein (made in Germany).
Con los accesorios de control remoto además, se puede tener un control total de la instalación en tiempo real, y con las graficas se puede analizar y optimizar la producción solar, y equilibrar consumos.
Por Qué STUDER
STUDER brinda desde hace muchos años la confiabilidad y el respaldo que los clientes necesitan. La nueva plataforma de comunicación permite a los usuarios verificar los parámetros de funcionamiento de manera sencilla desde cualquier lugar. El factor Swiss Made y los 10 años de Garantía resuiltaron un factor determinante.
Resultado del Proyecto
Se corrigió la instalación eléctrica que tenía una corriente de fuga y se dejaron de tener cortes de energía. Actualmente Q-Energy a través del monitoreo, verifica los consumos y el comportamiento del banco de baterías.
La demanda esta siendo atendida en su totalidad por la energía solar. Se ha podido identificar que pueden conectar más consumos que no tenían conectados, pensando que no se podían atender (esto gracias al monitoreo). Además, junto a Q-Energy, se está trabajando en un programa de formación para los jóvenes interesados en conocer mas de energía fotovoltaica.
System components
2 x Controladores MPPT VT-80 STUDER
2 x Inversores Cargadores XTH-6000-48
1 x Sistema de Control Studer RCC-02
1 x Monitoreo vía internet XCom-LAN
30 x Paneles solares policristalinos de 170Wp
24 x Elementos Sonnenschein OPzV SOLAR A600 A602/1960 C SOLAR
1 x Rack Metálico antisísmico
Responsible company
Q-ENERGY PERÚ S.A.C.
El Proyecto
La aldea infantil Westfalia Kinderdorf, es una institución benéfica sin fines de lucro que, desde hace más de 26 años, tiene como objetivo ayudar a niños, adolescentes y jóvenes huérfanos, víctimas de violencia familiar, en abandono, con habilidades especiales o en situación de extrema pobreza.
La aldea, se encuentra ubicada en el distrito de Cieneguilla, que en la actualidad atiende a 133 personas, entre niños, adolescentes y jóvenes, brindándoles un hogar con una familia, educación, alimentación, asistencia médica y psicológica, así como formación orientada a futuros profesionales y técnicos calificados.
La aldea, es un usuario de energía solar desde sus inicios, y cuenta con una instalación de energía de mas de 20 años, pero en los últimos meses estuvieron teniendo cortes de energía, lo cual los llevo a utilizar velas por la noche, significando esto un riesgo grande para los niños. Por esa razón, solicitaron a Q-Energy, hacer la evaluación del funcionamiento del sistema y proponerles la reposición de los equipos de control y potencia, así como del banco de baterías.
La Solución
Lo que necesitaba la aldea era tener un sistema de control y potencia, confiable y que permitiera hacer el monitoreo remoto, para verificar su correcto funcionamiento en producción solar y consumos.
El cliente conocía la marca STUDER y los proyectos realizados por Q-Energy, por lo cual, decidieron ejecutar la instalación con equipos electrónicos STUDER (Made in Switzerland) y baterías OPzV Sonnenschein (made in Germany).
Con los accesorios de control remoto además, se puede tener un control total de la instalación en tiempo real, y con las graficas se puede analizar y optimizar la producción solar, y equilibrar consumos.
Por Qué STUDER
STUDER brinda desde hace muchos años la confiabilidad y el respaldo que los clientes necesitan. La nueva plataforma de comunicación permite a los usuarios verificar los parámetros de funcionamiento de manera sencilla desde cualquier lugar. El factor Swiss Made y los 10 años de Garantía resuiltaron un factor determinante.
Resultado del Proyecto
Se corrigió la instalación eléctrica que tenía una corriente de fuga y se dejaron de tener cortes de energía. Actualmente Q-Energy a través del monitoreo, verifica los consumos y el comportamiento del banco de baterías.
La demanda esta siendo atendida en su totalidad por la energía solar. Se ha podido identificar que pueden conectar más consumos que no tenían conectados, pensando que no se podían atender (esto gracias al monitoreo). Además, junto a Q-Energy, se está trabajando en un programa de formación para los jóvenes interesados en conocer mas de energía fotovoltaica.
Perú: Sistema Fotovoltaico Aislado para Centro de Salud
El Proyecto
La Compañía Transportadora del Gas del Perú (TGP) es la empresa encargada del diseño, construcción y operación del sistema de transporte por ductos del gas natural y los líquidos de gas natural del Proyecto Gas de Camisea, ubicado en la localidad del mismo nombre en Cusco, Perú.
Como labores de responsabilidad social, a!enden muchas de las necesidades de las comunidades ubicadas en la zona de influencia. Por esemotivo, contrataron aQ-Energy Perú para el Suministro e Instalación de un sistema fotovoltaico aislado de 680Wen 220 Vac para que pueda cubrir las necesidades energéticas del puesto de salud de la comunidad.
La comunidad de Cashiriari, se encuentra ubicada en la selva del departamento de Cusco, en Camisea, distrito de Megantoni.
La Solución
La instalación del sistema de energía autónomo permite atender una carga de 2 kWh/día que cubre las necesidades energéticas del Puesto de Salud. Con la iluminación y la energía necesaria para el funcionamiento de equipos y refrigeradoras para garantizar la cadena de frio de las vacunas, el servicio medico que recibirá la comunidad será mucho mejor.
Por Qué STUDER
Para una comunidad donde el acceso es por río o helicóptero, y donde el equipamiento va a atender una necesidad tan importante como un Puesto de Salud, se tiene que ofrecer la mejor tecnología. STUDER es una marca que se ha logrado posicionar en los proyectos donde el cliente prioriza la confiabilidad. La función B.L.O. (Battery Lifetime Optimizer) que permite mejorar la expectativa de vida de las baterías (en este caso de plomo acido de placa tubular del fabricante Ritar), es lo que más valor le dio el cliente.
Resultado del Proyecto
El Puesto de Salud está funcionando sin problemas, y con la confianza de seguir así durante muchos años más. La comunidad esta contenta por la mejora de este servicio básico. STUDER es una marca reconocida por el cliente, ya que esta presente en muchos de sus proyectos, tanto de electrificación rural , como en los sistemas de control de válvulas y comunicaciones.
System components
1 x Controladores de carga Morningstar MPPT, modelo Ecoboost-30
1 x Inversores STUDER AJ-350-24
6 x Baterías Ritar OPzV 12-200 de Placa Tubular
1 x Rack Metálico an!sísmico
4 x Paneles Solares Policristalinos de 170Wp
Responsible company
Q-ENERGY PERÚ S.A.C.
El Proyecto
La Compañía Transportadora del Gas del Perú (TGP) es la empresa encargada del diseño, construcción y operación del sistema de transporte por ductos del gas natural y los líquidos de gas natural del Proyecto Gas de Camisea, ubicado en la localidad del mismo nombre en Cusco, Perú.
Como labores de responsabilidad social, a!enden muchas de las necesidades de las comunidades ubicadas en la zona de influencia. Por esemotivo, contrataron aQ-Energy Perú para el Suministro e Instalación de un sistema fotovoltaico aislado de 680Wen 220 Vac para que pueda cubrir las necesidades energéticas del puesto de salud de la comunidad.
La comunidad de Cashiriari, se encuentra ubicada en la selva del departamento de Cusco, en Camisea, distrito de Megantoni.
La Solución
La instalación del sistema de energía autónomo permite atender una carga de 2 kWh/día que cubre las necesidades energéticas del Puesto de Salud. Con la iluminación y la energía necesaria para el funcionamiento de equipos y refrigeradoras para garantizar la cadena de frio de las vacunas, el servicio medico que recibirá la comunidad será mucho mejor.
Por Qué STUDER
Para una comunidad donde el acceso es por río o helicóptero, y donde el equipamiento va a atender una necesidad tan importante como un Puesto de Salud, se tiene que ofrecer la mejor tecnología. STUDER es una marca que se ha logrado posicionar en los proyectos donde el cliente prioriza la confiabilidad. La función B.L.O. (Battery Lifetime Optimizer) que permite mejorar la expectativa de vida de las baterías (en este caso de plomo acido de placa tubular del fabricante Ritar), es lo que más valor le dio el cliente.
Resultado del Proyecto
El Puesto de Salud está funcionando sin problemas, y con la confianza de seguir así durante muchos años más. La comunidad esta contenta por la mejora de este servicio básico. STUDER es una marca reconocida por el cliente, ya que esta presente en muchos de sus proyectos, tanto de electrificación rural , como en los sistemas de control de válvulas y comunicaciones.
Peru: Telefónica telecom project
The challenge
For the past six years, Telefónica, one of the largest telecommunications companies in the world, has actively been working on reducing the diesel consumption of its base stations around the world. They have taken several initiatives in this direction such as replacing the old telecommunications equipment with modern electronics, to use renewable energy, mainly solar power, to generate energy and to use deep cycle gel batteries to create hybrid systems.
The solution
As the base stations used diesel generators for energy supply previously, it was a natural step forward to create hybrid solar systems. In these systems renewable energy is generated in the solar panels, stored in batteries and managed by the inverter/chargers. The diesel generators are mainly used for back up.
By using Studer's highly efficient "battery priority function", which gives priority to using renewable energy, Telefónica has drastically reduced the generator running times, saving diesel and improving generator lifetime. In some cases they have even completely removed the diesel generators and relocated them to other base stations.
Why Studer
Studer inverters and MPPT solar charge controllers are working perfectly together offering a fully integrated and synchronized energy system. Furthermore, Studer products are meeting the telecom market's demanding requirements in terms of reliability.
Project outcome
The savings due to the reduced use of diesel has allowed Telefónica to recover the investment cost in less than two years. As there is currently more energy available, the base stations have the possibility to install more telecommunications equipment.
System components
Responsible company
Q-Energy Peru
The challenge
For the past six years, Telefónica, one of the largest telecommunications companies in the world, has actively been working on reducing the diesel consumption of its base stations around the world. They have taken several initiatives in this direction such as replacing the old telecommunications equipment with modern electronics, to use renewable energy, mainly solar power, to generate energy and to use deep cycle gel batteries to create hybrid systems.
The solution
As the base stations used diesel generators for energy supply previously, it was a natural step forward to create hybrid solar systems. In these systems renewable energy is generated in the solar panels, stored in batteries and managed by the inverter/chargers. The diesel generators are mainly used for back up.
By using Studer's highly efficient "battery priority function", which gives priority to using renewable energy, Telefónica has drastically reduced the generator running times, saving diesel and improving generator lifetime. In some cases they have even completely removed the diesel generators and relocated them to other base stations.
Why Studer
Studer inverters and MPPT solar charge controllers are working perfectly together offering a fully integrated and synchronized energy system. Furthermore, Studer products are meeting the telecom market's demanding requirements in terms of reliability.
Project outcome
The savings due to the reduced use of diesel has allowed Telefónica to recover the investment cost in less than two years. As there is currently more energy available, the base stations have the possibility to install more telecommunications equipment.
Philippines: Solar Plant Power Backup
The Challenge
The TERASU project is a 40MWAC (60WMpDC) solar farm project in Concepcion, Tarlac built to produce renewable energy and help meet the Renewable Portfolio Standards (RPS mandate) recently implemented in the Philippines. Owned and developed by Sindicatum Renewable Energy Company, the project is located on a 62-hectare land near Barangay Sta. Rosa in Region III, Philippines. The project needed an efficient and reliable backup system to be able to secure an uninterrupted power supply at the solar plant in an event of power failure. Moreover, the necessity for a backup system will ensure the plant’s safety and reliability, so that in case of power interruptions, the control and monitoring room will remain operational until the power resumes.
The Solution
PowerPro, a total solution provider for electrical systems, installs a backup system consisting of Studer components and energy storage: three XTM 4000-48 Studer inverter-charger units for a UPS function, in combination with three BYD Battery-Box LVL15.4 for a total 46.2kWh battery storage capacity. The power management system secures 4-hour backup power to the MCR building (main control room) of the solar farm. In case of a power cut, the control and monitoring functions remain connected to the Studer system and use the energy stored in the batteries.
Why Studer
Robust, versatile, and adapted to the most commercial applications, the Studer Xtender series is a key player in the management of energy systems. The flagship of the series, XTM inverter-chargers are high-tech devices that allow the optimal use of available energy. The Studer units in the Xtender series are a perfect component in this installation project for their outstanding overload and power shaving capabilities, ultra-fast transfer relay, and smart-boost function.
Project outcome
After installation, the 60MW TERASU solar farm in Tarlac gets access to a total 46.2kWh power backup and uninterrupted power supply system, supplying most of the control and communication devices inside the main control room including the MVSG and SCADA. With this new energy management design, the solar farm is now equipped with a reliable backup system to guarantee safe and continuous operations, and to meet its renewable energy requirements.
System components
3 BYD Premium LVL 15.4kWh Li-ion Ba& ery
3 XTM 4000-48
1 RCC-02
1 Xcom-CAN
Responsible company
PowerPro Protection Supply Inc.
The Challenge
The TERASU project is a 40MWAC (60WMpDC) solar farm project in Concepcion, Tarlac built to produce renewable energy and help meet the Renewable Portfolio Standards (RPS mandate) recently implemented in the Philippines. Owned and developed by Sindicatum Renewable Energy Company, the project is located on a 62-hectare land near Barangay Sta. Rosa in Region III, Philippines. The project needed an efficient and reliable backup system to be able to secure an uninterrupted power supply at the solar plant in an event of power failure. Moreover, the necessity for a backup system will ensure the plant’s safety and reliability, so that in case of power interruptions, the control and monitoring room will remain operational until the power resumes.
The Solution
PowerPro, a total solution provider for electrical systems, installs a backup system consisting of Studer components and energy storage: three XTM 4000-48 Studer inverter-charger units for a UPS function, in combination with three BYD Battery-Box LVL15.4 for a total 46.2kWh battery storage capacity. The power management system secures 4-hour backup power to the MCR building (main control room) of the solar farm. In case of a power cut, the control and monitoring functions remain connected to the Studer system and use the energy stored in the batteries.
Why Studer
Robust, versatile, and adapted to the most commercial applications, the Studer Xtender series is a key player in the management of energy systems. The flagship of the series, XTM inverter-chargers are high-tech devices that allow the optimal use of available energy. The Studer units in the Xtender series are a perfect component in this installation project for their outstanding overload and power shaving capabilities, ultra-fast transfer relay, and smart-boost function.
Project outcome
After installation, the 60MW TERASU solar farm in Tarlac gets access to a total 46.2kWh power backup and uninterrupted power supply system, supplying most of the control and communication devices inside the main control room including the MVSG and SCADA. With this new energy management design, the solar farm is now equipped with a reliable backup system to guarantee safe and continuous operations, and to meet its renewable energy requirements.
South Africa: Off-Grid Lodges Kruger National Park
The challenge
There are a number of lodges in national parks across Africa that are off-grid and AC power availability is such that it is either not possible or the cost of bringing this power to the lodges is prohibitive. These lodges tend to run solely on generators 24/7. This solution is not only costly in itself, there is also a lot of noise and air pollution in some of the most pristine wildlife sanctuaries on the continent.
Two such lodges have now been converted to solar power with battery back-up and the generators only to be used in times when the loads have been particularly heavy or in times when there has been insufficient solar radiation.
The solution
In order to ensure the uninterrupted supply of power to the large number of chalets on these lodges, the system supplies energy during the day from the 20 kW AC coupled inverter. If there is any additional power needed this can be supplied from the batteries via the Xtenders.
The power at night is also supplied from the batteries and if there is a shortage for any reason then the generator will automatically supply this shortfall or be used to charge the batteries when required. The use of the generator is only as back-up and the system has been designed to supply the needs of the lodge mainly from renewables.
Why Studer
Because of the location of the lodges in very remote parts of the very large Kruger National Park, reliability of the equipment was of utmost importance. The temperatures in the park can also get very high and the Studer devices robustness and performance in harsh climates appealed to the customer.
The setup of the system is also easy in terms of the charge cycle of the batteries because the VarioString units are synchronized with the Xtenders. The generator auto-start is also managed very easily by battery SOC, voltage and/or time of day. When the Studer Innotec manufactured devices are installed in conjunction with other equipment, in the case of failures, the Studer devices historically keep functioning and keeps the system running.
Project outcome
The saving in reduction of diesel fuel that was previously used to run the generator 24/7 contributes tremendously towards the financial return on the investment. The reduction in noise and air pollution has also impacted the standing and perception of the lodges by the many visitors to the park.
System components
Responsible company
Current Automation
The challenge
There are a number of lodges in national parks across Africa that are off-grid and AC power availability is such that it is either not possible or the cost of bringing this power to the lodges is prohibitive. These lodges tend to run solely on generators 24/7. This solution is not only costly in itself, there is also a lot of noise and air pollution in some of the most pristine wildlife sanctuaries on the continent.
Two such lodges have now been converted to solar power with battery back-up and the generators only to be used in times when the loads have been particularly heavy or in times when there has been insufficient solar radiation.
The solution
In order to ensure the uninterrupted supply of power to the large number of chalets on these lodges, the system supplies energy during the day from the 20 kW AC coupled inverter. If there is any additional power needed this can be supplied from the batteries via the Xtenders.
The power at night is also supplied from the batteries and if there is a shortage for any reason then the generator will automatically supply this shortfall or be used to charge the batteries when required. The use of the generator is only as back-up and the system has been designed to supply the needs of the lodge mainly from renewables.
Why Studer
Because of the location of the lodges in very remote parts of the very large Kruger National Park, reliability of the equipment was of utmost importance. The temperatures in the park can also get very high and the Studer devices robustness and performance in harsh climates appealed to the customer.
The setup of the system is also easy in terms of the charge cycle of the batteries because the VarioString units are synchronized with the Xtenders. The generator auto-start is also managed very easily by battery SOC, voltage and/or time of day. When the Studer Innotec manufactured devices are installed in conjunction with other equipment, in the case of failures, the Studer devices historically keep functioning and keeps the system running.
Project outcome
The saving in reduction of diesel fuel that was previously used to run the generator 24/7 contributes tremendously towards the financial return on the investment. The reduction in noise and air pollution has also impacted the standing and perception of the lodges by the many visitors to the park.
South Africa: Off-grid system Cradle of Humankind
The challenge
Grid connection or grid independence? Today, as new residential areas develop outside the existing national grid network it is an important question to ask. The owner of this private residence, comprising four buildings for both residential and industrial use, choose energy independence over a costly grid connection.
One of the main challenges for this off-grid system was the location of its solar array. The area with maximal solar radiation was located 60 meters from the buildings with the power-electronics.
The solution
The residence is situated in the Cradle of Humankind north-west of Johannesburg, a known anthropological site where 40% of the worlds discovered human ancestor fossils have been found.
This off-grid system has an 84 kW solar array, 72 kVA power-electronics, a large battery bank for extended autonomy and a 50kVA generator for back-up. It supplies independent power to four buildings and several pumps for water supply. The generator is used for energy backup and has been automatically programmed to start at a certain state of charge (SOC) level.
The long distance between PV panels and power-electronics could have become costly for this off-grid system. By using VarioString MPPT solar charge controllers with high input PV voltage it was possible to use small diameter cables with low voltage drop providing an effective and economical solution.
The PV panels was mounted on high frames providing a well appreciated shaded parking underneath for the offices.
Why Studer
The VarioString high-voltage MPPT solar charge controller that provides balance of system advantages not available from any other suppliers.
The Xtender inverter/charger with a surge capacity that can handle three times its nominal power which is a great benefit in systems that has to cope with the start-up of large water pumps. No other device on the market in South Africa has this kind of capacity.
Project outcome
Choosing an independent energy solution has created a big change in energy consumption. Since its installation this robust and reliable system has made it possible to minimize the use of the generator resulting in massive diesel savings. The generator has only been used in case of emergencies or to charge the battery bank.
System components
Responsible company
Rubicon
The challenge
Grid connection or grid independence? Today, as new residential areas develop outside the existing national grid network it is an important question to ask. The owner of this private residence, comprising four buildings for both residential and industrial use, choose energy independence over a costly grid connection.
One of the main challenges for this off-grid system was the location of its solar array. The area with maximal solar radiation was located 60 meters from the buildings with the power-electronics.
The solution
The residence is situated in the Cradle of Humankind north-west of Johannesburg, a known anthropological site where 40% of the worlds discovered human ancestor fossils have been found.
This off-grid system has an 84 kW solar array, 72 kVA power-electronics, a large battery bank for extended autonomy and a 50kVA generator for back-up. It supplies independent power to four buildings and several pumps for water supply. The generator is used for energy backup and has been automatically programmed to start at a certain state of charge (SOC) level.
The long distance between PV panels and power-electronics could have become costly for this off-grid system. By using VarioString MPPT solar charge controllers with high input PV voltage it was possible to use small diameter cables with low voltage drop providing an effective and economical solution.
The PV panels was mounted on high frames providing a well appreciated shaded parking underneath for the offices.
Why Studer
The VarioString high-voltage MPPT solar charge controller that provides balance of system advantages not available from any other suppliers.
The Xtender inverter/charger with a surge capacity that can handle three times its nominal power which is a great benefit in systems that has to cope with the start-up of large water pumps. No other device on the market in South Africa has this kind of capacity.
Project outcome
Choosing an independent energy solution has created a big change in energy consumption. Since its installation this robust and reliable system has made it possible to minimize the use of the generator resulting in massive diesel savings. The generator has only been used in case of emergencies or to charge the battery bank.
Spain: Apoyo a la Red Electrica Salamanca
The challenge
This Project was carried out in a small village called Alberguería de Arganan, a Spanish rural area close to the border of Portugal.
In Spanish rural areas, it's really common for houses to not have enough power supplied by the grid to power all the loads houses have nowadays. That is due to the fact that those electrical installations were built some decades ago where, in the past, the need of powering loads was really low compared to today's needs (electrical household appliances in addition to the rest of the electrical devices in the home).
The solution
Power supplied by the electrical household to these households it's 220-230V, 50 Hz and 10A (single phase). The maximum power available it's 2,3 kVA. This is dependent upon the voltage and how stable the electrical grid is at any moment.
Why Studer
STUDER offers huge options for setting all the parameters up to allow the implementation of the required special applications and their needs. Furthermore, with the XCOM-LAN module, this household can be remotely monitored and in case of any failure the owner can be notified in real time.
The SMART-BOOST feature is the key to get more power than the grid can supply at any moment making you more independent of the electrical supplier.
Considering that nowadays there are lots of electrical devices in any household and sometimes most of them are connected at the same time, that load demand is much higher than the available power coming from the grid (only 2,2 kVA). Due to the load demand, usually you will see AC breakers falling down leaving the household in a blackout situation.
By adding the STUDER XTM 3500-24 and the lithium battery RB24V100 from RELiON Battery, when more power is needed it's supplied from the battery through the XTM 3500-24 and then the total power available becomes in 5,7 kVA thanks to the SMART-BOST feature.
Furthermore, villages as Alberguería de Arganan that are indeed at the endings of the Spanish electrical grid, suffer blackouts quite often because the electrical grid is overloaded and the power is not available at the end of the electrical line. Thanks to the energy stored in the battery and the inverter-charger, this technical trouble is now fixed because the new installed system acts as real-time backup power. Therefore, the electrical supply at this household is guaranteed.
Project outcome
Once the installation was finished, the customer could connect several electrical devices together without needing to consider the amount of power being used before having a blackout.
Having a look at the technical data recorded by the STUDER RCC-02 post installation, it was recorded the grid failed several times (blackouts), but the system reacted immediately avoiding the usual energy problems from the grid.
System components
Responsible company
Electricidad Samuel Domínguez
The challenge
This Project was carried out in a small village called Alberguería de Arganan, a Spanish rural area close to the border of Portugal.
In Spanish rural areas, it's really common for houses to not have enough power supplied by the grid to power all the loads houses have nowadays. That is due to the fact that those electrical installations were built some decades ago where, in the past, the need of powering loads was really low compared to today's needs (electrical household appliances in addition to the rest of the electrical devices in the home).
The solution
Power supplied by the electrical household to these households it's 220-230V, 50 Hz and 10A (single phase). The maximum power available it's 2,3 kVA. This is dependent upon the voltage and how stable the electrical grid is at any moment.
Why Studer
STUDER offers huge options for setting all the parameters up to allow the implementation of the required special applications and their needs. Furthermore, with the XCOM-LAN module, this household can be remotely monitored and in case of any failure the owner can be notified in real time.
The SMART-BOOST feature is the key to get more power than the grid can supply at any moment making you more independent of the electrical supplier.
Considering that nowadays there are lots of electrical devices in any household and sometimes most of them are connected at the same time, that load demand is much higher than the available power coming from the grid (only 2,2 kVA). Due to the load demand, usually you will see AC breakers falling down leaving the household in a blackout situation.
By adding the STUDER XTM 3500-24 and the lithium battery RB24V100 from RELiON Battery, when more power is needed it's supplied from the battery through the XTM 3500-24 and then the total power available becomes in 5,7 kVA thanks to the SMART-BOST feature.
Furthermore, villages as Alberguería de Arganan that are indeed at the endings of the Spanish electrical grid, suffer blackouts quite often because the electrical grid is overloaded and the power is not available at the end of the electrical line. Thanks to the energy stored in the battery and the inverter-charger, this technical trouble is now fixed because the new installed system acts as real-time backup power. Therefore, the electrical supply at this household is guaranteed.
Project outcome
Once the installation was finished, the customer could connect several electrical devices together without needing to consider the amount of power being used before having a blackout.
Having a look at the technical data recorded by the STUDER RCC-02 post installation, it was recorded the grid failed several times (blackouts), but the system reacted immediately avoiding the usual energy problems from the grid.
Spain: Charging point for electric vehicles, Elektra
El Proyecto
Elektra San Sebastián ha instalado un nuevo punto de recarga para la carga de vehículos eléctricos en el parking de sus instalaciones. El equipo instalado permite la carga en modo 1, 2 o 3 con conectores Schuko y Tipo II, permitiendo la carga simultánea de dos vehículos hasta 22KW de potencia, además de estar equipado con comunicaciones, contador de energía y sistema de acceso.
El sistema de recarga para vehículos eléctricos está alimentado por baterías de litio BYD, que se recargan a su vez mediante el excedente de la producción fotovoltaica de la instalación de autoconsumo existente y la red eléctrica en el periodo valle. Para la gestión de la carga y descarga de las baterías de litio, se utilizan 3 inversores/cargadores de la marca Studer.
Estos inversores están comunicados mediante RS232 con el sistema de monitorización implantado en Elektra y con la instalación de autoconsumo existente, por lo que cuando se detecta excedentes de producción solar este excedente es aprovechado para cargar las baterías. Si con este excedente no fuera necesario, se habilita la carga de las baterías por software durante el periodo valle.
Con la puesta en marcha de esta instalación, Elektra S.A. refuerza su apuesta por realizar una gestión eficiente de la energía, plasmada en el Sistema de Gestión de la Energía según la norma ISO 50001 desde el año 2015.
La Solución
Para este proyecto se optó por utilizar 3 inversores/cargadores XTH8000-48 de Studer, con comunicación CAN para la gestión de las baterías y comunicación RS-232 para la implementación de la instalación en el sistema de monitorización existente en Elektra. Estos inversores forman una red trifásica que permite gestionar la carga y descarga de las baterías de litio BYD y a su vez proporcionan los 22kW necesarios para la carga del vehículo eléctrico.
Por Qué STUDER
STUDER es una marca reconocida capaz de soportar importantes picos de arranque y que permite una perfecta comunicación con las baterías de litio BYD, además de contar con una gran robustez y fiabilidad.
Resultado del Proyecto
La solución ofrecida ha permitido cargar vehículos eléctricos con energía obtenida, bien de los excedentes de la instalación de autoconsumo existente o bien de periodos tarifarios donde la electricidad es más económica, permitiendo así una gestión más eficiente de la energía.
System components
3 x Inversor/cargador STUDER XTH8000-48
1 x Módulo de comunicación multi-protocolo STUDER Xcom-CAN
1 x Módulo de comunicación STUDER Xcom-232i
1 x Sistema de control STUDER RCC-02
2 x Baterías de Litio BYD de 13,8kW
Responsible company
Grupo Elektra
El Proyecto
Elektra San Sebastián ha instalado un nuevo punto de recarga para la carga de vehículos eléctricos en el parking de sus instalaciones. El equipo instalado permite la carga en modo 1, 2 o 3 con conectores Schuko y Tipo II, permitiendo la carga simultánea de dos vehículos hasta 22KW de potencia, además de estar equipado con comunicaciones, contador de energía y sistema de acceso.
El sistema de recarga para vehículos eléctricos está alimentado por baterías de litio BYD, que se recargan a su vez mediante el excedente de la producción fotovoltaica de la instalación de autoconsumo existente y la red eléctrica en el periodo valle. Para la gestión de la carga y descarga de las baterías de litio, se utilizan 3 inversores/cargadores de la marca Studer.
Estos inversores están comunicados mediante RS232 con el sistema de monitorización implantado en Elektra y con la instalación de autoconsumo existente, por lo que cuando se detecta excedentes de producción solar este excedente es aprovechado para cargar las baterías. Si con este excedente no fuera necesario, se habilita la carga de las baterías por software durante el periodo valle.
Con la puesta en marcha de esta instalación, Elektra S.A. refuerza su apuesta por realizar una gestión eficiente de la energía, plasmada en el Sistema de Gestión de la Energía según la norma ISO 50001 desde el año 2015.
La Solución
Para este proyecto se optó por utilizar 3 inversores/cargadores XTH8000-48 de Studer, con comunicación CAN para la gestión de las baterías y comunicación RS-232 para la implementación de la instalación en el sistema de monitorización existente en Elektra. Estos inversores forman una red trifásica que permite gestionar la carga y descarga de las baterías de litio BYD y a su vez proporcionan los 22kW necesarios para la carga del vehículo eléctrico.
Por Qué STUDER
STUDER es una marca reconocida capaz de soportar importantes picos de arranque y que permite una perfecta comunicación con las baterías de litio BYD, además de contar con una gran robustez y fiabilidad.
Resultado del Proyecto
La solución ofrecida ha permitido cargar vehículos eléctricos con energía obtenida, bien de los excedentes de la instalación de autoconsumo existente o bien de periodos tarifarios donde la electricidad es más económica, permitiendo así una gestión más eficiente de la energía.
Spain: Electrofil Oeste Distribución
El Proyecto
Electrofil Oeste Distribución, dentro de su departamento técnico Electrofil SUMA, diseña, calcula y suministra todos los equipos necesarios para ejecutar la instalación aislada fotovoltaica de 13kWp y 35kWh de acumulación.
La Solución
Se necesita ejecutar una instalación solar fotovoltaica totalmente aislada de la red, con apoyo de grupo electrógeno para dar suministro a los siguientes consumos:
- Casa de guardeses
- Sistema de climatización, bombeo y riego
- Edificio de Eventos
La potencia total demandada será de 15270W, considerando un coeficiente de simultaneidad de 0.6, tendremos una potencia pico máxima de 9160kW. El consumo total demandado por la instalación será de 38480kWh en los meses más desfavorables, los cuales dispondrán del apoyo del grupo electrógeno. El sistema propuesto nos permitirá una cobertura solar anual del 70%. La instalación está pensada para un uso continuado los 365 días del año y una gran vida útil.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones aisladas de sistemas de bombeo que sumado a su flexibilidad, robustez y garantía constituyen las principales razones para su elección. Además toda la instalación y sus valores son controlados remotamente con la App de STUDER.
Resultado del Proyecto
La ejecución del proyecto permitió satisfacer las necesidades de demanda que la propiedad necesita para su día a día, llevando a cabo una instalación sostenible y ecológica, además de independiente de cualquier compañía eléctrica. Todo ello con baterías de litio CEGASA.
System components
2 x Controladores de carga VS-120 STUDER
1 x Sistema de control RCC-02 STUDER
1 x Sistema de control XCOM-LAN STUDER
1 x Sistema de comunicación XCOM-CAN STUDER
2 x Inversor/Cargador XTENDER 6000/48 STUDER
30 x Paneles Solares de 435Wp
4 x Baterías Ebick Ultra 100 de 8.6kWh cada una de CEGASA
1 x Grupo Electrógeno de 19KVA
Responsible company
Electrofil Oeste Distribución
El Proyecto
Electrofil Oeste Distribución, dentro de su departamento técnico Electrofil SUMA, diseña, calcula y suministra todos los equipos necesarios para ejecutar la instalación aislada fotovoltaica de 13kWp y 35kWh de acumulación.
La Solución
Se necesita ejecutar una instalación solar fotovoltaica totalmente aislada de la red, con apoyo de grupo electrógeno para dar suministro a los siguientes consumos:
- Casa de guardeses
- Sistema de climatización, bombeo y riego
- Edificio de Eventos
La potencia total demandada será de 15270W, considerando un coeficiente de simultaneidad de 0.6, tendremos una potencia pico máxima de 9160kW. El consumo total demandado por la instalación será de 38480kWh en los meses más desfavorables, los cuales dispondrán del apoyo del grupo electrógeno. El sistema propuesto nos permitirá una cobertura solar anual del 70%. La instalación está pensada para un uso continuado los 365 días del año y una gran vida útil.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones aisladas de sistemas de bombeo que sumado a su flexibilidad, robustez y garantía constituyen las principales razones para su elección. Además toda la instalación y sus valores son controlados remotamente con la App de STUDER.
Resultado del Proyecto
La ejecución del proyecto permitió satisfacer las necesidades de demanda que la propiedad necesita para su día a día, llevando a cabo una instalación sostenible y ecológica, además de independiente de cualquier compañía eléctrica. Todo ello con baterías de litio CEGASA.
Spain: Instalación Aislada - Garaje en La Alberguería de Argañán
El Proyecto
Este proyecto ha sido ejecutado en un pequeño y precioso pueblo llamado La Alberguería de Argañán, una zona rural de España en la frontera con Portugal.
En zonas rurales de España es muy común ver como el coste del enganche a la red eléctrica suministrada por las compañías eléctricas es muy costoso. Todo esto sumado a un pago mínimo mensual a la compañía eléctrica, independientemente que no haya consumo eléctrico, alrededor de unos 20 euros mensuales, hace muy interesante este tipo de instalaciones con energías renovables.
En este caso, el consumo es prácticamente nulo, ya que simplemente es para abrir la puerta del garaje ciertos días al mes. A parte del enganche, que es un coste mayor a la inversión total de los equipos que forman la solución fotovoltaica, cada mes habría que pagar una cuota mínima a la compañía eléctrica que no se justifica.
La política del Gobierno Central en este ámbito es escasa para zonas rurales y hace que cada vez florezcan más instalaciones con energías renovables, haciendo a sus dueños ser independientes y ahorrar dinero.
La Solución
La instalación ha sido desarrollada para abrir la puerta eléctrica de un garaje unas dos veces por semana. Además de alimentarse una bombilla y un enchufe.
El alto coste que la compañía eléctrica le solicitaba al cliente por el enganche, y el pago mensual de una cuota de 20 euros, han hecho que el cliente se decantara por una solución aislada independiente de la red y absolutamente confiable.
Por Qué STUDER
STUDER ha sido elegido porque a través de un conocido, el cliente sabía que hay una instalación en un pueblo de al lado con un equipo STUDER instalado que lleva 21 años funcionando.
También la garantía de 10 años y la fabricación 100% Suiza bajo el marcado SWISS MADE le ha transmitido al cliente una confiabilidad total contra cualquier otro equipo que haya en el mercado.
Resultado del Proyecto
Una vez realizada la instalación, el cliente disfruta de energía en su garaje de forma independiente, y mucho mas económica.
También hay que resaltar que esta instalación es mucho más económica que haber realizado el enganche a la red eléctrica.
Otro factor muy importante es que la calidad de onda de los equipos STUDER evitan que la vida de los componentes electrónicos del motor que abre la puerta se reduzca comparado con la calidad de onda que llega a pueblos tan remotos como La Alberguería de Argañan.
Agradecimientos
Elektra: Suministrador del material eléctrico: https://www.grupoelektra.es
C&D Technologies and Trojan Battery Company: Especial mención a David Chambers por ceder la batería 24 AGM. https://www.trojanbattery.com
System components
1 x Inversor/cargador STUDER XTS 900-12
1 x Batería TROJAN 24 AGM, 84Ah en C100
1 x Regulador STECA PRS 1010
1 x Módulo Solar PEIMAR 150Wp
Responsible company
Studer Innotec SA
El Proyecto
Este proyecto ha sido ejecutado en un pequeño y precioso pueblo llamado La Alberguería de Argañán, una zona rural de España en la frontera con Portugal.
En zonas rurales de España es muy común ver como el coste del enganche a la red eléctrica suministrada por las compañías eléctricas es muy costoso. Todo esto sumado a un pago mínimo mensual a la compañía eléctrica, independientemente que no haya consumo eléctrico, alrededor de unos 20 euros mensuales, hace muy interesante este tipo de instalaciones con energías renovables.
En este caso, el consumo es prácticamente nulo, ya que simplemente es para abrir la puerta del garaje ciertos días al mes. A parte del enganche, que es un coste mayor a la inversión total de los equipos que forman la solución fotovoltaica, cada mes habría que pagar una cuota mínima a la compañía eléctrica que no se justifica.
La política del Gobierno Central en este ámbito es escasa para zonas rurales y hace que cada vez florezcan más instalaciones con energías renovables, haciendo a sus dueños ser independientes y ahorrar dinero.
La Solución
La instalación ha sido desarrollada para abrir la puerta eléctrica de un garaje unas dos veces por semana. Además de alimentarse una bombilla y un enchufe.
El alto coste que la compañía eléctrica le solicitaba al cliente por el enganche, y el pago mensual de una cuota de 20 euros, han hecho que el cliente se decantara por una solución aislada independiente de la red y absolutamente confiable.
Por Qué STUDER
STUDER ha sido elegido porque a través de un conocido, el cliente sabía que hay una instalación en un pueblo de al lado con un equipo STUDER instalado que lleva 21 años funcionando.
También la garantía de 10 años y la fabricación 100% Suiza bajo el marcado SWISS MADE le ha transmitido al cliente una confiabilidad total contra cualquier otro equipo que haya en el mercado.
Resultado del Proyecto
Una vez realizada la instalación, el cliente disfruta de energía en su garaje de forma independiente, y mucho mas económica.
También hay que resaltar que esta instalación es mucho más económica que haber realizado el enganche a la red eléctrica.
Otro factor muy importante es que la calidad de onda de los equipos STUDER evitan que la vida de los componentes electrónicos del motor que abre la puerta se reduzca comparado con la calidad de onda que llega a pueblos tan remotos como La Alberguería de Argañan.
Agradecimientos
Elektra: Suministrador del material eléctrico: https://www.grupoelektra.es
C&D Technologies and Trojan Battery Company: Especial mención a David Chambers por ceder la batería 24 AGM. https://www.trojanbattery.com
Spain: Instalación Aislada: El Txoko de Camaron
El Proyecto
Este proyecto ha sido ejecutado en un pequeño pueblo llamado La Alberguería de Argañán, una zona rural de España en la frontera con Portugal.
En zonas rurales de España es muy común ver como el coste del enganche a la red eléctrica suministrada por las compañías eléctricas es muy costoso y de irregular calidad. Pueblos preciosos como La Alberguería de Argañán sufren de muchos cortes eléctricos, especialmente en época de tormentas por la escasa inversión en la mejora de este tipo de infraestructuras.
La política del Gobierno Central en este ámbito es escasa para pueblos de zonas rurales y hace que cada vez florezcan más instalaciones con energías renovables, haciendo a sus dueños ser independientes de las empresas eléctricas pudiendo tener mejores soluciones que las ofrecidas hasta el día de hoy por dichas eléctricas.
La solucíon
El Txoko de Camaron es un recinto para recreo donde se pretende tener energía para alimentar luces, neveras, bombas de la piscina y consumos varios durante los períodos vacacionales que sus dueños pasan en el pueblo.
El alto coste que la compañía eléctrica le solicitaba al cliente y la irregular calidad de la red eléctrica hizo que el cliente se decantara por una solución aislada independiente de la red y absolutamente confiable.
Por Qué STUDER
STUDER fue elegido porque en una aplicación en la que el equipo XTS 900-12 se usa solo como inversor, la función BLO única en el mundo de STUDER, es capaz de proteger las baterías de descargas profundas continuadas.
También la garantía de 10 años y la fabricación 100% Suiza bajo el marcado SWISS MADE le ha transmitido al cliente una confiabilidad total contra cualquier otro equipo que haya en el mercado.
Resultado del Proyecto
Una vez realizada la instalación, el cliente disfruta de energía en su casa independiente de los posibles cortes, que son frecuentes, que hay en el suministro eléctrico.
También hay que resaltar que esta instalación es mucho más económica que haber realizado el enganche a la red eléctrica.
Otro factor muy importante es que la calidad de onda de los equipos STUDER evitan que la vida de los equipos electrónicos se reduzca comparado con la calidad de onda que llega a pueblos tan remotos como La Alberguería de Argañan.
System components
1 x Inversor/cargador STUDER XTS 900-12
1 x Sistema de control STUDER RCC-02
1 x Regulador MPPT QMax
2 x Batería de gel Sonnenschein Solarblock 330Ah en C100
1 x Módulo Solar Peimar 330Wp
Responsible company
Studer Innotec SA
El Proyecto
Este proyecto ha sido ejecutado en un pequeño pueblo llamado La Alberguería de Argañán, una zona rural de España en la frontera con Portugal.
En zonas rurales de España es muy común ver como el coste del enganche a la red eléctrica suministrada por las compañías eléctricas es muy costoso y de irregular calidad. Pueblos preciosos como La Alberguería de Argañán sufren de muchos cortes eléctricos, especialmente en época de tormentas por la escasa inversión en la mejora de este tipo de infraestructuras.
La política del Gobierno Central en este ámbito es escasa para pueblos de zonas rurales y hace que cada vez florezcan más instalaciones con energías renovables, haciendo a sus dueños ser independientes de las empresas eléctricas pudiendo tener mejores soluciones que las ofrecidas hasta el día de hoy por dichas eléctricas.
La solucíon
El Txoko de Camaron es un recinto para recreo donde se pretende tener energía para alimentar luces, neveras, bombas de la piscina y consumos varios durante los períodos vacacionales que sus dueños pasan en el pueblo.
El alto coste que la compañía eléctrica le solicitaba al cliente y la irregular calidad de la red eléctrica hizo que el cliente se decantara por una solución aislada independiente de la red y absolutamente confiable.
Por Qué STUDER
STUDER fue elegido porque en una aplicación en la que el equipo XTS 900-12 se usa solo como inversor, la función BLO única en el mundo de STUDER, es capaz de proteger las baterías de descargas profundas continuadas.
También la garantía de 10 años y la fabricación 100% Suiza bajo el marcado SWISS MADE le ha transmitido al cliente una confiabilidad total contra cualquier otro equipo que haya en el mercado.
Resultado del Proyecto
Una vez realizada la instalación, el cliente disfruta de energía en su casa independiente de los posibles cortes, que son frecuentes, que hay en el suministro eléctrico.
También hay que resaltar que esta instalación es mucho más económica que haber realizado el enganche a la red eléctrica.
Otro factor muy importante es que la calidad de onda de los equipos STUDER evitan que la vida de los equipos electrónicos se reduzca comparado con la calidad de onda que llega a pueblos tan remotos como La Alberguería de Argañan.
Spain: Instalación fotovoltaica aislada para vivienda en Tudela
El Proyecto
Hace ya varios años, el dueño de la finca decidió cambiar su modo de vida y retirarse a vivir al campo buscando una mayor tranquilidad, un mayor contacto con el entorno natural de la zona y cumplir con su proposito de respecto con el medio ambiente. Durante este tiempo ha ido desarrollando una serie de trabajos de adaptación de la hacienda, en vías de posibilitar un mayor autoabastecimiento, realizando por ello distintas inversiones en agricultura y ganadería ecológica.
Fruto de esta idea, ha sido necesario suplir las carencias energéticas de la finca situada en un entorno aislado de las infraestructuras convencionales. Por ello, a fin de garantizar el abastecimiento eléctrico de la finca, se ha implementado este sistema renovable que a su vez se acomoda a la perfeción con su idea de sostenibilidad.
La solucíon
La situación de la finca está aislada de las redes convencionales de abastecimiento eléctrico, a lo que se suma la imposibilidad legal de llevarse a cabo dichas opciones en este entorno y en la clara idea del cliente de evitar, todo lo posible, el empleo de combustibles fósiles. Es por ello, que se ha buscado la alternativa del uso de energías renovables con acumulación, en este caso de tipo fotovoltaico.
Por Qué STUDER
Principalmente por la garantía y seguridad en el servicio, en base a los altos criterios de Calidad y de Innovación que esta empresa “plasma” en sus productos. Algo que es totalmente vital en todas aquellas instalaciones que abastecen actividades o situaciones de mayor afección en caso de averías o anomalías.
Resultado del Proyecto
El resultado del proyecto es disponer de una finca aislada de la red eléctrica, que es autosuficiente, sin tener que pagar a la compañía y, sobre todo, el haber cumplido con un objetivo de respeto medio ambiental con el entorno desde el punto de vista de la generación energética.
System components
1 x Inversor/cargador STUDER XTH 6000-48
1 x Regulador solar MPPT STUDER VarioString VS-70
1 x Regulador solar MPPT STUDER VarioTrack VT-65
1 x Gestor de la instalación STUDER RCC-02
1 x Plataforma “pasarela” STUDER Xcom-CAN
1 x Sistema comunicación remota STUDER Xcom-GSM
1 x Batería de litio (LiFePO4) BYD B-Box Pro 10.0
11 x Módulo solar REC mod. Twim Peak REC350TP-2S
4 x Módulo solar REC mod. Twim Peak REC270TP
1 x Estructura de suelo SOLARSTEM AF-FLAT 30º doble
1 x Estructura de cubierta inclinada APLITECH
Responsible company
CAJ ECOENER
El Proyecto
Hace ya varios años, el dueño de la finca decidió cambiar su modo de vida y retirarse a vivir al campo buscando una mayor tranquilidad, un mayor contacto con el entorno natural de la zona y cumplir con su proposito de respecto con el medio ambiente. Durante este tiempo ha ido desarrollando una serie de trabajos de adaptación de la hacienda, en vías de posibilitar un mayor autoabastecimiento, realizando por ello distintas inversiones en agricultura y ganadería ecológica.
Fruto de esta idea, ha sido necesario suplir las carencias energéticas de la finca situada en un entorno aislado de las infraestructuras convencionales. Por ello, a fin de garantizar el abastecimiento eléctrico de la finca, se ha implementado este sistema renovable que a su vez se acomoda a la perfeción con su idea de sostenibilidad.
La solucíon
La situación de la finca está aislada de las redes convencionales de abastecimiento eléctrico, a lo que se suma la imposibilidad legal de llevarse a cabo dichas opciones en este entorno y en la clara idea del cliente de evitar, todo lo posible, el empleo de combustibles fósiles. Es por ello, que se ha buscado la alternativa del uso de energías renovables con acumulación, en este caso de tipo fotovoltaico.
Por Qué STUDER
Principalmente por la garantía y seguridad en el servicio, en base a los altos criterios de Calidad y de Innovación que esta empresa “plasma” en sus productos. Algo que es totalmente vital en todas aquellas instalaciones que abastecen actividades o situaciones de mayor afección en caso de averías o anomalías.
Resultado del Proyecto
El resultado del proyecto es disponer de una finca aislada de la red eléctrica, que es autosuficiente, sin tener que pagar a la compañía y, sobre todo, el haber cumplido con un objetivo de respeto medio ambiental con el entorno desde el punto de vista de la generación energética.
Spain: Museo Insolectric
El Proyecto
El objetivo principal de esta instalación es la de generar energía limpia y sostenible para un museo con cafetería, donde circulan aproximadamente unas dos mil personas por día, situado en un medio rural turístico y protegido por las autoridades competentes.
La Solución
Esta fuente de energía renovable suministra energía esencial para receptores eléctricos trifásicos de 400vac, como los sistemas de refrigeración y climatización del local del museo, grupos de presión de agua, cafetera profesional, congelador industrial alimentario, etc.
Del mismo sistema eléctrico se administra energía para receptores eléctricos monofásicos 230vac como alumbrado público parking, punto de recarga para coches eléctricos, sistemas de video vigilancia, alumbrado interior del museo, y electrodomésticos de cafetería, sistemas informáticos, etc.
Por Qué STUDER
Todo el diseño se ejecutó con material STUDER por tres criterios esenciales.
La fiabilidad del producto, la alta eficiencia de los equipos STUDER en rendimiento de funcionalidad en condiciones extrema de alta y baja temperaturas, y la rentabilidad a corto y medio plazo. Gracias a la robustez de los equipos STUDER hace que se reduzca el coste de la instalación y de los mantenimientos innecesarios.
Resultado del Proyecto
Se suministra energía limpia para el complejo del museo, el alumbrado del parking público y un punto de recarga de coches eléctricos.
System components
Componente por sistema
144 x módulos solares de 260W
8 x Reguladores MPPT VT-80 Studer
6 x inversores/cargadores XTM 4000-48 Studer
1 x BSP 500 Studer
1 x Monitoreo remote Xcom-LAN Studer
1 x BTS-01
1 x RCC-02
24 x elementos estacionarios de 1000Ah en C20
Responsible company
Insolectric, S.L.
El Proyecto
El objetivo principal de esta instalación es la de generar energía limpia y sostenible para un museo con cafetería, donde circulan aproximadamente unas dos mil personas por día, situado en un medio rural turístico y protegido por las autoridades competentes.
La Solución
Esta fuente de energía renovable suministra energía esencial para receptores eléctricos trifásicos de 400vac, como los sistemas de refrigeración y climatización del local del museo, grupos de presión de agua, cafetera profesional, congelador industrial alimentario, etc.
Del mismo sistema eléctrico se administra energía para receptores eléctricos monofásicos 230vac como alumbrado público parking, punto de recarga para coches eléctricos, sistemas de video vigilancia, alumbrado interior del museo, y electrodomésticos de cafetería, sistemas informáticos, etc.
Por Qué STUDER
Todo el diseño se ejecutó con material STUDER por tres criterios esenciales.
La fiabilidad del producto, la alta eficiencia de los equipos STUDER en rendimiento de funcionalidad en condiciones extrema de alta y baja temperaturas, y la rentabilidad a corto y medio plazo. Gracias a la robustez de los equipos STUDER hace que se reduzca el coste de la instalación y de los mantenimientos innecesarios.
Resultado del Proyecto
Se suministra energía limpia para el complejo del museo, el alumbrado del parking público y un punto de recarga de coches eléctricos.
Spain: Telecom ITELAZPI
El Proyecto
ITELAZPI es una empresa pública dirigida a la prestación de servicios portadores de los de radio y televisión y servicios de comunicaciones públicas, así como a la gestión de las infraestructuras públicas de telecomunicaciones; todo ello, desde la actualidad tecnológica, la calidad en el servicio y la protección del medio natural.
La responsabilidad corporativa de Itelazpi, tiene como fin ser una empresa responsable, para ello utiliza en algunos casos soluciones con energías renovables.
Como se puede ver en el Decálogo de Compromisos de Itelazpi, uno de los cinco objetivos estratégicos de la empresa es respetar su entorno y cuidar el medio ambiente, es decir ser una empresa responsable.
Es por ello que aplica la solución propuesta por la empresa instaladora Ekain Taldea con equipos de fabricantes que aportan las mayores garantías en el mercado para electrificación de lugares aislados.
En los repetidores de Itelazpi se han implementado tanto aerogeneradores ENAIR como BORNAY, utilizando sus equipos en combinación con STUDER.
La Solución
Para cumplir con el objetivo de disminuir su consumo de diésel, se han instalado baterías de plomo-ácido de ciclo profundo tecnología OPzS, con lo cual se ha reducido las horas de funcionamiento de los generadores diésel.
Esto ha sido posible gracias a acumular la energía producida por los aerogeneradores y por paneles fotovoltaicos. Solo en caso de no haber producción eólica o fotovoltaica se recurre al consumo de energía producida con diésel.
Por Qué STUDER
STUDER es una marca reconocida en sistemas de soluciones para instalaciones remotas de telecomunicaciones por la robustez de sus equipos. Una de las razones más importantes es que los equipos ofrecen un nivel de incidencias mínimo. Ekain Taldea mantenedor y proyectista, es a su vez Servicio Técnico de Studer por lo que la solvencia y rapidez en la respuesta están garantizadas.
Resultado del Proyecto
La solución ofrecida, basada en la acumulación directa a baterías, evita el uso de generadores de gasoleo. En algunos casos, según el repetidor se da una reducción de consumo de gasoleo entre 75% y el 100%.
System components
1 x Inversor / Cargador de 4000W STUDER.
1 x Aerogenerador de 3.5 kW a 48V
12 x Paneles Solares de 250W
1 x Grupo electrógeno de 10 kW automático.
24 x Elementos de baterías estacionarias OPzV de 1200Ah ó 2200Ah
1 x Regulador solar de 60Ah.
1 x Caseta prefabricada para albergar las baterías y controladores e inversor
Responsible company
EKAIN TALDEA
El Proyecto
ITELAZPI es una empresa pública dirigida a la prestación de servicios portadores de los de radio y televisión y servicios de comunicaciones públicas, así como a la gestión de las infraestructuras públicas de telecomunicaciones; todo ello, desde la actualidad tecnológica, la calidad en el servicio y la protección del medio natural.
La responsabilidad corporativa de Itelazpi, tiene como fin ser una empresa responsable, para ello utiliza en algunos casos soluciones con energías renovables.
Como se puede ver en el Decálogo de Compromisos de Itelazpi, uno de los cinco objetivos estratégicos de la empresa es respetar su entorno y cuidar el medio ambiente, es decir ser una empresa responsable.
Es por ello que aplica la solución propuesta por la empresa instaladora Ekain Taldea con equipos de fabricantes que aportan las mayores garantías en el mercado para electrificación de lugares aislados.
En los repetidores de Itelazpi se han implementado tanto aerogeneradores ENAIR como BORNAY, utilizando sus equipos en combinación con STUDER.
La Solución
Para cumplir con el objetivo de disminuir su consumo de diésel, se han instalado baterías de plomo-ácido de ciclo profundo tecnología OPzS, con lo cual se ha reducido las horas de funcionamiento de los generadores diésel.
Esto ha sido posible gracias a acumular la energía producida por los aerogeneradores y por paneles fotovoltaicos. Solo en caso de no haber producción eólica o fotovoltaica se recurre al consumo de energía producida con diésel.
Por Qué STUDER
STUDER es una marca reconocida en sistemas de soluciones para instalaciones remotas de telecomunicaciones por la robustez de sus equipos. Una de las razones más importantes es que los equipos ofrecen un nivel de incidencias mínimo. Ekain Taldea mantenedor y proyectista, es a su vez Servicio Técnico de Studer por lo que la solvencia y rapidez en la respuesta están garantizadas.
Resultado del Proyecto
La solución ofrecida, basada en la acumulación directa a baterías, evita el uso de generadores de gasoleo. En algunos casos, según el repetidor se da una reducción de consumo de gasoleo entre 75% y el 100%.
Spain: Vehiculos/Autocaravana
El Proyecto
Este proyecto ha sido ejecutado por un usuario final que ha adquirido una autocaravana y necesitaba tener 220Vac dentro del vehículo cuando está en marcha.
Estas autocaravanas están preparadas para tener 220Vac internamente cuando se recibe corriente eléctrica desde el exterior al estar estacionadas, vía una toma de corriente externa que se acopla a la toma de la autocaravana.
Este tipo de vehículos no tienen ningún inversor de serie que en marcha pueda generar 220Vac desde la batería auxiliar de servicios para alimentar equipos electrónicos.
Por Qué STUDER
STUDER ha sido elegido por la calidad de su onda ya que es reconocida como la mejor del mercado, haciendo que la vida de los componentes electrónicos no se vea reducida. Y también por la garantía que ofrece de 10 años
Otro de los factores es su inapreciable nivel de decibelios que emite al estar funcionando algo que es muy importante por estar dentro del habitáculo donde se descansa.
El consumo del equipo en stand-by es mínimo (1W) y teniendo en cuenta que estos vehículos disponen de baterías no muy grandes en capacidad y que están ciertos periodos del año sin utilizarse, esto permite que no se descargue la batería en los periodos que el vehículo no se este usando y este resguardado del sol de manera rápida como ocurre con otros equipos que tienen un consumo muy elevado en stand-by.
La Solución
La instalación ha sido desarrollada para poder recargar equipos como teléfonos móviles, ordenadores portátiles y demás equipos electrónicos.
Por otra parte, gracias a la consola RCC-02, se puede monitorear el estado de la batería con precisión exacta, permitiendo ser mucho mas cuidadoso con la batería.
Además, se ha añadido un panel fotovoltaico para cargar la batería de servicios del vehículo por medio de un regulador de Morningstar.
Resultado del Proyecto
Una vez realizada la instalación, el cliente disfruta de una toma de tensión de 220Vac en movimiento que además es energía proveniente del panel solar que hay instalado en el techo cuando se dispone de sol.
Es una comodidad que el cliente requería y que permite una solución extra al vehículo.
System components
1 x Inversor/cargador STUDER XTS 900-12
1 x Consola RCC-02 STUDER
1 x Batería AGM, 110Ah en C20
1 x Regulador Morningstar de 10
1 x Módulo Solar 180Wp
Responsible company
Grupo ELEKTRA
El Proyecto
Este proyecto ha sido ejecutado por un usuario final que ha adquirido una autocaravana y necesitaba tener 220Vac dentro del vehículo cuando está en marcha.
Estas autocaravanas están preparadas para tener 220Vac internamente cuando se recibe corriente eléctrica desde el exterior al estar estacionadas, vía una toma de corriente externa que se acopla a la toma de la autocaravana.
Este tipo de vehículos no tienen ningún inversor de serie que en marcha pueda generar 220Vac desde la batería auxiliar de servicios para alimentar equipos electrónicos.
Por Qué STUDER
STUDER ha sido elegido por la calidad de su onda ya que es reconocida como la mejor del mercado, haciendo que la vida de los componentes electrónicos no se vea reducida. Y también por la garantía que ofrece de 10 años
Otro de los factores es su inapreciable nivel de decibelios que emite al estar funcionando algo que es muy importante por estar dentro del habitáculo donde se descansa.
El consumo del equipo en stand-by es mínimo (1W) y teniendo en cuenta que estos vehículos disponen de baterías no muy grandes en capacidad y que están ciertos periodos del año sin utilizarse, esto permite que no se descargue la batería en los periodos que el vehículo no se este usando y este resguardado del sol de manera rápida como ocurre con otros equipos que tienen un consumo muy elevado en stand-by.
La Solución
La instalación ha sido desarrollada para poder recargar equipos como teléfonos móviles, ordenadores portátiles y demás equipos electrónicos.
Por otra parte, gracias a la consola RCC-02, se puede monitorear el estado de la batería con precisión exacta, permitiendo ser mucho mas cuidadoso con la batería.
Además, se ha añadido un panel fotovoltaico para cargar la batería de servicios del vehículo por medio de un regulador de Morningstar.
Resultado del Proyecto
Una vez realizada la instalación, el cliente disfruta de una toma de tensión de 220Vac en movimiento que además es energía proveniente del panel solar que hay instalado en el techo cuando se dispone de sol.
Es una comodidad que el cliente requería y que permite una solución extra al vehículo.
Spain: Vodafone telecom project
The challenge
Vodafone has made it one of their strategic business objectives to be a responsible company by taking care of and respecting the environment. One important step in this direction was to start using renewable energy in the electrification of their base stations and thereby reducing the use of diesel generators.
The solution
To reduce the diesel consumption, wind turbine manufacturer ENAIR suggested an energy system solution with battery storage of the generated renewable energy. The solution, based on the direct accumulation of batteries, comprise wind turbines, PV panels, deep-cycle lead-acid batteries with OPzS technology and power electronics from Studer Innotec.
With this system, the diesel generator is only used if there is no wind nor photovoltaic production and the batteries are discharged.
Why Studer
Studer is a highly recognized brand for renewable energy system solutions in remote telecommunication installations.
Besides its outstanding reliability, Studer offers a unique feature: the “battery priority function”, that allows using renewable energy as much as possible over costly and polluting generators.
Project outcome
The new renewable energy solution has successfully reduced the operating time of the diesel generators, saving 85% of diesel consumption. The payback period is about five years for a system that has a durability of about 25 years.
All this has been made possible thanks to the accumulation of energy produced by ENAIR wind turbines and photovoltaic panels.
System components
Responsible company
Enair
The challenge
Vodafone has made it one of their strategic business objectives to be a responsible company by taking care of and respecting the environment. One important step in this direction was to start using renewable energy in the electrification of their base stations and thereby reducing the use of diesel generators.
The solution
To reduce the diesel consumption, wind turbine manufacturer ENAIR suggested an energy system solution with battery storage of the generated renewable energy. The solution, based on the direct accumulation of batteries, comprise wind turbines, PV panels, deep-cycle lead-acid batteries with OPzS technology and power electronics from Studer Innotec.
With this system, the diesel generator is only used if there is no wind nor photovoltaic production and the batteries are discharged.
Why Studer
Studer is a highly recognized brand for renewable energy system solutions in remote telecommunication installations.
Besides its outstanding reliability, Studer offers a unique feature: the “battery priority function”, that allows using renewable energy as much as possible over costly and polluting generators.
Project outcome
The new renewable energy solution has successfully reduced the operating time of the diesel generators, saving 85% of diesel consumption. The payback period is about five years for a system that has a durability of about 25 years.
All this has been made possible thanks to the accumulation of energy produced by ENAIR wind turbines and photovoltaic panels.
Switzerland:Off-grid system at the Hörnlihütte
The Challenge
The Hörnlihütte is a Swiss mountain cabin situated at 3260m altitude directly at the foot of Matterhorn, the famous pyramid-shaped mountain. It constitutes the starting point for ascending the mountain and also serves as a refuge during changes in weather conditions.
First built in 1880 it recently underwent a major renovation to guarantee its sustainable development of energy and water supply and wastewater management. At this altitude there is no utility grid available. The only way to guarantee a reliable power supply is to create it yourself.
The Solution
Before transformation, the mountain cabin was neither insulated nor heated and received its energy supply from a diesel generator. The new 72kVA off-grid energy supply system in three-phase with a 30kVA diesel generator as backup, guarantees a sustainable, efficient and trouble-free operation of the mountain-cabin. The roof surfaces exposed to maximum sunlight is fitted with photovoltaic modules to produce electricity and the facade is equipped with solar thermal collectors to generate hot water.
The system performance can be increased to 105kW with CHP (Cogeneration Heat and Power).
Why Studer
Changing batteries, supplying diesel and maintenance work at high altitude is extremely costly. The Xtender inverter/charger is controlling the generator, thus optimizing diesel consumption and runtime. Its fully automatic charge management ensures an optimal battery charge which significantly prolongs the battery lifetime. Strong temperature fluctuations on the solar generator surface and snow reflections greatly affect the solar generator's operating voltage. The VarioString MPPT solar charge controller always handles the high voltage field precisely and with high efficiency.
Project outcome
The new renewable energy system provides reliable electrification 24/7 for the mountaineers and tourists visiting the mountain cabin from June until September. Hörnlihütte's sustainable development and modernisation was carried out to meet today's requirements for eco-friendliness, safety, hygiene and functionality. The water collection and supply have been improved and safeguarded. The new wastewater treatment system purifies and reuses the water multiple times.
The modernised cabin contains 120 beds, WiFi, a community room for 130 persons, toilets and showers on each floor.
System components
Responsible company
Solarbau Lowel GMBH
The Challenge
The Hörnlihütte is a Swiss mountain cabin situated at 3260m altitude directly at the foot of Matterhorn, the famous pyramid-shaped mountain. It constitutes the starting point for ascending the mountain and also serves as a refuge during changes in weather conditions.
First built in 1880 it recently underwent a major renovation to guarantee its sustainable development of energy and water supply and wastewater management. At this altitude there is no utility grid available. The only way to guarantee a reliable power supply is to create it yourself.
The Solution
Before transformation, the mountain cabin was neither insulated nor heated and received its energy supply from a diesel generator. The new 72kVA off-grid energy supply system in three-phase with a 30kVA diesel generator as backup, guarantees a sustainable, efficient and trouble-free operation of the mountain-cabin. The roof surfaces exposed to maximum sunlight is fitted with photovoltaic modules to produce electricity and the facade is equipped with solar thermal collectors to generate hot water.
The system performance can be increased to 105kW with CHP (Cogeneration Heat and Power).
Why Studer
Changing batteries, supplying diesel and maintenance work at high altitude is extremely costly. The Xtender inverter/charger is controlling the generator, thus optimizing diesel consumption and runtime. Its fully automatic charge management ensures an optimal battery charge which significantly prolongs the battery lifetime. Strong temperature fluctuations on the solar generator surface and snow reflections greatly affect the solar generator's operating voltage. The VarioString MPPT solar charge controller always handles the high voltage field precisely and with high efficiency.
Project outcome
The new renewable energy system provides reliable electrification 24/7 for the mountaineers and tourists visiting the mountain cabin from June until September. Hörnlihütte's sustainable development and modernisation was carried out to meet today's requirements for eco-friendliness, safety, hygiene and functionality. The water collection and supply have been improved and safeguarded. The new wastewater treatment system purifies and reuses the water multiple times.
The modernised cabin contains 120 beds, WiFi, a community room for 130 persons, toilets and showers on each floor.
Venezuela: Respaldo energético a servidores de Computación
El Proyecto
Gases Unidos, es una empresa que recarga y suministra tanques de oxígeno para uso médico. Cuenta con varias sedes en el país que suministran el preciado gas en otros estados del país. La operación administrativa de cada sede depende de los servidores ubicados en la sede principal.
Los inesperados cortes de energía eléctrica en la zona hacen que la operación de la sede y sus filiales se vea interrumpida. Por otro lado, la solución de sistemas electrógenos se descartó debido a la escasez y no confiabilidad del suministro de combustible en el país para su funcionamiento.
La propuesta fue instalar un sistema de respaldo con tecnología de batería de litio para dar respaldo energía tipo back up, a los servidores de la compañía, y así permitir la comunicación de sus servidores y la continuidad administrativa de las otras sedes.
La Solución
Para permitir que los servidores de computación pudieran mantener su funcionamiento ante los cortes de energía comunes en la zona y permitir la operatividad administrativa de la sede y sus filiales, se instaló un sistema de respaldo con 1 batería de litio de 3,5 kWh y 1 inversor Studer para redes de 120V y 48 voltios de batería, brindando así una autonomía de 3:30 horas. Además, se incluyó en el sistema la posibilidad de visualización y operación remota a través del dispositivo XCOM-LAN de STUDER, el cual permitirá al usuario siempre estar informado del status y operación del sistema de respaldo.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones. El monitoreo, su flexibilidad, robustez y garantía constituyen las principales razones para su elección.
Resultado del Proyecto
La instalación del nuevo sistema de respaldo usando Studer y Pylontech permitió dar seguridad de continuidad operativa administrativa en al menos 10:30 horas, ante los inesperados cortes de energía eléctrica de la zona, con una solución limpia y de poco espacio, permitiendo a las otras sedes dependientes continuar con sus operaciones.
System components
1 x inversor XTM-2600-48-01 STUDER
1 x Sistema de control RCC-02 STUDER
1 x componente de compatibilidad con baterías de litio XCOM-CAN STUDER
1 x componente de comunicación a internet XCOM-LAN STUDER
3 x batería de litio de 74 Ah Pylontech
Responsible company
Enersolar Ingeniería
El Proyecto
Gases Unidos, es una empresa que recarga y suministra tanques de oxígeno para uso médico. Cuenta con varias sedes en el país que suministran el preciado gas en otros estados del país. La operación administrativa de cada sede depende de los servidores ubicados en la sede principal.
Los inesperados cortes de energía eléctrica en la zona hacen que la operación de la sede y sus filiales se vea interrumpida. Por otro lado, la solución de sistemas electrógenos se descartó debido a la escasez y no confiabilidad del suministro de combustible en el país para su funcionamiento.
La propuesta fue instalar un sistema de respaldo con tecnología de batería de litio para dar respaldo energía tipo back up, a los servidores de la compañía, y así permitir la comunicación de sus servidores y la continuidad administrativa de las otras sedes.
La Solución
Para permitir que los servidores de computación pudieran mantener su funcionamiento ante los cortes de energía comunes en la zona y permitir la operatividad administrativa de la sede y sus filiales, se instaló un sistema de respaldo con 1 batería de litio de 3,5 kWh y 1 inversor Studer para redes de 120V y 48 voltios de batería, brindando así una autonomía de 3:30 horas. Además, se incluyó en el sistema la posibilidad de visualización y operación remota a través del dispositivo XCOM-LAN de STUDER, el cual permitirá al usuario siempre estar informado del status y operación del sistema de respaldo.
Por Qué STUDER
STUDER brinda la fiabilidad que los clientes exigen para instalaciones. El monitoreo, su flexibilidad, robustez y garantía constituyen las principales razones para su elección.
Resultado del Proyecto
La instalación del nuevo sistema de respaldo usando Studer y Pylontech permitió dar seguridad de continuidad operativa administrativa en al menos 10:30 horas, ante los inesperados cortes de energía eléctrica de la zona, con una solución limpia y de poco espacio, permitiendo a las otras sedes dependientes continuar con sus operaciones.
Argentina: Agroindustria en Cabos
Argentina: Electrificación rural, Pueblo Olaroz Chico
Argentina: Vivienda Aislada
Solar applications